Forwards Schedule for Review of NRC-prepared SEP Topic Safety Evaluations.Compliance w/30-day Review Time Will Not Be Possible for All Topics Due to Variable Availability of Manpower & Assignment of Resources to Other Activities
ML13317A711
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 10/20/1981
From: Moody W
SOUTHERN CALIFORNIA EDISON CO.
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
NUDOCS 8110270300
Download: ML13317A711 (2)


Text

Southern California Edison Company P. 0. BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD.

CALIFORNIA 91770 W. C. MOODY October 20 1981 TELEPHONES MANAGER, NUCLEAR LICENSING (213) 572-1817 (213) 572-1806 Director, Office of Nuclear Reactor Regulation Attention: D. M. Crutchfield, Chief Operating Reactors Branch No. 5 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C.

20555

(-re Gentlemen:

.1 I

CO4REG

Subject:

Systematic Evaluation Program San Onofre Nuclear Generating Station Unit 1 By letter dated April 7, 1981, we indicated our intention to review NRC prepared SEP topic safety evaluations and provide comments within 30 days of receipt. It has become apparent that complying with the 30 day review time will not be possible for all topics. This is due to the variable availability of manpower and the assignment of resources to other activities, including seismic reevaluation, SCE prepared SEP topic assessments, support to station operations during recent plant outages, and environmental qualification.

Although it is still our intention to review these evaluations as soon as possible following receipt, a 30 day turnaround time cannot be assured.

SCE currently has several NRC prepared SEP topic safety evaluations in-house for review. These topics are listed in Enclosure 1 along with the current schedule for providing comments. These schedules reflect consideration of other activities and therefore, it is anticipated that the listed dates are realistic. However, every effort will be made to expedite these reviews.

In the future, as SCE receives NRC-prepared safety evaluations, a quick assessment of the report and other ongoing activities will be made. If we will be unable to complete our review within 30 days, we will call the NRC project manager for SONGS 1 and inform him of the schedule for completion.

If you have any questions on this matter, please let me know.

Very truly yours,

4) 8110270300 811026 PDR ADOCK 05000206 P

PDR

Enclosure Schedule for Review of NRC-Prepared SEP Topic Safety Evaluations Topic Reference NRC Letter Completion Date II-3.B.1 Ability of Operating Plants to June 12, 1981 October 8, 1981 Cope with Design Basis Flooding III-3.C Inservice Inspection of July 27, 1981 October 27, 1981 Water Control Structures V-5 RCPB Leakage Detection June 3, 1981 December 15, 1981 V-10.B RHR Reliability June 20, 1981 November 20, 1981 V-11.B RHR Interlock Requirements June 20, 1981 November 20, 1981 VI-4 Containment Isolation System September 3, 1981 November 13, 1981 VI-7.B ESF Switchover From Injection July 24, 1981 November 13, 1981 to Recirculation Mode (Automatic ECCS Alignment)

VI-10.A Testing of Reactor Trip System August 28, 1981 November 30, 1981 and Engineered Safety Features, Including Response Time Testing VII-1.A Isolation of Reactor Protection September 9, 1981 November 30, 1981 System From Non-Safety Systems, Including Qualification of Isolation Devices VII-3 Systems Required for Safe June 20, 1981 November 20, 1981 Shutdown