Requests Addl Info to Complete Review of Topic VIII-4 Elec Penetrations of Reactor Containments. Info Incl:Circuit & Elec Penetration Info
ML13308B400
Person / Time
Site: San Onofre 
Issue date: 12/08/1978
From: Ziemann D
Office of Nuclear Reactor Regulation
To: James Drake
SOUTHERN CALIFORNIA EDISON CO.
References
TASK-08-04, TASK-8-4, TASK-RR NUDOCS 7812270046
Download: ML13308B400 (4)


Text

DEC 0 81978 Docket No. 50-206 Mr. James H. Drake Vice President Southern California Edison Company 2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770

Dear Mr. Drake:

We have completed our search of the dockets for the SEP Plants for information relative to Topic VIII-4, "Electrical Penetrations of Reactor Containments." The results of this effort has revealed the need for additional information to complete our evaluation of this topic.

-Please provide the information identified in the enclosure within ninety (90) days.

Sincerely, Original Signed by:

Dennis L. Ziemann Dennis L. Ziemann, Chief Operating Reactors Branch 2

Division of Operating.Reactors

Enclosure:

Requestfor Additional Information NCHmt NRCPU HSm ith cc:

Local PDR DEisenhut See next page ORB#2 RDG TERA NRR RDG JRBuchanan VStello ACRS(16)

BGrimes DDavis 0ELD OI&E(3)

DLZiemann ABurger DO 2

DOR:ORB#2 f DO 1

DOR ORB#2 H

chsah j rgr DDa tDLiema n111 OATE

./78 u..e/7

.7.8

/78.

NitC FORM 318 (9-76) NRCH 0240 uGs.

OVRNmaeT rfNnsm a

scas 1ars - s6

-70e

Southern Cal ifol 9.1a Edison Company December 8, 1978 cc Rollin E. Woodbury, Vice President and General Counsel Southern California Edison Company Post Office Box 800 Rosemead, California 91770 David R. Pigott Samuel B. Casey Chickerihg & Gregory Three Embarcadero Center Twenty-Third Floor San Francisco, California 94111 David W. Gilman Robert G. Lacy San Diego Gas & Electric Company P. 0. Box 1831 San Diego, California 92112 Mission Viejo Branch Library 24851 Chrisanta Drive Mission Viejo, California 92676 U.- S. Nuclear Regulatory Commission ATTN: Robert J. Pate Post Office Box 4167 San Clemente, California 92672

ENCLOSURE REQUEST FOR INFORMATION FROM SEP LICENSEES Topic VIII Electrical Penetrations of Reactor Containment We have performed a review of the information contained in your docket concerning electrical penetrations of reactor containment. The objective of this SEP topic is to determine the capability of penetrations to maintain containment integrity during short-circuit current conditions and the worst expected transient fault current resulting from single random failures of circuit overload protection devices. Based on information contained on your docket concerning electrical penetrations we have determined that additional information is necessary to confirm that this objective is satisfied. In this regard, we request that you provide the following information for a typical low-voltage penetration circuit (150-1000 Vac); a typical medium voltage penetration circuit (greater than 1000 Vac); and a typical direct current power penetration circiut (if any).

A. Circuit Information

1. Identify each typical circuit which has been selected.
2. Provide the trip curves (current versus time) for the primary and the secondary protection devices.
3. State the maximum short circuit current available to the selected penetration circuit (the short-circuit current for AC circuits should be expressed in rms symmetrical amperes with the symmetrical current being initially offset by a DC component. The short circuit current for direct current circuits should be based on the current having a constant DC value).
4. State the size of the conductor(s) for the selected circuit (that is, conductor size external to the electrical penetration).

B. Electric Penetration Information

1. State the manufacturer's electrical penetration identification number and provide the size of the conductor(s) in the penetration. Also provide the rated continuous current for each conductor.

.2. State the rated short-circuit overload current and the duration of this current.

3. Provide a description of all electrical tests for these penetrations and state the results of these tests.

-2

References:

1. Regulatory Guide 1.63, Revision 2, "Electrical Penetrations in Containment Structures for Water Cooled Nuclear Water Plants."
2. IEEE Standard 317-1976 - "IEEE Standard for Electrical Penetration Assemblies in Containment Structures for Nuclear Power Generating Stations."