IR 05000269-13-406, 05000270-13-406 and 05000287-13-406, on May 20-24, 2013, Oconee Nuclear Station - Notification of Cyber Security Milestones 1-7 Inspection and Request for Information
ML13058A319
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 02/27/2013
From: Mark King
NRC/RGN-II/DRS/EB2
To: Gillespie T
Duke Energy Corp
References
IR-13-406
Download: ML13058A319 (6)


See also: IR 05000269/2013406

Text

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

245 PEACHTREE CENTER AVENUE NE, SUITE 1200

ATLANTA, GEORGIA 30303-1257

February 27, 2013

Mr. T. Preston Gillespie, Jr.

Site Vice President

Duke Energy Corporation

Oconee Nuclear Station

7800 Rochester Highway

Seneca, SC 29672-0752

SUBJECT: OCONEE NUCLEAR STATION - NOTIFICATION OF CYBER SECURITY TI

MILESTONES 1-7 INSPECTION AND REQUEST FOR INFORMATION (NRC

INSPECTION REPORT NO. 05000269/2013406 AND 05000270/2013406 AND

05000287/2013406)

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)

Region II (RII) staff will conduct an inspection of the Cyber Security Milestones 1-7 requirements

specified by the conditions of your operating license at the Oconee Nuclear Station on May 20 -

24, 2013. The inspection team will be led by Mr. Jigar Patel, Reactor Inspector, of the NRC RII

office. The team will be composed of personnel from the NRC RII office and personnel from the

NRC office of Nuclear Security and Incident Response (NSIR). The inspection will be

conducted in accordance with Temporary Instruction (TI) 2201/004, Inspection of

Implementation of Interim Cyber Security Milestones 1-7. The TI inspection will be performed

to evaluate and verify your ability to meet the interim milestone requirements of the NRCs

Cyber Security Rule, Title 10, Code of Federal Regulations (CFR), Part 73, Section 54,

Protection of Digital Computer and Communication Systems and Networks.

In accordance with 10 CFR 73.54, each nuclear power plant licensee was required to submit

a proposed cyber security plan (CSP) and implementation schedule for NRC review and

approval. On December 14, 2009, by letter (ML093080517) to the Nuclear Energy Institute

(NEI), the NRC provided their expectations for the proposed implementation schedule. On

January 5, 2011, by letter (ML110060093) to the NRC, NEI issued an initial Template for the

Cyber Security Plan Implementation Schedule (ML110060097). On February 28, 2011, by

letter (ML110600206) to the NRC, NEI provided a revised, Template for the Cyber Security

Plan Implementation Schedule. The purpose of the letters attachment was to provide the

licensee with a generically written template to develop their proposed CSP implementation

schedule. Utilization of the generic template required the licensee to make conforming changes

to ensure the submitted schedule accurately accounted for site-specific activities. The CSP,

implementation schedule, and other applicable information for your facility provided the

Enclosure transmitted herewith contains SUNSI. When separated from enclosure, this

transmittal document is decontrolled

LIMITED INTERNAL

DISTRIBUTION PERMITTED

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION

T. Preston Gillespie, Jr. 2

implementation aspects, including the key intermediate milestone attributes and dates as well

as the full implementation dates. The implementation aspects were described based, in part, on

letters to the NRC dated November 20, 2009 (ML093410249), August 16, 2010

(ML1023001680, ML1023001681) and supplemented by letters dated September 27, 2010,

March 7, 2011, April 15, 2011 (ML111090627), and August 9, 2011 (ML11109A0741). By

reference to letter dated August 31, 2011 (ML11216A064), license condition 3.E was modified

for facility operating licenses DPR-38, DPR-47, and DPR-55 for Oconee Units 1, 2, and 3 to

ensure that the CSP would be implemented and maintained consistent with NRC requirements.

On February 21, 2013, during a conversation between Ms. Judy Smith of your staff, and

Mr. Jigar Patel, NRC RII, our respective staffs confirmed arrangements for a three day

information gathering onsite visit and a one-week onsite inspection. The subject TI inspection

provides a programmatic level review and verification of the licensees site-specific

implementation of Interim Milestones 1 through 7. The schedule for the onsite TI Inspection for

the Interim Milestones 1 through 7 is as follows:

  • Information gathering visit: May 7 - 9, 2013
  • Onsite inspection: May 20 - 24, 2013

The purpose of the information gathering visit is to: (1) obtain information and documentation

needed to support the TI inspection; (2) become familiar with the Oconee Nuclear Station Cyber

Security Program and plant layout; and (3) arrange administrative details, such as office space,

availability of knowledgeable office personnel and to ensure unescorted site access privileges.

In order to assure a productive TI inspection, we have enclosed a request for documents

needed to ensure the inspectors are adequately prepared. These documents have been

divided into three groups (I, II, & III). Group I lists information necessary to aid the inspectors in

planning for the TI inspection prior to the information gathering visit. It is requested that this

information be provided to the lead inspector via mail no later than April 10, 2013. Group II lists

information and possible areas for discussion necessary to assist the inspectors during the

TI inspection. It is requested this information be available during the information gathering visit

(May 7, 2013). Group III consists of those items that the inspectors will review, or need access

to, during the TI inspection. Group III also lists the information necessary to aid the inspectors

in tracking questions and answers identified as a result of the TI inspection. It is requested that

this information be provided to the lead inspector as the information is generated during the

TI inspection. It is important that all of these documents are up to date and complete in order to

minimize the number of additional documents requested during the preparation and/or the

onsite portions of the TI inspection.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, control number 3150-

0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a

request for information or an information collection requirement unless the requesting document

displays a currently valid Office of Management and Budget control number.

Your cooperation and support during this inspection will be appreciated. If you have questions

concerning this inspection, or the inspection team's information or logistical needs, please

contact Mr. Patel at (404) 997-4577, or me at (404) 997-4511.

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION

T. Preston Gillespie, Jr. 3

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be

available electronically for public inspection in the NRC Public Document Room or from the

Publicly Available Records (PARS) component of NRC's document system, ADAMS.

ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the

Public Electronic Reading Room). However, because of the security-related concerns

contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters

enclosure will not be available for public inspection.

Sincerely,

/RA/

Michael F. King, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No.: 50-269, 50-270, 50-287

License No.: DPR-38, DPR-47, DPR-55

Enclosure:

Document Request For Cyber Security Temporary

Instruction (TI) 2201/004 Interim Milestones 1-7 Inspection

(OFFICIAL USE ONLY)

cc: (See page 4)

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION

_________________________ xG SUNSI REVIEW COMPLETE G FORM 665 ATTACHED

OFFICE RII:DRS RII:DRS RII:DRS

SIGNATURE *RA RA RA

NAME PATEL FANNER KING

DATE 2/25/2013 2/25/2013 2/27/2013

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION

T. Preston Gillespie, Jr. 4

cc: David G. Black

Robert H. Guy Fleet Security Manager

Organizational Effectiveness Manager General Office

Oconee Nuclear Station Duke Energy Corporation

Duke Energy Corporation P. O. Box 1006

7800 Rochester Highway 526 S. Church Street

Seneca, SC 29672 Charlotte, NC 28201-1006

Terry L. Patterson Timothy J. Wadsworth

Safety Assurance Manager Security Specialist

Duke Energy Corporation General Office

Oconee Nuclear Station Duke Energy Corporation

7800 Rochester Highway P. O. Box 1006

Seneca, SC 29672 526 S. Church St., EC05P

Charlotte, NC 28201-1006

Kent Alter

Regulatory Compliance Manager David A. Cummings

Oconee Nuclear Station Associate General Counsel

Duke Energy Corporation General Office

ON03RC Duke Energy Corporation

7800 Rochester Highway P.O. Box 1006

Seneca, SC 29672 526 S. Church St., EC07H

Charlotte, NC 28201-1006

Terry W. King

Security Manager

Oconee Nuclear Station

Duke Energy Corporation

7800 Rochester Highway

Seneca, SC 29672

Daniel C. Durham

Security Safeguards Administrator

Oconee Nuclear Station

Duke Energy Corporation

7800 Rochester Highway

Seneca, SC 29672

M. Christopher Nolan

Director - Regulatory Affairs

General Office

Duke Energy Corporation

P. O. Box 1006

526 S. Church Street

Charlotte, NC 28201-1006

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION

Letter to T. Preston Gillespie, Jr. from Michael F. King dated February 27, 2013.

SUBJECT: OCONEE NUCLEAR STATION - NOTIFICATION OF CYBER SECURITY TI

MILESTONES 1-7 INSPECTION AND REQUEST FOR INFORMATION (NRC

INSPECTION REPORT NO. 05000269/2013406 AND 05000270/2013406 AND

05000287/2013406)