ML13323A384

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Repts 50-361/79-30 & 50-362/79-28 on 791101-30.No Noncompliance Noted
ML13323A384
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 01/04/1980
From: Spencer G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Papay L
SOUTHERN CALIFORNIA EDISON CO.
Shared Package
ML13323A385 List:
References
NUDOCS 8002070451
Download: ML13323A384 (2)


See also: IR 05000361/1979030

Text

og

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION V

1990 N. CALIFORNIA BOULEVARD

'

SUITE 202, WALNUT CREEK PLAZA

4.

WALNUT CREEK, CALIFORNIA 94596

JAN

4 8

Docket Nos.f5

(0-362-

Southern California Edison Company

P.O. Box 800

2244 Walnut Grove Avenue

Rosemead, California 91770

Attention:

Dr. L. T. Papay

Vice President, Advanced Engineering

Gentlemen:

.

Subject:

NRC Inspection at San Onofre Units 2 and 3

This refers to the inspections conducted by Mr. R. J. Pate of this

office during the period November 1-30, 1979 of activities authorized by

NRC Construction Permit Nos. CPPR-97 and 98, and to the discussions of

his findings held with Mr. D. E. Nunn and other members of your staff on

November 2, 9 and 30, 1979.

Areas examined during this inspection are described in the enclosed

inspection report.. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, inter

views with personnel, and observations by the inspector. No items of

noncompliance with NRC requirements were identified within the scope of

this inspection.

In accordance with Section 2.790 of the NRC's "Rules of Practice,"

Part 2, Title 10 Code of Federal Regulations, a copy of this letter and

the enclosed inspection report will be placed in the NRC's Public

Document Room. If this report contains any information that you believe

to be proprietary, it is necessary that you submit a written application

to this office, within 20 days of the date of this letter, requesting

that such information be withheld from public disclosure. The application

must include a full statement of the reasons why it is claimed that the

information is proprietary. The application should be prepared so that

8 00 2070

(

Southern California Edison Company

-2

any proprietary information identified is contained in an enclosure to

the application since the application without the enclosure will also be

placed in the Public Document Room. If we do not hear from you in this

regard within the specified period, the report will be placed in the

Public Document Room.

Should you have any questions concerning this inspection, we will be

glad to discuss them.with you.

Sincerely,

G. S. Spei cer, Chief

Reactor Construction and

Engineering Support Branch

Enclosure:

IE Inspection Report

Nos. 50-361/79-30

50-362/79-28

cc w/o enclosure:

R. Dretch, Vice President

Nuclear Engineering & Operations SCE