From: Hughey, John Sent: Friday, August 10, 2012 3:23 PM To: 'Duke, Paul R.'

Cc: Burkhardt, Janet

Subject:

NRC Acceptance Review for Salem-Hope Creek Cyber Security Plan Implementation of Milestone No. 6

Paul, By letter dated July 26, 2012, PSEG submitted a license amendment request for Hope Creek Generating Station and Salem Nuclear Generating Station, Unit 1 and 2, (ADAMS Accession No. ML12209A394; TAC Nos. ME9153, ME9154 and ME9155) regarding the Cyber Security Plan implementation of Milestone No. 6. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review.

The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Thank you and please contact me if you have any questions, John John Hughey Salem & Hope Creek Project Manager NRR / Division of Operating Reactor Licensing Phone: 301-415-3204 e-mail: John.Hughey@nrc.gov