Request for Additional Information for 2013 Decommissioning Funding Status Report
ML13175A173
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 06/28/2013
From: John Lamb
Plant Licensing Branch 1
To: Walsh K
NextEra Energy Seabrook
Lamb J, NRR/DORL/LPLI-2, 415-3100
References
TAC MF2445
Download: ML13175A173 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 June 28, 2013 Mr. Kevin Walsh, Site Vice President clo Michael O'Keefe Seabrook Station NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874

SUBJECT:

SEABROOK STATION, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION FOR 2013 DECOMMISSIONING FUNDING STATUS REPORT (TAC NO. MF2245)

Dear Mr. Walsh:

By letter dated March 25, 2013 (Agencywide Documents Access and Management System Accession No. ML13093A156), NextEra Energy Seabrook, LLC, submitted its 2013 Decommissioning Funding Status report.

The U.S. Nuclear Regulatory Commission staff has determined that additional information is necessary to complete its review. The request for additional information is enclosed. The licensee agreed to provide answers to the request for additional information within 30 days of the date of this letter.

If you have questions, you can contact me at 301-415-3100 andlor John.Lamb@nrc.gov.

Sincerely,

. Lamb, Senior Project Manager icensing Branch 1-2 n of Operating Reactor Licensing of Nuclear Reactor Regulation Docket No. 50-443

Enclosure:

Request for Additional Information cc wi enclosure: Distribution via ListServ

REQUEST FOR ADDITIONAL INFORMATION 2013 DECOMMISSIONING FUNDING STATUS REPORT NEXTERA ENERGY SEABROOK, LLC.

SEABROOK STATION, UNIT 1 DOCKET NO. 50-443 By letter dated March 25,2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13093A156), NextEra Energy Seabrook, LLC (NextEra or licensee) submitted its 2013 Decommissioning Funding Status (DFS) report for Seabrook Station, Unit 1 (Seabrook) as required under Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Section 50.75(f)(1).

The U.S. Nuclear Regulatory Commission (NRC) staff has determined that the following additional information is necessary to complete its review.

REQUEST FOR ADDITIONAL INFORMATION (RAI)

Indicate what portion of the accumulated fund balances are for radiological decommissioning activities only, Specify, if any, of the $460,911,928 for Seabrook is for non-radiological decommissioning costs such as spent fuel management or other non-radiological decommissioning activities.

On March 25, 2013, NextEra provided the amount accumulated in the decommissioning trust fund at the end of the calendar year preceding the date of the report for items included in 10 CFR 50.75 (b) and (c). Confirm that the dollar amounts identified above are exclusively for radiological decommissioning.

Per 10 CFR 50. 75(f)(1), licensees must identify "the amount accumulated to the end of the calendar year preceding the date of the report." This actual amount is dedicated for NRC decommissioning activities, as defined in 10 CFR 50.2. Per phone conversation on May 30, 2013, between NRC and NextEra staff (meeting summary may be found at NRC ADAMS Accession No. ML13158A197), NRC indicated that it would generate an RAI in response to NextEra's 2013 DFS report submission for Seabrook. Specifically, it remained unclear to the NRC staff what portion of the trust fund balance for Seabrook was dedicated to NRC decommissioning activities, as defined in 10 CFR 50.2.

Enclosure

June 28. 2013 Mr. Kevin Walsh. Site Vice President c/o Michael O'Keefe Seabrook Station NextEra Energy Seabrook. LLC P.O. Box 300 Seabrook. NH 03874

SUBJECT:

SEABROOK STATION, UNIT 1

  • REQUEST FOR ADDITIONAL INFORMATION FOR 2013 DECOMMISSIONING FUNDING STATUS REPORT (TAC NO. MF2245)

Dear Mr. Walsh:

By letter dated March 25.2013 (Agencywide Documents Access and Management System Accession No. ML13093A156), NextEra Energy Seabrook, LLC, submitted its 2013 Decommissioning Funding Status report.

The U.S. Nuclear Regulatory Commission staff has determined that additional information is necessary to complete its review. The request for additional information is enclosed. The licensee agreed to provide answers to the request for additional information within 30 days of the date of this letter.

If you have questions, you can contact me at 301415*3100 and/or John.Lamb@nrc.gov.

Sincerely.

Ira!

John G. Lamb, Senior Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443

Enclosure:

Request for Additional Information cc w/ enclosure: Distribution via ListServ DISTRIBUTION:

PUBLIC RidsNrrDorlDpr Resource RidsNrrPMSeabrook Resource LPLI-2 RlF RidsNrrDorlLpl1-2 Reso RidsNrrLAABaxter Reso urce urce RidsAcrsAcnw_MailCTR Resource RidsRgn1 MailCenter Resource KKarwoski. NRR RGrover. NRR ADAMS Accession No.: ML13175A173 "via memo LPL1-21PM

~==

JLamb 06/26/13 LPL1-2/PM JLamb 06128113