UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 November 6, 2013 Mr. John Dent, Site Vice President Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508
SUBJECT:
ASSESSMENT FOLLOW-UP LETTER - PILGRIM NUCLEAR POWER STATION
Dear Mr. Dent:
As a result of its quarterly review of plant performance, which was completed on November 1, 2013, the U.S. Nuclear Regulatory Commission (NRC) updated its assessment of Pilgrim Nuclear Power Station (Pilgrim). The NRCs evaluation consisted of a review of performance indicators (PIs) and inspection results. This letter informs you of the NRCs assessment of your performance and its plans for a future inspection at Pilgrim. This letter supplements, but does not supersede, the mid-cycle letter issued on September 3, 2013.
The NRCs review of Pilgrim identified that the Unplanned Scrams with Complications PI has crossed the green-to-white threshold. The change in the PI was due to a complicated reactor trip that occurred on August 22, 2013. The NRC determined the performance at Pilgrim to be in the Regulatory Response Column of the Reactor Oversight Process Action Matrix beginning in the third quarter of 2013.
Additionally, due to another reactor scram that occurred on October 14, 2013, the Unplanned Scrams per 7000 critical hours PI will cross the green-to-white threshold at the conclusion of the fourth quarter. Subsequently, at the conclusion of the fourth quarter, Pilgrim will likely have two white inputs contributing to the Initiating Events cornerstone, transitioning Pilgrim into the Degraded Cornerstone of the Action Matrix, and will therefore receive additional oversight from the NRC. Although the Action Matrix column designation for Pilgrim will not officially change to the Degraded Cornerstone Column until the PI data is submitted, reviewed, and posted following the end of the fourth quarter, planning and scheduling activities in anticipation of an Inspection Procedure (IP) 95002 supplemental inspection can occur. The NRC will be in contact to discuss any specific planning and scheduling activities regarding these PIs and the anticipated IP 95002 supplemental inspection, including your readiness for the NRC to conduct the inspection.
J. Dent 2
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (610) 337-5229 with any questions you have regarding this letter.
Sincerely,
/RA/
Darrell J. Roberts Director Division of Reactor Projects Docket No:
50-293 License No:
DPR-35 cc:
Distribution via ListServ
ML13310A318 SUNSI Review Non-Sensitive Sensitive
Publicly Available
Non-Publicly Available OFFICE klm RI/DRP RI/DRP RI/DRP NAME JDeBoer/JPD RMcKinley/RRM DRoberts/DJR DATE 11/5/13 11/5/13 11/6/13