E-mail from R.Guzman to J.Devincentis Acceptance of License Amendment Request - Revision to Cyber Security Plan Milestone 6 Implementation Schedule
ML122050022
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
(DPR-028)
Issue date: 07/23/2012
From: Richard Guzman
Division of Operating Reactor Licensing
To: Devincentis J
Entergy Nuclear Vermont Yankee
Guzman R, NRR/DORL 415-1030
References
TAC ME9012
Download: ML122050022 (1)


Text

From:

Guzman, Richard To:

"Devincentis, James M" Bcc:

Guzman, Richard

Subject:

VYNPS - Acceptance of LAR to modify Milestone #6 of CSP Implementation Schedule (TAC NO. ME9012)

Date:

Monday, July 23, 2012 7:42:00 AM

Jim, The purpose of this e-mail is to provide the results of the NRC staffs acceptance review of the subject license amendment request dated July 2, 2012. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed the application and concludes that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.

This message will be added to ADAMS as an official agency record. If you have any questions, please contact me.

Rich Guzman Sr. Project Manager NRR/DORL US NRC 301-415-1030 Richard.Guzman@nrc.gov