MONTHYEARML23334A1502023-11-30030 November 2023 NRC Request for Additional Information Re. Susquehanna Relief Request RR-02 ML23277A0412023-10-0505 October 2023 Notification of Commercial Grade Dedication Inspection (05000387/2024011 and 05000388/2024011) and Request for Information ML23013A2082023-01-13013 January 2023 Request for Additional Information ML22146A1022022-05-26026 May 2022 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000387/2022404 and 05000388/2022404 ML22146A0742022-05-25025 May 2022 NRR E-mail Capture - NRC Request for Additional Information - Susquehanna License Amendment Request ML22111A3132022-04-21021 April 2022 NRR E-mail Capture - NRC Request for Additional Information - Susquehanna License Amendment Request ML22041A1562022-02-10010 February 2022 Information Request for a Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000387/2022013 and 05000388/2022013 ML21316A1242021-11-18018 November 2021 Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Emergency Core Cooling Technical Specifications ML20056E4392020-02-21021 February 2020 Ti 2515/194 Inspection Documentation Request ML20010D2012020-01-0909 January 2020 Request for Additional Information Related to Request to Allow Application of Framatome Analysis Methodologies Necessary to Support a Planned Transition to Atrium 11 Fuel Under Maximum ML19319B1922019-11-14014 November 2019 NRR E-mail Capture - RAI for Susquehanna, 1 and 2 License Amendment Request - Replace the Emergency Service Water System and Residual Heat Removal Service Water System ML19319A0092019-11-14014 November 2019 NRR E-mail Capture - Draft RAI for SSES Units 1 and 2 LAR to Replace ESW Piping ML19128A0232019-05-0707 May 2019 Request for Additional Information: Susquehanna Steam Electric Station, Units 1 and 2 License Amendment Request for ESW Piping Replacement ML18352B1832018-12-13013 December 2018 Enclosurequest for Additional Information (Letter to K. Cimorelli Request for Additional Information Regarding Susquehanna Nuclear, Llc'S Decommissioning Funding Plan Update for Susquehanna Steam Electric Station Independent Spent Fuel Stor ML17180A2002017-07-0707 July 2017 Request for Additional Information Regarding License Amendment Request to Revise Diesel Generator Surveillance Requirements with New Steady State Voltage and Frequency Limits ML17059D2142017-03-0606 March 2017 Susquehanna Steam Electric Station - Supplemental Information Needed for Acceptance of Requested Licensing Action Re: License Amendment Request to Revise Diesel Generator Surveillance Requirements with New Steady State Voltage Frequency Limits ML16251A0652016-09-0909 September 2016 Susquehanna Steam Electric Station, Unit 2 - RAI Regarding Temporary Change of Unit 2, Technical Specifications 3.7.1 & 3.8.7 to Allow Replacement of Unit 1, 480 Volt Engineered Safeguard System Load Center Transformers(CAC No. MF7298) ML16245A2052016-09-0101 September 2016 Draft Request for Additional Information Replacement of Load Center Transformers ML16243A0952016-08-30030 August 2016 Draft Request for Additional Information Application for Approval of Indirect Transfer of Control of Licenses ML16060A2302016-03-24024 March 2016 Acceptance of Requested Licensing Action License Amendment Request for Temporary Change of Unit 2 Technical Specifications 3.71 and 3.87 to Allow Replacement of Unit 1 480V Ess Load Center Transformers ML15316A5632015-11-13013 November 2015 Request for Additional Information Regarding Proposed Relief Requests for the Third 10-Year Inservice Inspection Interval(Cac Nos. MF6302 Through MF6307) ML15292A1782015-10-15015 October 2015 TSTF-425 LAR Draft 3rd RAIs ML15230A0802015-08-26026 August 2015 Request for Additional Information Regarding License Amendment Request to Adopt NEI 99-01, Revision 6, EAL Scheme Change ML15209A9742015-08-24024 August 2015 Request for Additional Information License Amendment Request to Adopt Technical Specifications Task Force Traveler (TSTF)-425 ML15229A2002015-08-17017 August 2015 E-mail from J. Whited to J. Jennings SSES Draft TSTF-425 RAIs ML15229A2092015-08-17017 August 2015 SSES Draft Request for Additional Information Licensee Request to Adopt TSTF-425 ML15230A0462015-08-17017 August 2015 Draft RAIs SSES EAL Scheme Change LAR in Accordance with NEI 99-01 Rev 6 ML15183A3502015-07-0202 July 2015 SSES Relief Requests 3RR-19, 3RR-20, and 3RR-21 Draft Identified Information Insufficiencies (TAC Nos. MF6302 Through MF6307) ML15103A3962015-05-22022 May 2015 Request for Additional Information License Amendment Request to Adopt Technical Specifications Task Force Traveler (TSTF)-425 (TAC Nos. MF5151 and MF5152) ML15128A5162015-05-0808 May 2015 SSES Draft Request for Additional Information LAR for Implementation of TSTF-425 ML15128A5092015-05-0808 May 2015 E-mail from J. Whited to D. Filchner SSES Draft Request for Additional Information LAR for Implementation of TSTF-425 ML15008A4702015-01-30030 January 2015 Request for Additional Information Request to Revise Technical Specification 3.4.10, RCS Pressure and Temperature (P/T) Limits. ML15016A2742015-01-16016 January 2015 Draft RAIs License Amendment Request for Change to TS 3.4.10 P/T Limits (TAC Nos. MF4597 and MF45980) ML15016A2722015-01-16016 January 2015 E-mail from J. Whited to D. Filchner Draft RAIs License Amendment Request for Change to TS 3.4.10 P/T Limits (TAC Nos. MF4597 and MF45980) ML14343A9842015-01-0808 January 2015 Request for Additional Information Relief Request 4RR-01 ML14345A2412014-12-16016 December 2014 Request for Additional Information Request for Order Approving Indirect Transfer of Control and Conforming License Amendments ML14346A1022014-12-12012 December 2014 Draft License Transfer Revised 2nd RAIs ML14346A4022014-12-12012 December 2014 Draft RAIs Relief Request 4RR-01 ML14346A4012014-12-12012 December 2014 E-mail from J. Whited to D. Filchner Susquehanna Steam Electric Station Draft RAIs Relief Request 4RR-01 ML14346A1002014-12-12012 December 2014 E-mail from J. Whited to R. Sgarro Susquehanna Steam Electric Station Draft License Transfer Revised 2nd RAIs ML14342A8082014-12-0808 December 2014 E-mail from J. Whited to R. Sgarro (PPL) SSES Units 1 and 2 Draft RAIs Application for Approval of Indirect Transfer of Control of Licenses ML14342A8132014-12-0808 December 2014 SSES Units 1 and 2 Draft RAIs Application for Approval of Indirect Transfer of Control of Licenses ML14233A2772014-08-27027 August 2014 Request for Additional Information License Amendment Request to Change the Low Pressure Safety Limit ML14233A3392014-08-21021 August 2014 Draft RAIs for Susquehanna Steam Electric Station Units 1 and 2 License Amendment Request for Changes to the Low Pressure Safety Limits ML13298A7582014-03-0707 March 2014 Request for Additional Information Regarding Request for Changes to Technical Specification Surveillance Requirements to Increase Diesel Generator Minimum Steady State Voltage (TAC ME9607 and ME960) ML13298A7812014-03-0707 March 2014 Request for Additional Information Regarding Request for Changes to Technical Specification Surveillance Requirement 3.8.1.19 to Increase Diesel Generator Minimum Steady State Frequency (TACs ME9609. ML14013A1502014-01-31031 January 2014 Request for Additional Information Regarding Relief Requests for the Fourth 10-Year Inservice Testing Interval ML14024A4752014-01-24024 January 2014 Draft 4th IST RRs 1RR05 RAIs ML13338A4422013-12-19019 December 2013 Request for Additional Information Regarding Relief Requests for the Fourth Ten-Year Inservice Inspection Interval ML13312A9142013-12-18018 December 2013 Request for Additional Information Regarding Request for Changes to Technical Specification Surveillance Requirements 3.5.1.12 2023-11-30
[Table view] |
Text
DRAFT REQUEST FOR ADDITIONAL INFORMATION REGARDING PROPOSED LICENSE AMENDMENT REQUEST TO CHANGE TECHNICAL SPECIFICATION SURVEILLANCE REQUIREMENTS TO INCREASE DIESEL GENERATOR MINIMUM STEADY STATE VOLTAGE SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 DOCKET NOS. 50-387 AND 50-388 By letter to the Nuclear Regulatory Commission (NRC) dated September 18, 2012,1 as supplemented by letter dated, May 10, 2013,2 PPL Susquehanna, LLC (PPL, the licensee) submitted a license amendment request (LAR) for Susquehanna Steam Electric Station (SSES),
Units 1 and 2. The proposed amendments would change Technical Specification (TS)
Surveillance Requirements (SRs) 3.8.1.9, 3.8.1.11, 3.8.1.12 and 3.8.1.19 in TS 3.8.1, AC Sources-Operating. Specifically, the proposed amendments would increase the Diesel Generator (DG) acceptable minimum steady state voltage when operating in emergency/isochronous mode.
The NRC staff has reviewed the information that the licensee provided in support of its proposed license amendments. In order for the staff to complete its review, the licensee is requested to address the following requests for additional information.
Background:
In order to be considered operable, structures, systems and components (SSCs) must be capable of performing the safety functions specified by its design, within the required range of design physical conditions, initiation times, and mission times. In addition, TS operability considerations require that SSCs meet all surveillance requirements. In order to be considered operable, SSCs must be capable of performing the safety functions specified by their design, within the required range of design physical conditions, initiation times, and mission times. For operability determination purposes, the mission time is the duration of SSC operation that is credited in the design basis for the SSC to perform its specified safety function.
The staff considers that all SRs with specific parameters including proper DG output voltage demonstrate the capability of the DGs to satisfy the specified safety function as credited in the design basis accident conditions delineated in the Final Safety Analyses Report.
The staff has made following observations:
- The response to NRC Question 3 in the licensees submittal dated, May 10, 2013,states SSES DG loading calculations, in general, are based on nominal voltages.
- The license amendment request dated September 18, 2012, for changing minimum allowable frequency states An SSES calculation and cable data confirms that the 1
Agencywide Documents Access and Management System Accession No. ML12262A322 2 ADAMS Accession No. ML13130A130.
DRAFT
voltage drop between Diesel Generator E and the 4.16 k V buses is significantly higher than that for Diesel Generators A-D. The increased voltage drop corresponds with an increase in current, causing the Diesel Generator to increase power output, which causes a frequency dip.
- Calculation EC-024-1031, attached to letter dated May 10, 2013, states It is appropriate to base the maximum steady state current on the DG-A through D rating rather than the higher rating of DG-E. This is because steady state loads must stay within the capability of the lower machine rating. The highest DG load shown in the FSAR diesel loading tables is in FSAR table 8.3-3 which shows a maximum steady state diesel load of 3976.85 KW (DG-A). This is close to the 4000 KW machine nominal rating. For purposes of determining the maximum steady state current, a steady state loading of 4000 KW will be used.
Requests for Additional Information:
RAI 4: The response to RAI 1 stated that The steady state output voltage when operating in the droop (test) mode is not being changed because when operating in the test configuration the DG output voltage is determined by the electrical power grid to which it is connected. SR 3.8.1.3 requires each DG to be synchronized, loaded and operated for 60 minutes at a load 3600 kW and 4000 kW. The staff concurs that this SR requires operation of the DG in droop mode and as such verification of DG voltage is not required. However, SRs 3.8.1.7, 3.8.1.15 and 3.8.1.20 do not require the DG to be synchronized to the grid but have voltage parameters to be validated.
Explain how these SRs demonstrate the operability of the DGs when the LAR states that these parameters are non conservative.
RAI 5: Assuming that DGs A-D are operating at the proposed allowable voltage of 4000V, provide details on the maximum DG load due to the increase in current at the lower voltage, as nominal voltage was used to calculate maximum steady state diesel load of 3976.85 KW.
RAI 6: Assuming DG E is substituting for one of the other DGs and is operating at the proposed allowable output voltage of 4000V, provide details on the maximum load that DG-E will be supplying in view of the increased current flow at a voltage below the nominal voltage.
RAI 7: At the onset of an event, some pumps may be operating under run out conditions for an extended duration, imposing a higher load on the associated motors. Validate that the consequential higher loading on DG-E, when operating at 4000V, will not result in steady state voltage less than the reset setpoint of degraded voltage relays.
RAI 8: Validate that the current value used in Calculation EC-024-1031 is still bounding based on responses to RAIs 5, 6 and 7 above.
RAI 9: Validate that plant procedures used to perform SRs verifying DG loading capability (e.g. SR 3.8.1.3) envelope the postulated accident loading based on limiting DG voltage.
RAI10: Validate that the consequences of the change in DG loading due to operation at 4000V has been considered for impact on other DG SRs such as fuel oil and lube oil storage requirements.