ML13317A793

From kanterella
Jump to navigation Jump to search
Advises That Controllers Identified in TER 19A for FCV1115 D,E & F Are Scheduled for Replacement During First Outage of Sufficient Duration After Dec 1983,in Response to NRC Safety Evaluation Re Environ Qualification of Electrical Equipment
ML13317A793
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 12/15/1981
From: Baskin K
Southern California Edison Co
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
IEB-79-01B, IEB-79-1B, NUDOCS 8112230188
Download: ML13317A793 (1)


Text

Southern California Edison Company P. 0. BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD, CALIFORNIA 91770 K. P. BASKIN TELEPHONE MANAGER OF NUCLEAR ENGINEERING, December 15, 1981 (213) 572-1401 SAFETY, ANO LICENSING Director of Nuclear Reactor Regulation Attention:

D. M. Crutchfield, Chief Operating Reactors Branch No. 5 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C.

20555 Gentlemen:

DEC221981

Subject:

Docket No. 50-206

0)

Environmental Qualification of Safety-Related Electrical Equipment San Onofre Nuclear Generating Station Unit 1 By letter dated November 4, 1981 we transmitted to you our response to the NRC's Safety Evaluation Report.

The letter indicated that some equipment would be replaced and that we would be providing a replacement schedule for that equipment.

Specifically, we indicated that the equipment identified in TER No.

19A and 79 was being replaced.

TER No.

19A relates to controllers for FCV 1115 D, E and F and TER No.

79 relates to Reactor Coolant RTD's.

The controllers identified in TER No.

19A for FCV1115 D, E and F are scheduled for replacement during the first outage of sufficient duration after

December, 1983.

The Reactor Coolant RTD's identified in TER No.

79 are scheduled for replacement by the next scheduled refueling outage (i.e.,

approximately Spring, 1983).

These dates are based on conceptual and preliminary information regarding the design time, material availability, fabrication and qualification of the equipment.

If the above installation dates cannot be met, based on final engineering, we will inform you.

If you have any questions regarding this information, please let me know.

Very truly yours, O89 at 1.1230185000206' PDR ADC

_D,

-P 6