0 UNITED STATES 0

NU LEAR REGULATORY COMMISSION REGION V 1990 N. CALIFORNIA BOULEVARD SUITE 202, WALNUT CREEK PLAZA WALNUT CREEK, CALIFORNIA 94596 Docket Nos. 50-361 50-362 Southern California Edison Company P. 0. Box 800 2244 Walnut Grove Avenue Rosemead, California 91770 Attention: Mr. Jack B. Moore Vice President Gentlemen:

Subject:

Interim Report on Taylor Forge.Pipe Defects, San Onofre Nuclear Generating Station Units 2 and 3 (your letter of June 4, 1979)

Thank you for your letter, referenced above, which provided additional information subsequent to your February 22, 1979 and April 6, 1979 letters regarding the subject matter pursuant to 10 CFR 50.55(e).

We are looking forward to receipt of your final report which you indicate will be submitted by June 22, 1979.

Your cooperation with us is appreciated.

Sincerely,

.$nglke irector cc: J. H. Drake, Vice President Engineering and Construction 7907180 73cP