ML13248A366
| ML13248A366 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley |
| Issue date: | 09/06/2013 |
| From: | Veronica Rodriguez Plant Licensing Branch 1 |
| To: | Emily Larson FirstEnergy Nuclear Operating Co |
| Baxter A | |
| References | |
| Download: ML13248A366 (2) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 6, 2013 Mr. Eric A. Larson, Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P.O. Box 4, Route 168 Shippingport, PA 15077 SURIECT:
BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 - PROJECT MANAGER REASSIGNMENTS
Dear Mr. Larson:
By letter dated August 23, 2013, you were informed of the establishment of the Mitigating Strategies Directorate (MSD) in the agency. Mr. Peter J. Bamford, Licensing Project Manager (PM) for Beaver Valley Power Station (BVPS), Unit Nos. 1 and 2, is temporarily providing support to the MSD. Therefore, this letter is to inform you that effective September 1, 2013, through October 5,2013, Mr. John G. Lamb is assigned as the agency's licensing PM for BVPS, Unit Nos. 1 and 2. Starting October 6, 2013, Mr. Jeffrey Whited will assume this responsibility.
Mr. Lamb may be reached at (301) 415-3100 or via e-mail atJohn.Lamb@nrc.gov.Mr. Whited may be reached at (301) 415-4090 or via e-mail at Jeffrey.Whited@nrc.gov.
We will notify you once Mr. Bamford resumes his duties. We apologize for any inconvenience that this may cause.
Sincerely,
"\\,
)
lr~~'~
Veronica M. Rodriguez, ~g Chief Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412 cc: Distribution via ListServ
September 6,2013 Mr. Eric A. Larson, Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P.O. Box 4, Route 168 Shippingport, PA 15077
SUBJECT:
BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 - PROJECT MANAGER REASSIGNMENTS
Dear Mr. Larson:
By letter dated August 23, 2013, you were informed of the establishment of the Mitigating Strategies Directorate (MSD) in the agency. Mr. Peter J. Bamford, Licensing Project Manager (PM) for Beaver Valley Power Station (BVPS), Unit Nos. 1 and 2, is temporarily providing support to the MSD. Therefore, this letter is to inform you that effective September 1, 2013, through October 5, 2013, Mr. John G. Lamb is assigned as the agency's Licensing PM for BVPS, Unit Nos. 1 and 2. Starting October 6,2013, Mr. Jeffrey Whited will assume this responsibility.
Mr. Lamb may be reached at (301) 415-3100 or via e-mail atJohn.Lamb@nrc.gov.Mr. Whited may be reached at (301) 415-4090 or via e-mail at Jeffrey. Whited@nrc.gov.
We will notify you once Mr. Bamford resumes his duties. We apologize for any inconvenience that this may cause.
Sincerely, lraJ Veronica M. Rodriguez, Acting Chief Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412 cc: Distribution via ListServ DISTRIBUTION:
PUBLIC RidsNrrDorlDpr RidsNrrPMBeaverValley RidsAcrsAcnw_MailCTR Resource RidsRgnlMailCenter RidsNrrDorlLPl1-2 GHunegs, R-I RidsNrrLAABaxter LPLI-2R/F DSpindler, R-1 ECarfang, R-1 ADAMS Accession No.: ML13248A366
- via e-mail OFFICE LPL1-2/PM LPL1-2/PM LPL1-2/LA JLamb JWhited ABaxter*
09/06/13 09/05/13 09/05/13 LPL1-2BC A VRodriguez 09/06113 OFFICIAL RECORD COpy