ML12366A264

From kanterella
Jump to navigation Jump to search
IR 05000287-12-013; 05/07/2012 - 10/09/2012; Oconee Nuclear Station, Unit 3; Digital Instrumentation and Control Modification Inspection
ML12366A264
Person / Time
Site: Oconee Duke Energy icon.png
Issue date: 12/31/2012
From: Nease R
NRC/RGN-II/DRS/EB1
To: Gillespie T
Duke Energy Corp
Linda K. Gruhler 404-997-4633
References
IR-12-013
Download: ML12366A264 (21)


See also: IR 05000287/2012013

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

245 PEACHTREE CENTER AVENUE NE, SUITE 1200

ATLANTA, GEORGIA 30303-1257

December 31, 2012

Mr. T. Preston Gillespie, Jr.

Site Vice President

Duke Energy Corporation

Oconee Nuclear Station

7800 Rochester Highway

Seneca, SC 29672-0752

SUBJECT: OCONEE NUCLEAR STATION UNIT 3 - REACTOR PROTECTIVE

SYSTEM/ENGINEERED SAFEGUARDS PROTECTIVE SYSTEM (RPS/ESPS)

DIGITAL MODIFICATION - U.S. NUCLEAR REGULATORY COMMISSION

INSPECTION REPORT 05000287/2012013

Dear Mr. Gillespie, Jr.:

On October 9, 2012, the U. S. Nuclear Regulatory Commission (NRC) completed an inspection

at your Oconee Nuclear Station, Unit 3 reactor facility. The enclosed inspection report

documents the inspection results, that were discussed with you and other members of your

staff.

The inspection was performed in accordance with Inspection Procedure 52003, Digital

Instrumentation and Control Modification Inspection, and also focused on the list of

recommended Site Inspection Follow-Up Items outlined in the RPS/ESPS Safety Evaluation

dated January 28, 2010, (ADAMS Accession Number ML100220016). The inspection

examined activities conducted under your license as they relate to safety, compliance with the

Commissions rules and regulations, and with the conditions of your license. The team

reviewed selected procedures and records, observed activities, and interviewed personnel. No

findings were identified during this inspection.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter, its

Enclosures, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room, or from the Publicly Available Records (PARS) component of the

T. P. Gillespie, Jr.

2

NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA by Eric J. Stamm Acting For/

Rebecca L. Nease, Chief

Engineering Branch 1

Division of Reactor Safety

Docket No. 50-287

License No. DPR-55

Enclosure:

Inspection Report 05000287/2012013,

w/Attachment: Supplemental Information

cc: (See page 3 and 4)

T. P. Gillespie, Jr.

2

NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA by Eric J. Stamm Acting For/

Rebecca L. Nease, Chief

Engineering Branch 1

Division of Reactor Safety

Docket No. 50-287

License No. DPR-55

Enclosure:

Inspection Report 05000287/2012013,

W/Attachment: Supplemental Information

cc: (See page 3 and 4)

Distribution:

J. Bartley, RII, DRP

C. Rapp, RII, DRP

G. Ottenberg, RII, SRI

E. Elli, RII, SI

M. Endress, RII, RI

C. Evans, RII, EICS

L. Douglas, RII, EICS

RIDSNRRDIRS

PUBLIC

RidsNrrPMOconee Resource

X PUBLICLY AVAILABLE

G NON-PUBLICLY AVAILABLE G SENSITIVE X NON-SENSITIVE

ADAMS: X Yes

ACCESSION NUMBER: ML12366A264 X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED

OFFICE

RII:DRS

RII:DRS

RII:DRS

RII:CCI

RII:CCI

SIGNATURE

EJS2 for SAW4

EJS2 for RLN1

SXD7 via e-mail

SAW4 for CRS2 via e-mail

LSD2 via e-mail

NAME

S. WALKER

R. NEASE

S. DARBALI

S. SMITH-STANDBERRY

L. DUMONT

DATE

12/ 19 /2012

12/ 31 /2012

12/ 19 /2012

12/ 20/ 2012

12/ 20 /2012

E-MAIL COPY

YES

NO

YES

NO

YES

NO

YES

NO

YES

NO

OFFICIAL

RECORD

COPY DOCUMENT

NAME:

S:\\DRS\\DIGITAL

IC\\OCONEE

MODIFICATION\\OCONEE RPS-ESPS_2012013.DOCX

T. P. Gillespie, Jr.

3

cc:

Thomas D. Ray

Plant Manager

Oconee Nuclear Station

Duke Energy Corporation

Electronic Mail Distribution

James A. Kammer

Design Engineering Manager

Oconee Nuclear Station

Duke Energy Corporation

Electronic Mail Distribution

Robert H. Guy

Organizational Effectiveness Manager

Oconee Nuclear Station

Duke Energy Corporation

Electronic Mail Distribution

Terry L. Patterson

Safety Assurance Manager

Duke Energy Corporation

Electronic Mail Distribution

Kent Alter

Regulatory Compliance Manager

Oconee Nuclear Station

Duke Energy Corporation

Electronic Mail Distribution

Judy E. Smith

Licensing Administrator

Oconee Nuclear Station

Duke Energy Corporation

Electronic Mail Distribution

Joseph Michael Frisco, Jr.

Vice President, Nuclear Design Engineering

General Office

Duke Energy Corporation

Electronic Mail Distribution

M. Christopher Nolan

Director - Regulatory Affairs

General Office

Duke Energy Corporation

Electronic Mail Distribution

David A. Cummings (acting)

Fleet Regulatory Compliance & Licensing

Manager

General Office

Duke Energy Corporation

Electronic Mail Distribution

Alicia Richardson

Licensing Administrative Assistant

General Office

Duke Energy Corporation

Electronic Mail Distribution

Lara S. Nichols

Deputy General Counsel

Duke Energy Corporation

Electronic Mail Distribution

David A. Cummings

Associate General Counsel

General Office

Duke Energy Corporation

Electronic Mail Distribution

Division of Radiological Health

TN Dept. of Environment & Conservation

401 Church Street

Nashville, TN 37243-1532

Sandra Threatt, Manager

Nuclear Response and Emergency

Environmental Surveillance

Bureau of Land and Waste Management

Department of Health and Environmental

Control

Electronic Mail Distribution

Senior Resident Inspector

U.S. Nuclear Regulatory Commission

Oconee Nuclear Station

7812B Rochester Hwy

Seneca, SC 29672

Charles Brinkman

Director

Washington Operations

Westinghouse Electric Company

Electronic Mail Distribution

cc: (continued on page 4)

T. P. Gillespie, Jr.

4

cc: (continued from page 3)

County Supervisor of Oconee County

415 S. Pine Street

Walhalla, SC 29691-2145

W. Lee Cox, III

Section Chief

Radiation Protection Section

N.C. Department of Environmental

Commerce & Natural Resources

Electronic Mail Distribution

Enclosure

U. S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket No:

50-287

License No:

DPR-55

Report No:

05000287/2012013

Licensee:

Duke Energy Company

Facility:

Oconee Nuclear Station, Unit 3

Location:

7821 Rochester Highway

Seneca, SC 29672

Dates:

May 7, 2012 - October 9, 2012

Inspectors:

S. Walker, Senior Reactor Inspector, RII DRS (Lead)

S. Darbali, Technical Reviewer, NRR

L. Dumont, Construction Inspector, RII CCI

C. Smith-Standberry, Construction Inspector, RII CCI

Approved by:

Rebecca L. Nease, Chief

Engineering Branch 1

Division of Reactor Safety

SUMMARY OF FINDINGS

IR 05000287/2012013; 5/7/2012 - 10/9/2012; Oconee Nuclear Station, Unit 3; Digital

Instrumentation and Control Modification Inspection.

This inspection was conducted by a team of three NRC inspectors from the Region II office, and

one technical reviewer from the Office of Nuclear Reactor Regulation. No findings were

identified. The NRC's program for overseeing the safe operation of commercial nuclear power

reactors is described in NUREG-1649, Reactor Oversight Process, (ROP) Revision 4, dated

December 2006.

REPORT DETAILS

Background Information

On January 31, 2008, Duke Energy Carolinas submitted a first-of-a-kind license amendment

request to upgrade the Oconee Nuclear Station to a digital Reactor Protective System (RPS)

and Engineered Safeguards Protective System (ESPS). The proposed amendment would allow

replacement of the existing Bailey Meter Company analog, solid-state design, RPS/ESPS with a

digital computer based TELEPERM XS (TXS) platform at Oconee Units 1, 2 and 3. The digital

RPS/ESPS would provide signal processing, signal validation, and protection logic function for

these systems.

NRR approved the LAR and issued a safety evaluation report (SER) dated January 28, 2010

(ML100220016). NRR conducted an evaluation of the license amendment as part of the normal

review process. This included a review of the design and capabilities of the modification.

Regional inspectors were tasked with performing documentation and functionality reviews after

the system left the vendor in accordance with Inspection Procedure 52003.

In addition, the SER discussed inspection activities (Section 3.14., Regional Activities) for the

digital RPS/ESPS that would be addressed by the NRC regional office during site acceptance

testing, installation, startup testing, and operation of the system. The activities, referred to as

inspection follow-up items, were intended to verify licensee activities that were not part of the

licensing process, but were related to the safe operation of the digital RPS/ESPS system. The

bases for the inspection activities were derived from Chapter 7 of the Standard Review Plan

(SRP), and explained in detail throughout the SER.

Region II developed a site-specific inspection plan to select and review the activities associated

with the major phases of the digital I&C modification. Region II observed portions of testing,

installation, and operation of the RPS/ESPS modification on Unit 1 in 2011. This included a

sample of inspection requirements involving four major areas of effort: (1) developing an

understanding of the modification design; (2) documentation verification; (3) review of testing,

operations, and training; and (4) a review of plans for maintenance and repair efforts. The

results of the inspection were documented in Inspection Report 05000269/2011011

(ML 12069A088).

This report documents the inspection results for the RPS/ESPS modification on Unit 3. For the

Unit 3 review, the site-specific inspection plan included an emphasis on: 1) review of corrective

action program (CAP) documents to ensure lessons learned and operating experience had

been properly captured and implemented; and 2) additional emphasis was considered for those

licensee activities that included new or different management controls, or were being

managed/controlled in a different manner, or implemented with new techniques.

Because the SER was applicable to all three units, many of the inspection follow-up items that

were previously reviewed during the Unit 1 inspection effort were not reviewed again.

4

4.

OTHER ACTIVITIES

4OA5 Other Activities - Digital Instrumentation and Control Modification Inspection (52003)

.1

Design Review

.1.1

Full Scope Modification

a. Inspection Scope

The team reviewed all the documentation required to gain a working knowledge of the

digital instrumentation and control (I&C) modification including, but not limited to: the

staffs SER; any licensing commitment documents; manufacturers literature on the

hardware and software being installed; and applicable drawings and schematics. In

addition, the team reviewed design specification attributes including design architecture,

input consolidations, isolation and interface devices, affected indicators, and the credited

function of the system to verify proper system requirements were met and/or maintained

during installation.

The team discussed several changes the licensee made during the Unit 1 installation to

verify that they were appropriately captured in the Unit 3 scope. The team also reviewed

the Unit 3 modification project plan to determine if any changes following installation on

Unit 1 had been appropriately evaluated.

b. Observations and Findings

No findings were identified. The team determined that given the complexity and large

scale of the modification, the licensee adequately implemented the full scale design.

The team reviewed Problem Investigation Program (PIP) O-11-8106 documenting the

licensees lessons learned from Unit 1, and observed that the Integrated Test performed

on Unit 1 was not being performed on Unit 3, or following installation on Unit 2 in 2014.

The PIP stated that the Unit 3 modification test plan should outline the purpose for the

integrated test performed on Unit 1, and the necessary justification to support not

performing the test on Unit 3. When the team reviewed the Unit 3 mod test plan, it was

noted there had been no justification for not performing the test. The team questioned

whether there were components or features that would not be tested due to removal of

the integrated testing. Following discussions, the licensee revised the modification test

plan to document that the integrated test performed on Unit 1 was to be a final

demonstration of what was considered to be the worst cases for the network loading and

power supply loading with all ES channels tripped and six of 10 RPS trips generated.

This test scope was not required by the SER, or by the post-modification testing

requirements. Software integration and loading of the TXS cabinet power supplies

was demonstrated by Factory Acceptance Testing, Site Acceptance Testing, and

post-modification verification and functional tests. The team found the justification

acceptable.

5

.1.2

Modification Schedule

a. Inspection Scope

The team reviewed the licensees proposed schedule for implementation to verify the

licensee properly evaluated any associated shutdown risk due to modification

implementation and emergent changes to the schedule. The team reviewed the

licensees modification plan to verify whether the implementation would be done in

conjunction with shutdown risk activities, such as a complete core offload or mid-loop

operations. The team reviewed and assessed the emergent issues to evaluate the

potential impact on the overall implementation and testing schedule.

b. Observations and Findings

No findings were identified. The team determined the licensee adequately scheduled

installation, maintenance, and testing appropriate to the circumstances. As emergent

issues arose, the licensee would prioritize issues utilizing safety and risk insights. The

team determined the licensee incorporated lessons learned from the Unit 1 installation

which provided for more effective scheduling.

.2

Documentation Review

.2.2

Procedure Review

a. Inspection Scope

The team performed, on a sampling basis, a review of the licensee procedures affected

by the modification of the RPS/ESPS system. PIPs were reviewed to verify issues that

arose during installation that may affect procedural guidance were appropriately entered

into the CAP and resolved.

The inspection consisted of the review of surveillance, abnormal operating, emergency

operating, annunciator response, maintenance, and testing procedures that were

updated for Unit 3. These procedures were reviewed in order to assure that they

accurately reflected Unit 1 implementation; any new systems attributes; and were in

accordance with the design commitments and technical specifications. The team was

provided a list of changes made to Unit 3 RPS/ESPS versus Unit 1 installation, which

included the approved scope of the Unit 3 engineering changes and the associated

PIPs. There were several PIPs reviewed from this list to confirm adequate changes

were made to the Unit 3 and associated procedures. The team also reviewed the

engineering change (EC) documents for the RPS and ESPS project (EC 77069 and

EC 77070).

b. Observations and Findings

No findings were identified.

6

Procedures:

The team determined that the RPS/ESPS Maintenance, Testing, and Operation

procedures reviewed for Unit 3 were adequate and consistent with Unit 1, the design

capability, and plant specifications. Any modifications that were made on Unit 3 and

differed from Unit 1 were reflected in the Unit 3 procedures.

The team requested several operational procedures from the licensee in order to verify

that the test machine, which is a portable unit that can be used to perform calibration

checks and logic tests on TXS systems, was correctly identified in the procedures. The

licensee staff stated that the test machine was not incorporated in their operation

procedures because they have no plan to use the unit in the future. The team also

determined that the implementation of the Technical Specifications (TS), applicable

licensee standards, and vendor recommendations were appropriately integrated in the

sampled calibration procedures.

The team reviewed several PIPs (listed in the Documents Reviewed section of this

report) that were listed on a requested lessons learned list of Unit 1 issues. These PIPs

were written as a result of various issues discovered during Unit 1 installation of the

RPS/ESPS system, and some required hardware modifications or procedure changes,

as resolution. Affected procedures that were listed in the PIP were reviewed by the

team to verify described changes were actually implemented in the procedure, and were

similar to those changes of Unit 1 procedures.

The team identified some differences in the Unit 3 procedures; however, interviews with

the licensee staff revealed that these differences were either new modifications planned

for Unit 3, which will be implemented on Unit 1 at a later date; or they were minor

changes that would only be specific to Unit 3. The changes that were relevant to the

human factors of the Graphical Service Monitors (GSM) were verified by inspectors,

because according to the written PIPs, the GSM for Unit 1 required several modifications

that have not yet been implemented on Unit 1. According to the licensee, the required

changes for Unit 1 have been captured and will be reflected in the continuous use

procedures for Unit 3 by use of notes to point users to differences for Unit 3. The work

to implement the changes on Unit 1 is scheduled for the next outage date. The

inspectors interviewed training personnel to verify that maintenance personnel were

trained in the differences between the systems on each unit. According to the licensee,

the training did not have to be repeated because the same user skill set required for Unit

1 is used for Unit 3. For other changes implemented, the users are able to refer to

procedures, as well as the Users Manual and training was not required.

Configuration Management:

On Unit 1, the licensee failed to perform adequate post modification testing to evaluate

the adequacy of a design modification to the RPS/ESPS, and allowed an improper wiring

configuration of the nuclear instrumentation (NI) Power Range detector cables affecting

all four RPS channels (LER 05000269/2011-05-01). The team determined the licensee

took appropriate corrective actions to prevent this from happening on the Unit 3

RPS/ESPS modification.

The team conducted interviews and was provided with the corrected drawings and

procedures for Unit 3. The design drawings used for the connection of the NI cables

7

were modified to show in more detail the connection points for each cable. Procedure

TN/3/A/77070/001, Reactor Protective System Replacement Modification, was

modified to show proper labels for the cable terminations, and new signature blocks for

implementation management and engineering oversight were added. A new continuity

test sequence for Power Range NIs was added to procedure TN/3/A/77070/001. A new

section was also added to procedure TN/3/A/77070/002, Functional Checkout of Unit 3

RPS Replacement Modification, to include the Power Range NI, and hot leg cable

testing.

The team inspected the RPS Channel A cabinet 1 (3PPSCA0001) to verify that the

Power Range connection for 3NI-5 was performed according to drawing O-2781, Rev.

16E. The team concluded that the connection of triaxial cables JC and JA was

performed according to the drawing.

Bend Radius:

During the Unit 1 installation and inspection, the team noted that the four channels of the

RPS system had wires (e.g., Okonite model 3BA-12U) that had appeared to have

exceeded the allowable bend radius. The inspectors determined that the training radius

for the wire, as specified by the manufacturer, was four times the outer diameter (4xOD)

of the wire. The licensee documented this issue in the CAP as PIP O-11-6850. The

licensee concluded that guidance for recommended target minimum bending radius for

individual insulated conductors within enclosures would be added to the procedures for

making cable terminations, as well as included in the pre-job briefings for such work.

Just prior to the inspection teams arrival onsite for the Unit 3 inspection, the licensee

discovered the procedures had not been properly updated. As a result, the licensee

issued PIP O-12-5512 and conducted a walkdown to determine if there were any wires

that exceeded their bend radius. The results of the inspections identified five examples

of wires that were bent more than needed; however, the licensee noted none of the

examples were reported as being less than the 4xOD limit. A follow-up walkdown was

performed by the inspection team. The team inspected ES cabinets 3PPSCA0017,

3PPSCA0018, and 3PPSCA0010; and RPS cabinets 3PPSCA0001 and 3PPSCA0002,

for potential bend radius issues on cables and conductors. The team observed several

examples of inadequate bend radius (most notable in RPS cabinet 3PPSCA0001) that

were less than 4xOD.

The team identified that the licensee did not adequately incorporate acceptance criteria

for bend radii of low voltage cables as a result of an NRC issue identified during Unit 1

RPS Installation. Specifically, the NRC identified that the governing procedures for

conductor installation (DPS-1390.01-00-003 and IP/0/A/3009/017,Wire Terminal

Installation, Labeling, and Termination 600V or Less, Rev. 35), did not have specific

guidance to verify bend radii for single conductor cables that could cause degradation.

The licensee conducted a subsequent follow-up inspection and provided an update to

PIP O-12-5512; where they listed the conductors, (approximately 54, excluding spares

and shields), that were identified to have a small bend radius, (between 1xOD and

2xOD), and were subsequently corrected (to 4xOD or greater) per work orders. The

licensee stated that they had no plans to correct any spare or shield cables that may

8

have inadequate bend radii. The inspectors noted that spare cables should be tested

prior to being used to ensure no damage has occurred due to an inadequate bend

radius.

Based on the information collected and evaluations performed, the licensee determined

the minimum bend radius to be 2xOD for individual conductors 10AWG and smaller,

serving low voltage, low current instrumentation and controls circuits. The licensee

stated conductors for power feeder cables shall follow vendor recommended bend

radius values; and conductors for lw voltage, low current I&C cables should be not less

than 2xOD minimum bend radius; unless restricted by vendor qualification reports.

Following several discussions and review of the evaluations performed by the licensee,

the team found the licensees position on bend radius acceptable. Because the system

had not returned to service at the time of discovery, the as-found cables were not

considered degraded, and the licensee took immediate corrective actions, the team

considered this issue appropriately resolved.

Panel Wiring:

The inspection team performed spot checks to verify cable terminations on the RPS and

ESPS cabinets were being performed according to the drawings. The team inspected

the following cabinets, terminals, and drawings:

For RPS cabinet 3PPSCA0001, the team looked at terminal blocks X011 and

X111 and compared them with drawing O-2781, Rev. 16E (Interconnection

Diagram Nuclear Instrumentation and Reactor Protection System Cabinet

3PPSCA0001)

For RPS cabinet 3PPSCA0002, the team looked at terminal blocks X023, X026,

and X122 and compared them with drawing O-2781-02, Rev. C (Interconnection

Diagram Nuclear Instrumentation and Reactor Protection System Cabinet

3PPSCA0002); and terminal block X016 and compared it to drawing O-2781-03,

Rev. D (Interconnection Diagram Nuclear Instrumentation and Reactor

Protection System Cabinet 3PPSCA0002)

For ESPS cabinet 3PPSCA0017, the team looked at terminals 53 and 56

on terminal block 121 and compared it with drawing O-2757-G, Rev. 18C

(Connection Diagram Engineering Safeguards Cabinet 3PPSCA0017); and

terminal blocks X112, TB-5, and TB-6 and compared them to drawing

O-2757-G-001, Rev. D (Connection Diagram Engineering Safeguards Cabinet

3PPSCA0017)

For the terminals checked, the inspectors concluded that the wiring for those terminals

was correct. The team conducted interviews and went through the work order that was

used to perform the terminations for RPS cabinet 3PPSCA0001. The team noted that

compared to the RPS/ESPS cabinets on Unit 1, the cabinets on Unit 3 were wired in a

much more organized manner. The licensee attributes this to giving 'ownership' of each

cabinet to a group of electricians, and having only them work on those cabinets. The

licensee incorporated this format based on lessons learned from Unit 1.

9

.2.3

Design Bases Document Review

a. Inspection Scope

The team conducted sample reviews of the Updated Final Safety Analysis Report

(UFSAR), design basis documents, TSs, and plant drawings to verify that design basis

documents were adequately updated to reflect the replacement RPS/ESPS system.

b. Observations and Findings

No findings were identified. The team noted that the design basis documents were

adequately updated to reflect the new system and associated design changes. The

team also reviewed the UFSAR change summary package and observed the

subsequent UFSAR revision included the appropriate updates to reflect the design

changes to Unit 3. Because this modification is being installed on each one of the units

in phases, the UFSAR revision did not specifically denote which unit was modified;

rather it generically addressed units as either a unit with the RPS installed or not

installed.

During the Unit 1 installation, the team observed the ES changes and the UFSAR

change packages referenced IEEE 279, Criteria for Protection Systems for Nuclear

Power Generating Stations, however, the new RPS/ESPS is licensed to IEEE 603,

IEEE Standard for Safety Systems for Nuclear Power Generating Stations. The

licensee captured this issue in the CAP as PIP-O-11-6663. The team reviewed the

status of this PIP and found the licensee took appropriate corrective actions to update

the UFSAR.

.3

Testing, Operations, and Training

.3.1

Software Testing Plan

a. Inspection Scope

The team reviewed the installation and startup test procedures for the RPS/ESPS

systems to assess whether the procedures ensured that the as-installed modifications

were consistent with the SER, the design drawings, and the licensees commitments.

Any changes or deviations from Unit 1 were noted and discussed with the licensee to

understand the purpose of any changes and to ensure the design and licensing bases

were maintained. The team performed field reviews of the modification of the digital

RPS/ESPS system, which was in the process of being installed and tested on Unit 3.

The team observed portions of the installation testing, including component checks,

functional testing, and start-up testing to verify the testing plan was adequate in

identifying proper design implementation. The team assessed whether the procedures

were clear and sufficiently detailed enough to allow site personnel to perform the tests.

The team observed portions of the Unit 3 ES Voter Actuation Testing on the Even Voter.

The licensee used procedure TN/3/A/77069/002, ES Post-Modification Functional

Verification, and inspectors observed Subsection 4.4.13.42 through 4.4.13.66 to verify

the testing was adequately performed and the test procedure was properly followed.

The Unit 3 ES Test modification plan (770609) was also reviewed in order to verify that

the performed testing procedure used was included in the plan.

10

The team reviewed several PIPs (listed in the Documents Reviewed section of this

report) associated with user document reviews of the RPS/ESPS system given that user

documentation evaluations were considered by the NRC staff to be necessary

components of acceptable methods for meeting the requirements of Appendices A and

B to 10 CFR Part 50 and were not available at the time of the SER.

The team reviewed Duke Energys Nuclear System Directive 106, Configuration

Management, to ensure that software installation and test procedures were developed

by the licensee, in accordance with this directive which assures systems, structures, and

components are operated, maintained and modified within their design basis. The team

reviewed procedure IP/3/A/0315/026, TXS (Teleperm XS) Service Unit Software

Loading, to verify that limitations were put in place to prevent the development of new or

modified operational software on the service unit since such actions were not approved

in the SER. The inspection team discussed software limitation mechanisms with the

licensee to further understand what level of privilege that is required, and who from the

staff has such privilege to load the system or application software.

The team reviewed a number of licensee site-specific documents that described the

Software Life Cycle process associated with the TXS from the Digital System

Specification (ODSS-0806-PPS.0003) document. The Digital System Specification

described the recommended requirements as well as the responsibilities to ensure that

RPS/ESPS provides intended results. The team assessed the Digital System

Specification document to verify that it met the requirements of Branch Technical

Position 7-14 (BTP 7-14).

b. Observations and Findings

No findings were identified. The team observed installation testing, functional testing,

and system start-up testing. The team found that the test plans assured adequate

controls to implement the modification. The team found that the licensee addressed any

potential issue according to its safety and risk significance. The team observed the

RPS/ESPS system start-up test and that it had functioned properly. It was noted that

some inputs could not be simulated during the testing stages, and would only be verified

during actual plant startup. These inputs were assessed and determined to be not

safety significant, and would cause no increase to public health and safety if not tested

prior to startup. The team determined the licensee adequately performed testing which

was in accordance with the Unit 3 ES testing procedures and that the testing procedures

were detailed and clear.

The team observed that the licensee employed a two-phase process to assess their end

user documentation associated with the RPS/ESPS system. First, a document review

phase was performed in 2008 in preparation for the Unit 1 project. Then, Verification &

Validation (V&V) document evaluation activities in accordance with procedure, Nuclear

System Directive 705, were accomplished to demonstrate proper translation of the TXS

User Manuals into their end user procedures. The team reviewed PIPs that outlined the

different types of issues identified, and the action taken to resolve them, during the

document review phase and the V&V document evaluation phase.

During the inspection, the team determined that the Software Operations Plan of the

Digital System Specification ODSS-806.0003 Attachment F-1, did not clearly define how

the licensee would restrict unauthorized changes to the hardware. In addition, the team

11

could not find any provisions on how the licensee would respond to security problems.

In accordance with BTP7-14, these measures are to be defined in the licenses Software

Operations Plan. The inspector could not assess the software Installation Process

which describes the installation process, the goals of that process, and a general

description of the environment, (such as temperature, humidity, vibration, and rack

space), within which the computer system and software system is qualified to operate.

The licensee demonstrated that this specific information was captured appropriately in

other documents. The licensee captured this issue in the CAP as PIP O-12-6592.

3.4

Personnel Training

a. Inspection Scope

The team reviewed training documents and interviewed personnel to verify that

operators, technicians, and system engineers had been adequately trained and have

an understanding of the system commensurate with their responsibilities.

b. Observations and Findings

No findings were identified. Following review of relevant documents, the team

determined the licensee underwent appropriate training in preparation for

implementation of the RPS/ESPS modification. The team reviewed the ongoing training

requirements and documents, specifically on Go/NoGo Testing and GSM Functional

Testing. The licensee stated training procedures for Unit 1 and Unit 3 were taken from

the GSM User Manual. There was no required retraining for Unit 3 maintenance

personnel because the User Manual and Operating procedures had been updated with

any major differences.

3.5

Hardware and Software Failures

a. Inspection Scope

The team reviewed test incident reports and PIPs to verify the licensee was

appropriately capturing hardware and software failures that occurred, and that the issues

were properly resolved.

b. Observations and Findings

No findings were identified. The team determined the licensee utilized an appropriate

threshold for entering issues into the CAP. The team followed up on several PIPs

identified during the Unit 1 installation and found them to have had adequate resolution

(the issue with inadequate bend radius was an exception). The team noted that the

licensee documented several new issues related to the implementation of the system,

categorized each issue based on its significance, proposed appropriate corrective

actions, and documented the resolution(s). The issues were appropriately entered into

the CAP as PIPs (during the SAT, issues discovered were documented as test incident

reports), and subsequently tracked separately in accessible tables. The licensee also

reviewed the issues to determine mode applicability to ensure design basis limits and

commitments (i.e., TS LCO) were maintained.

12

3.8

Indication and Annunciation

a. Inspection Scope

The team reviewed procedures, performed walkdowns, and observed control room

operations and testing; to verify proper indication and annunciation for system failures,

and system bypass were functional, and met the licensing basis as stated in the SER.

b. Observations and Findings

No findings were identified.

4OA6 Meetings, Including Exit Meeting

Exit Meeting Summary

The inspection team presented the inspection results to the staff during an exit with

members of licensee management on October 9, 2012. The inspectors asked the

licensee if any of the material examined during the inspection should be considered

proprietary and no proprietary information was identified.

ATTACHMENT: SUPPLEMENTAL INFORMATION

Attachment

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

M. Bailey, I&C Systems Manager

J. Bryan, OMP RPS/ES Engineering Supervisor

J. Ledbetter, RPS/ES Maintenance Training Supervisor

B. Loftis, RPS/ES Subject Matter Expert

W. MacIntyre, Operations Tech Support Supervisor

B. Shingleton, Regulatory Compliance

B. Thomas, RPS/ES Outage Coordinator

NRC

A. Sabisch, Senior Resident Inspector

R. Stattel, Senior Technical Reviewer, NRR

2

Documents Reviewed

Procedures

NSD 106, Configuration Management, Rev. 6

NSD 705, Instructions for the Verification and Validation of Technical Procedures Rev. 7

PT/0/B/0115/009, Key Verification, Rev. 069

PT/0/A/0600/001 A, Loss of Computer, Rev. 030

TN/1/A/90423/002, Functional Checkout of Unit 1 ES Replacement Modification, Rev. 001

AM/1/A/0315/017, TXS RPS Channels A, B, C, and D Parameter Changes for Abnormal/Normal

Operating Conditions, Rev. 0

TN/3/A/77069/002, Functional Checkout of Unit 3 ES Replacement Modification, Rev. 2

TT/3/A/77069/001, Unit 3 ESPS Startup Functional Test, Rev. 0

PT/3/A/0202/012, Component Test of ES Channels 1 & 2, Rev. 23

OP/3/A/1102/001, Controlling Procedure for Unit Startup, Rev. 253

PT/0/A/0711/001, Zero Power Physics Testing, Rev. 63

PT/0/A/1103/020, Power Maneuvering Predictions, Rev. 21

IP/3/A/0315/001G, TXS Plant Protective System Cabinet ON3PPSCA0011 Power Up, Rev. 0

IP/3/A/0315/001J, TXS Plant Protective System Cabinet ON3PPSCA0016 Power Up, Rev. 0

IP/3/A/0315/011 B, TXS RPS 3NI-6 Power Range Instrument Calibration, Rev. 1

IP/3/A/0315/011 C, TXS RPS 3NI-7 Power Range Instrument Calibration, Rev. 1

IP/3/A/0315/011 D, TXS RPS 3NI-8 Power Range Instrument Calibration, Rev. 1

IP/3/A/0315/026, TXS Service Unit Software Loading, Rev.0

Calculations and Miscellaneous Documents

EC 77070, U3 RPS Engineering Change and Modification Test Plan, Rev. 3

EC 77069, U3 ESFAS Engineering Change and Modification Test Plan, Rev. 2

EC 90423, U1 ESFAS Engineering Change and Modification Test Plan, Rev. 2

EC 90482, U1 RPS Engineering Change and Modification Test Plan, Rev. 2

ODSS-0866.PPS.0001, Digital System Specification, Rev. 0

OSC-3348, RPS/ES Failure Modes and Effects Analysis Summary Calculations, Rev. 6

OM 201.N-0024.005, Oconee Nuclear Station, Unit 1 RPS/ESFAS Controls Upgrade Software

Design Description, Rev. 012

ODSS-0806.PPS.0001, Unit 1 TXS Reactor Protection System and Engineered Safeguards

Software (RPS/ES)

ODSS-0806.PPS.0003, Digital System Specification (dated 11/14/2011), Rev. 0

Unit 3 RPS/ES Equipment Management Plan (EMP), Rev. 0

Maintenance and Test Facility (MTF) Control/Access Agreement for Unit 3 RPS/ES, Rev. 0

Drawings

O-2781, Interconnection Diagram Nuclear Instrumentation and Reactor Protection System

Cabinet 3PPSCA0001, Rev. 16E

O-2781-02, Interconnection Diagram Nuclear Instrumentation and Reactor Protection System

Cabinet 3PPSCA0002, Rev. C

O-2781-03, Interconnection Diagram Nuclear Instrumentation and Reactor Protection System

Cabinet 3PPSCA0002, Rev. D

O-2757-G, Connection Diagram Engineering Safeguards Cabinet 3PPSCA0017, Rev. 18C

O-2757-G-001, Connection Diagram Engineering Safeguards Cabinet 3PPSCA0017, Rev. D

3

Codes & Standards

IEEE Std. 603-1998, Standard for Safety Systems for Nuclear Power Generating Stations

IEEE Std. 7-4.3.2-2003, Standard Criteria for Digital Computers in Safety Systems of Nuclear

Power Generating Stations

RG 1.152, Criteria for Digital Computers in Safety Systems of Nuclear Power Plants

PIPs Reviewed

O-08-06242, Maintenance Manual Volume 1

O-08-06243, Maintenance Manual Volume 3

O-08-06245, Maintenance Manual Volume 2

O-08-00789, Maintenance Manual Volume 4

O-09-06059, Bitable Removal

O-09-05857, Maintenance Manual Volume 3

O-09-06746, Maintenance Manual Volume 4

O-10-07591, Bitable Removal O-10-08224, Software Loading

O-10-04983, No requirements for how OAC determines health of data from RPS/ES TXS

cabinets

O-10-10037, Problem discovered in validation of IP/1/A/0315/080 Go Test

O-11-07081, Rolled leads for Upper and Lower core flux detectors

O-11-05900, Procedure issues during ES Even Voter Alarm Test

O-11-05756, RPS/ES Ne Optics Port Tap Dip Switch settings

O-11-05635, Diverse HPI/LPI Bypass position but no stat alarms

O-11-04487, TXS cabinets 17 & 18 are to be electrically isolated from Bailey ACS cabinets

O-11-05512, Procedure error identified during power up of ES Cabinet 16

O-11-05593, Unexpected stat alarms received that clear at power up

O-11-10361, GSM Screens do not provide consistent results

O-11-00946, Additional work needed to meet Tech Spec Surveillance requirements

O-11-00279, Inadequate reflash capability exists in hardware design of ES Voter

O-11-04841, Loss of Manual Bypass Statalarm on loss of SVE2 software

O-11-06889, IC1 and IC2 ES Trouble Alarms locked in

O-11-06872, Unit 1 control room receiving RPS Trouble statalarms

O-11-06062, IEC26 RPS/ES Testing Issue

O-11-04902, U1 RPS/ES Fire break material cannot be installed as designed

O-11-04259, Rework of Fire Penetration 1CF-56/54

O-11-05827, ES 1A WR Pressure out of cal

O-11-05554, Testing delays due to unexpected statalarm actuations and incorrect statalarm

indications

O-11-05866, ES-6 Trip Alarm not received as expected during testing

O-11-05916, Polarity is reversed for RPS Channel E RC Flow transmitters

O-11-06097, During the design phase of the RPS/ES project for Unit 1, the rewiring of events

recorder was not designed per the wiring convention used at ONS

O-11-06663, Revise UFSAR change package for RPS/ES to refer to IEEE 603

O-11-07865, Received 1C RPS Trouble and OAC Alarm 1C RPS Hot Leg Temperature

O-11-08016, Documentation of 1EOC26 RPS/ES Lessons Learned

O-12-04855, Prompt Investigation Response Team Report for PIP O-12-4580

O-12-04852, Unit 3 ES/RPS Unexpected voltage found on 3UB2

O-12-04143, Unit 3 ES/RPS Voltage found in 3B2 RCPPM cabinet during zero energy checks

O-12-03846, This PIP documents the actions being taken to address the need to replace the

499 ohm resistors for the Units 1, 2 and 3 RPS and ES, based on SVT approval of the

requested change

O-12-06591, Unit 3 NI-2 SR Level signal for Refueling and ZPPT areas reading negative value

4

O-12-03442, An additional problem identified with 499 ohm 0.1% precision resistors in U1

O-12-06526, Discussion on QA condition of PSW pressurizer heater cables - separation issue

O-12-05512, Inadequate bend radius in ES and RPS cabinets

O-12-06439, Oconee RPS/ES system cyber security issue

PIPs Generated Due to Inspection:

O-12-04609, New labels for RPS Cabinets 5 & 6 are incorrect

O-12-06592, Enhancements needed to RPS/ES Software Operations Plan