Forwards IE Insp Repts 50-361/79-17 & 50-362/79-17 on 790501-0601.No Noncompliance Noted
ML13309A732
Person / Time
Site: San Onofre  
Issue date: 07/06/1979
From: Spencer G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Johari Moore
SOUTHERN CALIFORNIA EDISON CO.
Shared Package
ML13309A733 List:
References
NUDOCS 7908170107
Download: ML13309A732 (2)


See also: IR 05000361/1979017

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION V

1990 N. CALIFORNIA BOULEVARD

SUITE 202, WALNUT CREEK PLAZA

WALNUT CREEK, CALIFORNIA 94596

JUL

9 1?9-

Docket Nos. 50-3614'lI

50-362

Southern California Edison Company

P. 0. Box 800

2244 Walnut Grove Avenue

Rosemead, California 91770

Attention: Mr. J. B. Moore

Vice President

Gent emen:

Subject:

NRC Inspection at San Onofre Units 2 and 3

This refers to the inspection conducted by Mr. R. J. Pate of this office

during the period May 1 to June 1, 1979, of activities authorized by

NRC Construction Permit No. CPPR-97 and CPPR-98, and to the disccusion of

our findings held with Mr. D. E. Nunn and other members of your staff

on May 11, 18, 25, and June 1, 1979.

Areas examined during this inspection are described in the enclosed inspection

report. Within these areas, the inspection consisted of selective examinations

of procedures and representative records, interviews with personnel, and obser

vations by the inspectors.

No items of noncompliance with NRC requirements were identified within the scope

of this inspection.

In accordance with Section 2.790 of the NRC's "Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room. If this

report contains any information that you believe to be proprietary, it is necessary

that you submit a written application to this office, within 20 days of the date

of this letter, requesting that such information be withheld from public disclos

ure. The application must include a full statement of the reasons why it is

claimed that the information is proprietary. The application should be prepared

so that any proprietary information identified is contained in an enclosure to

the application, since the application without the enclosure will also be placed

in the Public Document Room. If we do not hear from you in this regard within

.the specified period, the report will be placed in the Public Document Room.

Southern California Edison Company

-2-

JUL

Should you have any questions concerning this inspection, we will be glad to

discuss them with you.

Sincerely,

G. S. Spencer, Chief

Reactor Construction and

Engineering Support Branch

Enclosure:

IE Inspection Report

Nos. 50-361/79-17

50-362/79-17

cc w/o enclosure:

J. H. Drake, Vice President

Engineering & Construction, SCE