WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov]

Sent: Monday, August 27, 2012 7:49 AM To: Poole, Justin; Bryan, Robert H Jr; Arent, Gordon Cc: Boyd, Desiree L; Templeton, Pamela J

Subject:

2012-08 WBN Project Plan - Unit 2.pdf Attachments: 2012-08 WBN Project Plan - Unit 2.pdf Please see attached for todays 9:15 phone call.

Thank you,

~*~*~*~*~*~*~*~*~*~*~

Désireé L. Boyd WBN Unit 2 Licensing dlboyd@tva.gov 423-365-8764 1

Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 734 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF319038DB)

Subject:

2012-08 WBN Project Plan - Unit 2.pdf Sent Date: 8/27/2012 7:48:44 AM Received Date: 8/27/2012 7:48:47 AM From: Boyd, Desiree L Created By: dlboyd@tva.gov Recipients:

"Boyd, Desiree L" <dlboyd@tva.gov>

Tracking Status: None "Templeton, Pamela J" <pjtempleton@tva.gov>

Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>

Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov>

Tracking Status: None "Arent, Gordon" <garent@tva.gov>

Tracking Status: None Post Office: TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 250 8/27/2012 7:48:47 AM 2012-08 WBN Project Plan - Unit 2.pdf 208400 Options Priority: Standard Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date:

Recipients Received:

WBN UNIT 2 PROJECT PLAN: 08/27/2012 Page 2 of 36 I. SUBMITTAL LOOK-AHEAD Item No. Description Resp. Person Due Date License Amendments / Technical Specifications

1. Common Service Station Transformer (CSST) A & B Credit Shea October 12, 2012 SSER Open Item 32:
2. Hilmes January 13, 2013 Revise Diesel Generator Frequency Allowable Value. [Commitment 113676066]

SSER Appendix HH Open Items (requiring submittal)

SSER Open Item 1:

Following completion of cable pulls, submit letter to NRC either:

1.
  • Affirming no power assisted cable pulls were made, or Hilmes January 17, 2014
  • Documenting any power assisted cable pulls.

[Commitment 113676047]

SSER Open Item 13:

2. Submit an ASME Section XI Inservice Test Program for the first ten year interval McDonald / Crouch June 12, 2014 six months before receiving an Operating License. [Commitment NCO080008033:

Item 017 of Enclosure 2 of letter T90 080128 001]

SSER Open Item 25:

3. Submit documentation of liability insurance coverage pursuant to 10 CFR 140.11(a)(4). Arent June 27, 2014

[Commitment 113676162]

SSER Open Item 37:

4. Submit changes to the Emergency Plan (REP) prior to fuel load. Detchemendy November 15, 2013

[Commitment 111032952]

SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 08/27/2012 Page 3 of 36 Item No. Description Resp. Person Due Date SSER Open Item 41:

5. Update Plant design displays & dose assessment models to provide two unit capability. Hilmes / Koontz November 15, 2013

[Commitment 111033086]

SSER Open Item 43:

6. Submit Emergency Plan implementing procedures no less than 180 days before schedule Detchemendy November 15, 2013 issuance of Operating License. [Commitment ____________]

SSER Open Item 61:

7. Fuel Thermal Conductivity Degradation Model (PAD Code) - Note: currently this is a Koontz October 26, 2012 License Condition - tracking PWROG activity to update code. [Commitment 113676152]

SSER Open Item 70:

8. McDonald / Crouch September 28, 2012 Submit Pre-Service Inspection program update. [Commitment 113676155]

SSER Open Item 81:

Provide Electronic Filter Test Results for General Atomic High Range Rad Monitor.

[Commitment 113676079]

9. Hilmes August 31, 2012 MIL Std 461-E low frequency susceptibility testing from 30 Hz to 150 kHz of the I/F converter will be completed and a test report submitted. [Commitment 113442002]

SSER Open Item 79:

Perform an EMI survey of the containment high range radiation monitors after they are

10. Hilmes March 4, 2014 installed in WBN Unit 2, and submit the results to the NRC within two weeks of the survey being completed. [Commitment 112177753]

SSER Open Item 83:

11. Provide Letter verifying completion of data storm test on DCS. Hilmes August 30, 2013

[Commitment 113676093]

SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 08/27/2012 Page 4 of 36 Item No. Description Resp. Person Due Date SSER Open Item 132:

x Submit letter documenting that plant modifications to add high VCT level alarm to main control room annunciator system have been completed. [Commitment 113111704]

12. Arent / Wallace May 24, 2013 x Submit letter documenting that procedure changes associated with limiting the number of operating primary water pumps and isolating potential boron dilution paths have been made. [Commitment 113111705]

SSER Open Item 134:

13. Provide resolution of dam stability analysis for Cherokee and Douglas Dams finite element Stockton August 31, 2012 analysis.

Submit a Technical Specification and Bases change package to TVA Licensing to change Table 3.3.3-1, Line item 6 (Reactor Vessel Water Level) to remove the reference to

14. note (g) and bases to show RVLIS as a Type A variable. Stockton August 27, 2012 PER 488815 [Commitment 113307292]

SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 08/27/2012 Page 5 of 36 Item No. Description Resp. Person Due Date Other Submittals

1. As-Constructed Fire Protection Report [Commitment 113461862] Hilmes July 18, 2014
2. U2 FSAR With As-Constructed Figures [Commitment 112068531] Arent September 12, 2014 Prior to fuel load, a final report will be submitted following certain validation activities as
3. Koontz / Enis July 18, 2014 described in the IPEEE Design Report (Enclosure 1). [Commitment 111027893]

TVA will provide the NRC staff an updated [security] classification scheme that reflects

4. these changes for WBN Unit 2. [Commitment 111033038: RAI Response 3.r of Reynolds May 23, 2014 Enclosure 2. of Letter T02 100427 001]
5. Submit a merged U2 FSAR / U1 UFSAR [Commitment 111360889] Licensing April 2016
6. Two Unit ODCM Woods / Shea September 14, 2012
7. As-Constructed PRA Guey / Koontz July 18, 2014
8. TMI Commitment Review Letter Licensing January 24, 2014
9. Letter to terminate Part 30/40 License after receipt of Part 50 License Licensing December 4, 2015
10. ASME Section III N-3 Report Crouch September 2014
11. Letter to NRC for notification of Vital Area Boundary Restoration Licensing January 24, 2014
12. Unit 2 Completion Letter Licensing August 8, 2014
13. Fire Protection Report [Commitment 113644252] Hilmes / Wiggal September 13, 2012 SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 08/27/2012 Page 6 of 36 Item No. Description Resp. Person Due Date Other Submittals

14. PAM variable Calculation for EOP reviews. Partch December 31, 2012
15. Regulatory Framework Update [for status as of 12/31/2012] Elton January 18, 2013 Regional Submittals 1.

SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 08/27/2012 Page 7 of 36 Item No. Description Resp. Person Due Date Fukushima NRC Order EA-12-049; Mitigating Strategies Order:

Licensees to develop, implement, and maintain guidance and strategies to maintain or restore core NRC Update

1. Williams cooling, containment and SFP cooling capabilities following a beyond-design-basis external event. 10/31/2012 Must be implemented in all modes.

NRC Order EA-12-049; Mitigating Strategies Order:

Strategies must be capable of mitigating a simultaneous loss of all alternating current (AC) power and NRC Update

2. Williams loss of normal access to the ultimate heat sink and have adequate capacity to address challenges to 10/31/2012 core cooling, containment, and SFP cooling capabilities at all units on a site.

NRC Order EA-12-049; Mitigating Strategies Order:

Provide reasonable protection for the associated equipment from external events. Such protection NRC Update

3. Williams must demonstrate that there is adequate capacity to address challenges to core cooling, 10/31/2012 containment, and SFP cooling capabilities at all units on a site.

NRC Order EA-12-051; Order:

Licensees to provide instrumentation, able to withstand design-basis natural phenomena and remain reliable at temperature, humidity and radiation levels at saturation conditions, to monitor SFP water NRC Update

4. Hilmes level from the control room. 10/31/2012 DCN 59683, Spent Fuel Pool Level Indication 10% of package 10 CFR 50.54 F Letter Request for Information:

Licensees to reevaluate the seismic hazards at their sites against current NRC requirements and

5. Williams 1/29/2013 guidance, and if necessary, update the design basis and SSCs important to safety to protect against the updated hazards.

SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 08/27/2012 Page 8 of 36 Item No. Description Resp. Person Due Date Fukushima 10 CFR 50.54 F Letter Request for Information:

Licensees to reevaluate the flooding hazards at their sites against current NRC requirements and

6. Williams 1/29/2013 guidance, and if necessary, update the design basis and SSCs important to safety to protect against the updated hazards.

10 CFR 50.54 F Letter Request for Information:

7. Recommendation 9.3 requires licensees to evaluate communication and staffing needs for multi-unit Williams 4/30/2013 events.

SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 08/27/2012 Page 9 of 36 Item No. Description Resp. Person Due Date Waste Confidence

1. Develop TVA approach to Waist Confidence Vigluicci/Baker 12/13/2012 SOURCE: POD UPDATES, COMMITMENTS

WBN UNIT 2 PROJECT PLAN: 08/27/2012 Page 10 of 36 Item No. Description Resp. Person Due Date Significant New Regulatory Issues New Station Blackout Rule

1. Hilmes Spring 2013 Ongoing rulemaking 10 CFR 50.46 Rule Change
2. Oxidation limits Koontz/Westinghouse Spring 2013 Ongoing rulemaking NRC Bulletin 2012-01
3. Design Vulnerability in Electric Power Systems Shea 10/25/2012 Fleet Response SOURCE: POD UPDATES, COMMITMENTS