ML13322A920
| ML13322A920 | |
| Person / Time | |
|---|---|
| Site: | San Onofre |
| Issue date: | 07/03/1980 |
| From: | Crews J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| To: | Papay L SOUTHERN CALIFORNIA EDISON CO. |
| Shared Package | |
| ML13322A919 | List: |
| References | |
| NUDOCS 8008110110 | |
| Download: ML13322A920 (2) | |
See also: IR 05000206/1980016
Text
vpIREGu,
p
le
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION V
o
A
1990 N.
CALIFORNIA BOULEVARD
SUITE 202, WALNUT CREEK PLAZA
WALNUT CREEK, CALIFORNIA 94596
JUL 3
1980
Docket No. 50-206
Southern California Edison Company
P. 0. Box 800
2244 Walnut Grove Avenue
Rosemead, California 91770
Attention:
Dr. L. T. Papay
Vice President, Advanced Engineering
Gentlemen:
Subject:
NRC Inspection -
San Onofre Unit 1
This refers to the inspection conducted by Messrs. L. Miller and R. Pate
of this office on May 5-30, 1980, of activities authorized by NRC License
No. DPR-13, and to the discussion of our findings held by Mr. Miller with
Mr. Brunet and other representatives of the Southern California Edison
Company at the conclusion of the inspection.
Areas examined during this inspection are described in the enclosed inspection
report. Within these areas, the inspection consisted of selective examinations
of procedures and representative records, interviews with personnel, and obser
vations by the inspectors.
Based on the results of this inspection, it appears that one of your activities
was not conducted in full compliance with NRC requirements, as set forth in the
Notice of Violation, enclosed herewith as Appendix A. This item of noncompliance
has been categorized into a level as described in our correspondence to all NRC
licensees dated December 31, 1974.
This notice is-sent to you pursuant to the provisions of Section 2.201, of the
NRC's "Rules of Practice," Part 2, Title 10, Code of Federal Regulations.
Section 2.201 requires you to submit to this office within twenty (20) days
of your receipt of this notice, a written statement or explanation in reply
including (1) corrective steps which have been taken by you and the results
achieved; (2) corrective steps which will be taken to avoid further violations;
and (3) the date when full compliance will be achieved.
Southern California Edison Company
-2-
JUL 3 1980
During this inspection, it was also found that one of your activities appeared
to deviate from generally accepted industry standards, as set forth in the
Notice of Deviation enclosed herewith as Appendix B. Please submit to this
office, within twenty (20)
days of your receipt of this notice, a written state
ment or explanation in reply including the cause of the deviation and the steps
you plan to take to assure timely implementation and completion of corrective
actions. Your written reply should include the date(s) when your corrective
action(s) were or will be completed.
In accordance with Section 2.790 of the NRC's "Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room. If this
report contains any information that you believe to be proprietary, it is
necessary that you submit a written application to this office, within 20 days
of the date of this letter, requesting that such information be withheld from
public disclosure. The application must include a full statement of the reasons
why it is claimed that the information is proprietary. The application should
be prepared so that any proprietary information identified is contained in an
enclosure to the application, since the application without the enclosure will
also be placed in the Public Document Room. If we do not hear from you in this
regard within the specified period, the report will be placed in the Public
Document Room.
Should you have any questions concerning this inspection we will be glad to
discuss them with you.
Sincerely,
.6re
s, Chief
eactor Operations and Nuclear
Support Branch
Enclosures:
1. Notice of Violation - APPENDIX A
2. Notice of Deviation - APPENDIX B
3. IE Inspection Report
No. 50-206/80-16
cc w/o Enclosure 3:
R. Dietch, Vice President
Nuclear Engineering & Operations, SCE
J. M. Curran, SCE