Letter Sequence Acceptance Review |
|---|
|
Results
Other: ML13339A764, ML14010A371, ML14251A231, ML14323A680, ML15057A228, ML15089A123, ML15238B576, PLA-7071, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (NRC Order EA-12-049), PLA-7137, Second Six-Month Status Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, PLA-7222, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. (NRC Order EA-12-051), PLA-7296, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Level Instrumentation (NRC Order EA-12-051), PLA-7610, Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Event (NRC Order EA-12-049)
|
MONTHYEARML13183A3892013-07-10010 July 2013 Online Reference Portal for Review of Mitigation Strategies Submittal in Response to Order EA-12-049 Project stage: Approval PLA-7071, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (NRC Order EA-12-049)2013-08-26026 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (NRC Order EA-12-049) Project stage: Other PLA-7072, Request for Implementation Date Relief in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2013-08-26026 August 2013 Request for Implementation Date Relief in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Request ML13277A3522013-10-0303 October 2013 Acceptance Review: Susquehanna, Units 1 and 2, Proposed Relief Requests for the Fourth Ten-Year Inservice Inspection Interval Project stage: Acceptance Review ML14010A3712014-01-15015 January 2014 Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for Susquehanna Steam Electric Station, Units 1 and 2, TAC Nos.: MF0888 and MF0889 Project stage: Other ML13339A7642014-01-24024 January 2014 Interim Staff Evaluation and Audit Report Relating to Overall Integrated Plan in Response to Order EA-12-049 - Mitigation Strategies Project stage: Other PLA-7137, Second Six-Month Status Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-02-28028 February 2014 Second Six-Month Status Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other ML14251A2312014-08-27027 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard Requirements for Mitigation Strategies for Beyond-Design-Basis External Events(Nrc Order EA-12-049) PLA-7204 Project stage: Other PLA-7222, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. (NRC Order EA-12-051)2014-08-27027 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. (NRC Order EA-12-051) Project stage: Other ML14323A6802014-11-24024 November 2014 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other ML15057A2282015-02-25025 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (NRC Order EA-12-049) PLA-7295 Project stage: Other PLA-7296, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Level Instrumentation (NRC Order EA-12-051)2015-02-25025 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Level Instrumentation (NRC Order EA-12-051) Project stage: Other ML15089A1232015-04-13013 April 2015 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 (TAC Nos. MF0888, MF0889, MF0890, and MF0891 Project stage: Other ML15238B5762015-08-26026 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (NRC Order EA-12-049) Project stage: Other PLA-7610, Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Event (NRC Order EA-12-049)2017-05-31031 May 2017 Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Event (NRC Order EA-12-049) Project stage: Other 2014-11-24
[Table View] |
Text
From:
Hughey, John To:
dlfilchner@pplweb.com Cc:
Whited, Jeffrey
Subject:
Acceptance Review: Susquehanna, Units 1 and 2, Proposed Relief Requests for the Fourth Ten-Year Inservice Inspection Interval.
Date:
Thursday, October 03, 2013 9:27:00 AM
- Duane, By letter dated August 30, 2013, PPL submitted a relief requests 4RR-02, 4RR-05, 4RR-06, 4RR-07 and 4RR-08 for Susquehanna, Units 1 and 2 (ADAMS Accession No. ML13247A167; TAC Nos. MF2705 - MF2714). The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of these proposed relief requests. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
If you have any questions, please contact me.
John Hughey Susquehanna Acting Project Manager Salem / Hope Creek Project Manager NRR / Division of Operating Reactor Licensing Phone: 301-415-3204 e-mail: John.Hughey@nrc.gov