ML13035A214
ML13035A214 | |
Person / Time | |
---|---|
Site: | Sequoyah ![]() |
Issue date: | 02/26/2013 |
From: | John Lubinski Division of License Renewal |
To: | John Carlin Tennessee Valley Authority |
Yoo, M, 415-8583 | |
References | |
Download: ML13035A214 (15) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 26,2013 Mr. John T. Carlin Site Vice President Sequoyah Nuclear Plant, Units 1 and 2 Tennessee Valley Authority P.O. Box 2000 Soddy-Daisy, TN 37384
SUBJECT:
DETERMINATIOI\\J OF ACCEPTABILITY AND SUFFICIENCY FOR DOCKETING, PROPOSED REVIEW SCHEDULE, AND OPPORTUNITY FOR A HEARING REGARDING THE APPLICATION FROM TENNESSEE VALLEY AUTHORITY FOR REI\\JEWAL OF THE OPERATING LICENSES FOR SEOUOYAH NUCLEAR PLANT, UNITS 1 AND 2
Dear Mr. Carlin:
By letter dated January 7, 2013, the U.S. Nuclear Regulatory Commission (NRC or the staff) received the Tennessee Valley Authority application for renewal of Operating Licenses DPR-77 and DPR-79 for Sequoyah Nuclear Plant, Units 1 and 2 (SON). Notice of receipt of this application was published (n the Federal Register on February 22,2013 (78 FRN 12365). The purpose of this letter is to provide the results of the staff's acceptance review of the license renewal application for SON. The acceptance review determines whether the application contains sufficient information to allow the staff to proceed with the safety and environmental reviews.
The staff has reviewed your application following the guidance in NUREG-1800, Revision 2, "Standard Review Plan for Review of License Renewal Applications (LRA) for l\\Juclear Power Plants," and NUREG-1555, "Standard Review Plans for Environmental Reviews for Nuclear Power Plants." As a result, the staff has determined that the application is sufficient and acceptable for docketing in accordance with Title 10 of the Code of Federal Regulations (CFR)
Sections 2.101, 51.45, 51.53(c), 54.19, 54.21, 54.22, and 54.23. However, the staff's determination does not preclude requests for additional information (RAls) as the review proceeds.
This letter forwards the staff's safety and environmental review schedule for SON application (Enclosure 1). The NRC staff will follow established review procedures and the enclosed schedule to complete the reviews required by 10 CFR Parts 51 and 54. Milestones for hearing activities are not included in the enclosed schedule because these dates, if needed, would be established by the Commission or the Atomic Safety and Licensing Board. We would like to emphasize that the staff's review of your*LRA will be very detailed and thorough. The staff will make every effort to meet the scheduled milestones; thus, your responses to the staff's RAls, if needed, must be complete and provided in a timely manner. In addition, the staff noted that for certain aging management programs and time-limited aging-analyses, the staff will likely require additional resources during audits and in preparation of additional RAls to verify claims of consistency with the Generic Aging Lessons Learned Report recommendations. We request
Sincerely, Division of License J. Carlin
- 2 that you inform the NRC staff as early as possible should potential delays arise in your support of the schedule.
Finally, we have also enclosed a copy of the notice related to your application that is being sent to the Office of the Federal Register for publication (Enclosure 2). This notice announces the opportunity to request a hearing and to file a petition for leave to intervene.
If you have any questions related to the safety review of the Sequoyah LRA, please contact Mr.
Richard Plasse, Project Manager, by telephone at 301-415-1427 or via e-mail at Richard.Plasse@nrc.gov. If you have any questions related to the environmental review of the Sequoyah LRA, please contact Mr. Emmanuel Sayoc, Project Manager, by telephone at 301-415-4084 or via e-mail at EmmanueI.Sayoc@nrc.gov.
irector enewal Office of Nuclear Reactor Regulation Docket Nos. 50-327, 50-328
Enclosures:
As stated cc w/encls: Listserv
ENCLOSURE 1 Sequoyah Nuclear Plant, Units 1 and 2 License Renewal Application Review Schedule
SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 LlCEI\\JSE RENEWAL APPLICATION REVIEW SCHEDULE Milestone Scheduled Actual Receive license renewal application (LRA) 01/15/13 1115113 Publish Federal Register Notice (FRN) - LRA availability 02/2013 2122/13 Publish FRN acceptancelrejection and opportunity for hearing 03/2013 Publish FRN environmental scoping meeting 03/2013
~udit - Scoping & Screening Methodology 03/11/13 fAudit - Aging Management Programs 03/18/13 Public Meeting - License Renewal Overview and Environmental Scoping meeting 04/03/13 Audit - Environmental 04/8113 Deadline for filing hearing requests and petitions for intervention 05/2013 Environmental scoping period ends 05/2013 Inspection - Regional TBD Issue draft supplemental environmental impact statement (SEIS) 02/2014 Publish FRN draft SEIS available for comments 02/2014 Public Meeting - draft SEIS meeting 03/2014 Issue safety evaluation report (SER) with open items 03/2014 End of draft SEIS comment period 04/2014 lA.dvisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 05/2014 Issue final SEIS 10/2014 U.S. Environmental Protection Agency FRN Published - availability of final SEIS 10/2014 Issue final SER 10/2014 IACRS full committee meeting 12/2014 Decision - Director, NRR 02/2015 Commission decision, if hearing granted TBD
[7590-01-P]
UNITED STATES NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-327, 50-328; NRC-20XX-XXXX]
Notice of Acceptance for Docketing of the Application, Notice of Opportunity for Hearing, Regarding Renewal of Facility Operating License Nos. DPR-77, DPR-79 for an Additional 20-Year Period Tennessee Valley Authority Sequoyah Nuclear Plant, Units 1 and 2 The U.S. Nuclear Regulatory Commission (NRC or the Commission) is considering an application for the renewal of operating licenses DPR-77 and DPR-79, which authorizes Tennessee Valley Authority (TVA), to operate the Sequoyah Nuclear Plant (SON) Unit 1 at 3455 megawatts thermal and Unit 2 at 3455 megawatts thermal. The renewed licenses would authorize the applicant to operate SON, Units 1 and 2, for an additional 20 years beyond the period specified in the current licenses. SQN Units 1 and 2 are located in Soddy-Daisy, TN; the current operating license for Unit 1 expires on September 17, 2020, and Unit 2 expires on September 15, 2021.
TVA submitted the application dated January 7,2013, pursuantto Title 10, Part 54, of the Code of Federal Regulations (10 CFR Part 54), to renew operating licenses DPR-77 and DPR-79. A notice of receipt and availability of the license renewal application (LRA) was published in the Federal Register on February 22, 2013 (78 FRN 12365).
. The Commission's staff has determined that TVA has submitted sufficient information in accordance with 10 CFR Sections 54.19,54.21,54.22,54.23,51.45, and 51.53(c), to enable
-2 the staff to undertake a review of the application, and that the application is therefore acceptable for docketing. The current Docket Numbers, 50-327 and 50-328, for operating license numbers DPR-77, DPR-79, respectively, will be retained. The determination to accept the LRA for docketing does not constitute a determination that a renewed license should be issued, and does not preclude the NRC staff from requesting additional information as the review proceeds.
Before issuance of the requested renewed licenses, the NRC will have made the findings required by the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations. In accordance with 10 CFR 54.29, the NRC may issue a renewed license on the basis of its review if it finds that actions have been identified and have been or will be taken with respect to: (1) managing the effects of aging during the period of extended operation on the functionality of structures and components that have been identified as requiring aging management review, and (2) time-limited aging analyses that have been identified as requiring review, such that there is reasonable assurance that the activities authorized by the renewed license will continue to be conducted in accordance with the current licensing basis (CLB) and that any changes made to the plant's CLB will comply with the Act and the Commission's regulations.
Additionally, in accordance with 10 CFR 51.95(c), the NRC will prepare an environmental impact statement that is a supplement to the Commission's NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Power Plants," dated May 1996. In considering the LRA, the Commission must find that the applicable requirements of Subpart A of 10 CFR Part 51 have been satisfied, and that matters raised under 10 CFR 2.335 have been addressed. Pursuant to 10 CFR 51.26, and as part of the environmental scoping process, the staff intends to hold a public scoping meeting. Detailed information regarding the environmental seeping meeting will be the subject of a separate Federal Register notice.
Within 60 days after the date of publication of this Federal Register notice, any person
-3 whose interest may be affected by this proceeding and who wishes to participate as a party in the proceeding must file a written request for a hearing and a petition for leave to intervene with respect to the renewal of the license. Requests for a hearing or petitions for leave to intervene must be filed in accordance with the Commission's "Rules of Practice for Domestic Licensing Proceedings and Issuance of Orders" in 10 CFR Part 2. Interested persons should consult a current copy of 10 CFR 2.309, which is available at the Commission's Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike (first floor). Rockville, Maryland 20852 and is accessible from the NRC's Agencywide Documents Access and Management System (ADAMS) Public Electronic Reading Room on the Internet at http://www.nrc.govlreading-rm/adams.html. Persons who do not have access to the Internet or who encounter problems in accessing the documents located in ADAMS should contact the NRC's PDR reference staff by telephone at 1-800-397-4209, or 301-415-4737, or bye-mail at PDR.Resource@nrc.gov. If a request for a hearing/petition for leave to intervene is filed within the 60-day period, the Commission or a presiding officer designated by the Commission or by the Chief Administrative Judge of the Atomic Safety and Licensing Board Panel will rule on the request and/or petition; and the Secretary or the Chief Administrative Judge of the Atomic Safety and Licensing Board Panel will issue a notice of a hearing or an appropriate order. In the event that no request for a hearing or petition for leave to intervene is filed within the 60-day period, the NRC may, upon completion of its evaluations and upon making the findings required under 10 CFR Parts 51 and 54, renew the license without further notice.
As required by 10 CFR 2.309, a petition for leave to intervene shall set forth with particularity the interest of the petitioner in the proceeding, and how that interest may be affected by the results of the proceeding, taking into consideration the limited scope of matters that may be considered pursuant to 10 CFR Parts 51 and 54. The petition must specifically explain the reasons why intervention should be permitted with particular reference to the following factors: (1) The nature of the requestor's/petitioner's right under the Act to be made a
-4 party to the proceeding; (2) the nature and extent of the requestor's/petitioner's property, financial, or other interest in the proceeding; and (3) the possible effect of any decision or order which may be entered in the proceeding on the requestors/petitioner's interest. The petition must also set forth the specific contentions which the petitioner/requestor seeks to have litigated at the proceeding.
Each contention must consist of a specific statement of the issue of law or fact to be raised or controverted. In addition, the requestor/petitioner shall provide a brief explanation of the basis for each contention and a concise statement of the alleged facts or the expert opinion that supports the contention on which the requestor/petitioner intends to rely in proving the contention at the hearing. The requestor/petitioner must also provide references to those specific sources and documents of which the requestor/petitioner is aware and on which the requestor/petitioner intends to rely to establish those facts or expert opinion. The requestor/petitioner must provide sufficient information to show that a genuine dispute exists with the applicant on a material issue of law or fact. 1 Contentions shall be limited to matters within the scope of the action under consideration. The contention must be one that, if proven, would entitle the requestor/petitioner to relief. A requestor/petitioner who fails to satisfy these requirements with respect to at least one contention will not be permitted to participate as a party.
Petitions filed after the deadline, amended petitions, and supplemental petitions will not be entertained absent a determination by th'e Commission, the Atomic Safety and Licensing Board Panel or a Presiding Officer that the petition should be granted and/or the contentions should be admitted based upon a balancing of the factors specified in 10 CFR 2.309(c)(1 )(i)
(viii).
1 To the extent that the application contains attachments and supporting documents that are not publicly available because they are asserted to contain safeguards or proprietary information, petitioners desiring access to this information should contact the applicant or applicant's counsel to discuss the need for a protective order.
-5 A State, county, municipality, Federally-recognized Indian Tribe, or agencies thereof, may submit a petition to the Commission to participate as a party under 10 CFR 2.309(d)(2).
The petition should state the nature and extent of the petitioner's interest in the proceeding.
The petition should be submitted to the Commission by [INSERT DATE: 60 DAYS FROM THE DATE OF PUBLICATION OF THIS FEDERAL REGISTER NOTICE]. The petition must be filed in accordance with the filing instructions in section IV of this document, and should meet the requirements for petitions for leave to intervene set forth in this section, except that State and Federally-recognized Indian tribes do not need to address the standing requirements in 10 CFR 2.309(d)(1) if the facility is located within its boundaries. The entities listed above could also seek to participate in a hearing as a nonparty pursuant to 10 CFR 2.315(c).
Any person who does not wish, or is not qualified, to become a party to this proceeding may request permission to make a limited appearance pursuant to the provisions of 10 CFR 2.315(a). A person making a limited appearance may make an oral or written statement of position on the issues, but may not otherwise participate in the proceeding. A limited appearance may be made at any session of the hearing or at any prehearing conference, subject to such limits and conditions as may be imposed by the Atomic Safety and Licensing Board. Persons desiring to make a limited appearance are requested to inform the Secretary of the Commission by [INSERT DATE: 60 DAYS FROM THE DATE OF PUBLICATION OF THIS FEDERAL REGISTER NOTICE].
The Commission requests that each contention be given a separate numeric or alpha designation within one of the following groups: (1) Technical (primarily related to safety concerns); (2) environmental; or (3) miscellaneous.
As specified in 10 CFR 2.309, if two or more requestors/petitioners seek to co-sponsor a contention or propose substantially the same contention, the requestors/petitioners will be required to jointly designate a representative who shall have the authority to act for the requestors/petitioners with respect to that contention.
-6 All documents filed in NRC adjudicatory proceedings, including a request for hearing, a petition for leave to intervene, any motion or other document filed in the proceeding prior to the submission of a request for hearing or petition to intervene, and documents filed by interested governmental entities participating under 10 CFR 2.315(c), must be filed in accordance with the NRC E-Filing rule (72 FR 49139, August 28,2007). The E-Filing process requires participants to submit and serve all adjudicatory documents over the internet, or in some cases to mail copies on electronic storage media. Participants may not submit paper copies of their filings unless they seek an exemption in accordance with the procedures described below.
To comply with the procedural requirements of E-Filing, at least ten (10) days prior to the filing deadline, the petitionerl requestor must contact the Office of the Secretary bye-mail at HEARINGOOCKET@NRC.GOV, or by calling (301) 415-1677, to request (1) a digital identification (10) certificate, which allows the participant (or its counselor representative) to digitally sign documents and access the E-Submittal server for any proceeding in which it is participating; and (2) advise the Secretary that the participant will be submitting a request or petition for hearing (even in instances in which the participant, or its counselor representative, already holds an NRC-issued digital 10 certificate). Based upon this information, the Secretary will establish an electronic docket for the hearing in this proceeding if the Secretary has not already established an electronic docket. Information about applying for a digital certificate is available on NRC's public website at http://WWW.nrc.gov/site-help/e-submittals/appl'y:
certificates.html. System requirements for accessing the E-Submittal server are detailed in NRC's "Guidance for Electronic Submission," which is available on the agency's public website at http://www.nrc.gov/site-help/e-submittals.html. Participants may attempt to use other software not listed on the website, but should note that the NRC's E-Filing system does not support unlisted software, and the NRC Meta System Help desk will not be able to offer assistance in using unlisted software.
If a person is electronically submitting a document to the NRC in accordance with the E-Filing rule, the participant must file the document using the NRC's online, Web-based submission form. In order to serve documents through Electronic Information Exchange (EIE),
users will be required to install a Web browser 'plug-in from the NRC website. Further information on the Web-based submission form, including the installation of the Web browser plug-in, is available on the NRC's public website at http://www.nrc.gov/site-help/e submittals.htm!.
Once a participant has obtained a digital 10 certificate and a docket has been created, the participant can then submit a request for hearing or petition for leave to intervene.
Submissions should be in Portable Document Format (PDF) in accordance with NRC guidance available on the NRC public website at http://www.nrc.gov/site-help/e-submittals.htmI.Afiling is considered complete at the time the documents are submitted through the NRC's E-Filing.
system. To be timely, an electronic filing must be submitted to the E-Filing system no later than 11 :59 p.m. Eastern Time on the due date. Upon receipt of a transmission, the E-Filing system time-stamps the document and sends the submitter an e-mail notice confirming receipt of the document. The E-Filing system also distributes an e-mail notice that provides access to the document to the NRC Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the documents on those participants separately. Therefore, applicants and other participants (or their counselor representative) must apply for and receive a digital 10 certificate before a hearing request/petition to intervene is filed so that they can obtain access to the document via the E-Filing system.
A person filing electronically using the agency's adjudicatory E-Filing system may seek assistance by contacting the NRC Meta System Help Desk through the "Contact Us" link located on the NRC website at http://www.nrc.gov/site-help/e-submittals.html.by e-mail at MSHD.Resource@nrc.gov, or by a toll-free call at 866-672-7640. The NRC Meta System Help
-8 Desk is available between 8 a.m. and 8 p.m., Eastern Time, Monday through Friday, excluding government holidays.
Participants who believe that they have a good cause for not submitting documents electronically must file a motion, in accordance with 10 CFR 2.302(g), with their initial paper filing requesting authorization to continue to submit documents in paper format. Such filings must be submitted by: (1) first class mail addressed to the Office of the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention:
Rulemaking and Adjudications Staff; or (2) courier, express mail, or expedited delivery service to the Office of the Secretary, Sixteenth Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland, 20852, Attention: Rulemaking and Adjudications Staff. Participants filing a document in this manner are responsible for serving the document on all other participants.
Filing is considered complete by first-class mail as of the time of deposit in the mail, or by courier, express mail, or expedited delivery service upon depositing the document with the provider of the service. A presiding officer, having granted an exemption request from using E-Filing, may require a participant or party to use E-Filing if the presiding officer subsequently determines that the reason for granting the exemption from us of E-Filing no long exists.
Documents submitted in adjudicatory proceedings will appear in NRC's electronic hearing docket which is available to the public at http://ehd.nrc.gov/EHD/, unless excluded pursuant to an order of the Commission, or the presiding officer. Participants are requested not to include personal privacy information, such as social security numbers, home addresses, or home phone numbers in their filings, unless an NRC regulation or other law requires submission of such information. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, participants are requested not to include copyrighted materials in their submission.
Detailed information about the license renewal process can be found under the Nuclear Reactors icon at http://www.nrc.gov/reactors/operating/licensing/renewal.htmlon the NRC's
-9 Web site. Copies of the application to renew the operating license for SON are available for public inspection at the Commission's Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland 20852-2738, and at httQ://www.nrc.gov/reactors/oQerating/licensing/renewal/aQQlications.html. the NRC's Web site while the application is under review. The application may be accessed in ADAMS through the NRC's Public Electronic Reading Room on the Internet at httQ:llwww.nrc.gov/reading rm/adams.html under ADAMS Accession Number ML130240007. As stated above, persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS may contact the NRC PDR reference staff by telephone at 1-800-397-4209 or 301-415-4737, or bye-mail to PDR@nrc.gov.
Petitions filed after the deadline, amended petitions, and supplemental petitions will not be entertained absent a determination by the Commission, the Atomic Safety and Licensing Board Panel or a Presiding Officerthat the petition should be granted and/or the contentions should be admitted based upon a balancing of the factors specified in 10 CFR 2.309(c)(1 )(i)
(viii).
The NRC staff has verified that a copy of the license renewal application is also available to local residents near SON, at the Chattanooga-Hamilton County Library - Northgate Branch, 520 Northgate Mall, Chattanooga, TN 37415; the Chattanooga.:.Hamiiton County Library-Downtown Branch, 1001 Broad St., Chattanooga, TN 37402; and the Signal Mountain Library, 1114 James Blvd., Signal Mountain, TN 37377.
Dated at Rockville, Maryland, this 26th day of February, 2013.
FOR THE NUC R REGULATORY COMMISSION
/
/
~hn
- ubinski,
- rector Division of License Renewal Office of Nuclear Reactor Regulation
ML13044A700 (Package), ML13035A214(Letter),
ML13043A203(Federal Register Notice) ML13044A877 (Enc!. 1)
- concurred via email FFICE LA:RPB2:DLR*
PM:RPB1 :DLR BC: RPB1 :DLR PM:RPB2:DLR NAME DMorey ESayoc DATE 2/15/13 2/14/13 OFFICE D:DLR N
JLubinski 2/25/13 2/26/13 DATE
Letter to John T. Carlin from John W. Lubinski dated February 26, 2013
SUBJECT:
DETERMINATION OF ACCEPTABILITY AND SUFFICIENCY FOR DOCKETING, PROPOSED REVIEW SCHEDULE, AND OPPORTUNITY FOR A HEARING REGARDING THE APPLICATION FROM TENNESSEE VALLEY AUTHORITY, FOR RENEWAL OF THE OPERATING SEQUOYAH NUCLEAR PLANT UNITS ONE AND TWO DISTRIBUTION:
HARD COPY:
DLRRF E-MAIL:
PUBLIC [or NON-PUBLIC, if applicable]
RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRsrg Resource