Progress Energy 1C Serial: RNP-RA/12-0078 JUL 2 6 201Z Attn: Document Control Desk United States Nuclear Regulatory Commission Washington, DC 20555 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-26 1/RENEWED LICENSE NO. DPR-23 SUPPLEMENTAL INFORMATION REGARDING H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 INSERVICE INSPECTION PROGRAM PLAN FOR THE FIFTH TEN-YEAR INTERVAL Ladies and Gentlemen:
By letter to the Nuclear Regulatory Commission (NRC) dated Mrch 14;2012 (Agencywide Documents Access and Management System Accession No: ML12082A009), Carolina Power &
Light Company, doing business as Progress Energy Ckrolinas, Inc., submitted the Inservice Inspection (ISI) Program Plan for the Fifth 10-Year Interval for the H. B. Robinson Steam Electric Plant, Unit No. 2 (HBRSEP). The NRC by NRC letter dated June 13, 2012 (ADAMS Accession No. ML12156A147) requested additional information to complete the review of Relief Request (RR)-02. Progress Energy Carolinas, Inc., by letter to the NRC dated June 19, 2012 (ADAMS Accession No. ML12187A249) provided the requested information.
In a coifdi-eiid' dal'l between the NRC' Staff and HBRSEP personnel on July 13, 2012 the NRC asked if RR-02 contained any B9.32 welds in the request. In response, Progress Energy Carolinas, Inc is providing 'the f0lfl6,ýin':suplpllemental information.
The welds that cannot currently be inspected due to insulation and listed in the attachment to our
-June 19, 2012 letter do not include any welds to which the B9.32 criterion of ASME B&PV Code,Section XI, 2007 Edition !';ith!'2008'Addenda, Table IWB-2500-1 would be applicable.
This document contains'no nevw Regulatory Commitments. If you have any questions concerning this matter, please contact Richard Hightower, Supervisor - Licensing/Regulatory Programs at (843)'857-1329.':
Sihcerely,ý
- j '
Sharon A. Wheeler Manager - Support Services - Nuclear.
Progress Energy Carolinas, Inc.
Robinson Nuclear Plant 3581 West Entrance Road Hartsville, SC 29550 2z
SUPPLEMENTAL INFORMATION RELATED TO ISI RELIEF REQUEST-02 United States Nuclear Regulatory Commission Serial: RNP-RA/12-0078 Page 2 of 2 SAW/sjg c:
Mr. V. M. McCree, NRC, Region II Ms. A. T. Billoch-Col6n, NRC Project Manager, NRR NRC Resident Inspector, HBRSEP