Forwards IE Insp Repts 50-361/79-07 & 50-362/79-07 on 790201-28 & Notice of Violation
ML13309A692
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 04/27/1979
From: Spencer G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Noore J
SOUTHERN CALIFORNIA EDISON CO.
Shared Package
ML13309A693 List:
References
NUDOCS 7907110705
Download: ML13309A692 (2)


See also: IR 05000361/1979007

Text

UNITED

STATES

NUCLEAR REGULATORY COMMISSION

REGION V

SUITE 202, WALNUT CREEK PLAZA

1990 N. CALIFORNIA BOULEVARD

.WALNUT CREEK, CALIFORNIA 94596

APR27 7'9

Docket Nos-T-36

Southern California Edison Company

P. 0. Box 800

2244 Walnut Grove Avenue

Rosemead, California

91770

Attention: Mr. Jack B. Moore

Vice President

Gentlemen:

Subject:

NRC Inspection at San Onofre Units 2 and 3

O This refers to the inspections conducted by Mr. R. J. Pate and

Mr. D. P. Haist of this office during the period February 1-28, 1979,

of activities authorized by NRC Construction Permit Nos. CPPR-97

and 98, and to the discussions of our findings held with Mr.

H. B. Ray and other members of your staff on February 2,.9 and 23,

1979.

Areas examined during this inspection are described in the enclosed

inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, in

terviews with personnel, and observations by the inspectors.

Based on the results of this inspection, it appears that certain of

your activities were not conducted in full compliance with NRC require

ments, as set forth in the Notice of Violation, enclosed herewith as

Appendix A. These items of noncompliance have been categorized into

a level as described in our correspondence to all NRC licensees dated

December 31, 1974.

This notice is sent to you pursuant to the provisions of Section 2.201,

of the NRC's "Rules of Practice," Part 2, Title 10, Code of Federal

Regulations. Section 2.201 requires you to submit to this office,

0

7

07 110 7 Q 5

Southern California Edison Company

-2

?within thirty (30) days of your receipt of this notice, a written state

ment or explanation in reply including (1) corrective steps which have

been taken by you and the results achieved; (2) corrective steps which

will be taken to avoid further violations; and (3) the date when full

compliance will be achieved.

In accordance with Section 2.790 of the NRC's "Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter

and the enclosed inspection report will be placed in the NRC's Public

Document Room. If this report contains any information that you

believe to be proprietary, it is necessary that you submit a written

application to this. office, within 30 days of the date of this letter,

requesting that such information be withheld from public disclosure.

The application must include a full statement of the reasons why it is

claimed that the information is proprietary. The application should

be prepared so that any proprietary information identified is contained

in an enclosure to the application, since the application without the

enclosure will also be placed in the Public Document Room. If we do

not hear from you in this regard within the specified period, the

report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be

glad to discuss them with you.

Sincerely,

G. S. S ncer, Chief

Reactor Construction and

Engineering Support Branch

Enclosures:

1. Appendix A -

Notice of Violation

2. IE Inspection Report

Nos. 50-361/79-07

and 50-362/79-07

cc w/o enclosure 2:

J. H. Drake, Vice President

Engineering and Construction, SCE