ML12181A070

From kanterella
Jump to navigation Jump to search

Closeout of Bulletin 2011-01, Mitigating Strategies
ML12181A070
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 07/05/2012
From: Farideh Saba
Plant Licensing Branch II
To: Annacone M
Carolina Power & Light Co
Saba, Farideh
References
BL-11-001, TAC ME6407, TAC ME6408
Download: ML12181A070 (8)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 5,2012 Mr. Michael J. Annacone Vice President Brunswick Steam Electric Plant Carolina Power & Light Company Post Office Box 10429 Southport, North Carolina 28461

SUBJECT:

BRUNSWICK STEAM ELECTRIC PLANT, UNITS 1 AND 2 - CLOSEOUT OF BULLETIN 2011-01, "MITIGATING STRATEGIES" (TAC NOS. ME6407 AND ME6408)

Dear Mr. Annacone:

On May 11, 2011, the U.S. Nuclear Regulatory Commission (NRC) issued Bulletin 2011-01, "Mitigating Strategies" (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML111250360), to all holders of operating licenses for nuclear power reactors, except those that have permanently ceased operation and have certified that fuel has been removed from the reactor vessel. The purpose of the bulletin was to obtain a comprehensive verification that licensees' mitigating strategies to maintain or restore core cooling, spent fuel cooling, and containment following a large explosion or fire were compliant with Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(hh)(2).

The bulletin required two sets of responses pursuant to the provisions of 10 CFR 50.54(f).

Carolina Power & Light Company, the licensee for Brunswick Steam Electric Plant, Units 1 and 2 (Brunswick), provided its responses to the bulletin by letters dated June 8 and July 7, 2011 (ADAMS Accession Nos. ML11166A069 and ML11200A121, respectively). By letter dated November 17, 2011 (ADAMS Accession No. ML11308A658), the NRC sent the licensee a request for additional information (RAI) on its July 7, 2011, response. The licensee responded to the RAI by letter dated December 13, 2011 (ADAMS Accession No. ML11356A119).

The NRC staff has reviewed the information submitted by the licensee for Brunswick and verified that the licensee provided the information requested in the Bulletin 2011-01. The NRC staff concluded that the licensee's response to the bulletin is acceptable. The staff evaluation of the licensee's responses to Bulletin 2011-01 is summarized in the enclosure to this letter. No further information or action under the bulletin is requested.

M. Annacone

- 2 If you have any questions regarding this letter, please contact me at (301) 415-1447.

Sincerely, Farideh E. Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-325 and 50-324

Enclosure:

Summary of NRC Bulletin 2011-01 Response Review cc w/encl: Distribution via ListServ

SUMMARY

OF NRC BULLETIN 2011-01, "MITIGATING STRATEGIES" RESPONSE REVIEW BRUNSWICK STEAM ELECTRIC PLANT, UNITS 1 AND 2 DOCKET NOS, 50-325 AND 50-324 On May 11, 2011, the U.S. Nuclear Regulatory Commission (NRC) issued Bulletin 2011-01, "Mitigating Strategies," (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML111250360) to all holders of operating licenses for nuclear power reactors, except those that have permanently ceased operation and have certified that fuel has been removed from the reactor vessel. The bulletin required two sets of responses pursuant to the provisions of with Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(f). The first responses were due 30 days after issuance of the bulletin.

By letter dated June 8, 2011 (ADAMS Accession No. ML11166A069), Carolina Power & Light Company, the licensee for Brunswick Steam Electric Plant Units 1 and 2 (Brunswick), provided its response to this first set of questions (first response). The second responses were due 60 days after issuance of the bulletin. By letter dated July 7, 2011 (ADAMS Accession No. ML11200A121), Carolina Power & Light Company provided its response to this second set of questions (second response). By letter dated November 17, 2011 (ADAMS Accession No. ML11308A658), the NRC sent a request for additional information (RAI) on the second response. The licensee responded to the RAI by letter dated December 13, 2011 (ADAMS Accession No. ML11356A119). As summarized below, the NRC staff has verified that the licensee provided the information requested in the bulletin for Brunswick.

1.0 BACKGROUND

On February 25, 2002, the NRC issued EA-02-026, "Order for Interim Safeguards and Security Compensatory Measures" (ICM Order). Section B.5.b of the ICM Order required licensees to develop specific guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities using readily available resources (equipment and personnel) that can be effectively implemented under the circumstances associated with the loss of large areas of the plant due to explosions or fire.

By letter dated August 9, 2007 (ADAMS Accession No. ML072070375), the NRC staff issued its Safety Evaluation (SE) to document the final disposition of information submitted by Brunswick regarding Section B.5.b of the ICM Order. Along with the SE, the staff issued a conforming license condition to incorporate the B.5.b mitigating strategies into the licensing basis.

On March 27, 2009, the NRC issued 10 CFR 50.54(hh)(2) as a new rule, in order to capture the B.5.b mitigating strategies and related license conditions as regulatory requirements for both current and future licensees. At that time, licensee compliance with the conforming license conditions was sufficient to demonstrate compliance with 10 CFR 50.54(hh)(2) (74 FR 13926),

therefore no further actions were required on the part of current licensees.

Enclosure

- 2 2.0 30-DAY REQUEST In order to confirm continued compliance with 10 CFR 50.54(hh)(2), the Bulletin 2011-01 requested that licensees address the following two questions within 30 days of issuing the bulletin:

1. Is the equipment necessary to execute the mitigating strategies, as described in your submittals to the NRC, available and capable of performing its intended function?
2. Are the guidance and strategies implemented capable of being executed considering the current configuration of your facility and current staffing and skill levels of the staff?

The NRC staff reviewed the licensee's first response dated June 8, 2012, to determine if it had adequately addressed these questions.

2.1 Question 1: Availability and Capability of Equipment The licensee confirmed in its response that the equipment it needs to execute the 10 CFR 50.54(hh)(2) mitigating strategies is available and capable of performing its intended function.

The NRC staff verified that this confirmation covered equipment needed for each of the three phases of B.5.b mitigation strategies. Therefore, the NRC staff finds that the licensee has adequately responded to Question 1.

2.2 Question 2: Guidance and Strategies Can Be Executed The licensee confirmed in its response that the guidance and strategies it has implemented for 10 CFR 50.54(hh)(2) are capable of being executed considering the current facility configuration, staffing levels, and staff's skills. Since the licensee has considered its current facility configuration, staffing levels, and staff's skills, and confirmed that it can execute its implemented guidance and strategies, the NRC staff finds that the licensee has adequately responded to Question 2.

3.0 60-DAY REQUEST The Bulletin 2011-01 required a response to the following five questions within 60 days of issuing the bulletin:

1. Describe in detail the maintenance of equipment procured to support the strategies and guidance required by 10 CFR 50.54(hh)(2) in order to ensure that it is functional when needed.
2. Describe in detail the testing of equipment procured to support the strategies and guidance required by 10 CFR 50.54(hh)(2) in order to ensure that it will function when needed.
3. Describe in detail the controls for ensuring that the equipment is available when needed.

- 3

4. Describe in detail how configuration and guidance management is ensured so that strategies remain feasible.
5. Describe in detail how you ensure availability of offsite support.

The NRC staff reviewed the licensee's submittals to determine if it had adequately addressed these questions. This was accomplished by verifying that the submittals listed equipment, training, and offsite resources which were relied upon to make conclusions in the August 9, 2007, SE or are commonly needed to implement the mitigating strategies.

3.1 Questions 1 and 2: Maintenance and Testing of Equipment Questions 1 and 2 of the 50-day request required licensees to describe in detail the maintenance and testing of equipment procured to support the strategies and guidance required by 10 CFR 50.54(hh)(2) in order to ensure that it is functional when needed. In its second response dated July 7,2012, the licensee for Brunswick listed the equipment used to support the 10 CFR 50.54(hh)(2) mitigating strategies which receives maintenance or testing. For each item, the licensee described the maintenance and testing performed, including the frequency and basis for the maintenance or testing activity. In its RAI response, the licensee clarified the frequency for performing certain testing activities.

The NRC staff verified that the licensee listed equipment that typically requires maintenance or testing which was relied upon to make conclusions in the SE or commonly needed to implement the mitigating strategies. In its second response, the licensee stated that the portable pump, portable power supply, hoses, spray nozzles, and communications equipment receive maintenance or testing. In its RAI response, the licensee for Brunswick described how it ensures it has sufficient fuel for the portable pump. The licensee also identified other items that support the mitigating strategies that receive maintenance or testing.

The NRC staff verified that the licensee described the process used for corrective actions and listed the testing performed to ensure that the strategies were initially feasible. The licensee stated in its second response that its 10 CFR Part 50, Appendix B, corrective action program is used to document equipment failure, establish priorities, and perform trending.

Based upon the information above, the NRC staff finds that the licensee has provided the information requested by Questions 1 and 2.

3.2 Question 3: Controls on Eguipment Question 3 of the 50-day request required licensees to describe in detail the controls on equipment, such as inventory requirements, to ensure that the equipment is available when needed. A list of inventory deficiencies and associated corrective actions to prevent loss was also requested.

The NRC staff verified that the licensee described its process for ensuring that B.5.b equipment will be available when needed. In its second response, the licensee identified equipment included in its inventory, the inventory frequency, storage requirements, and items verified.

Items verified include proper quantity, location, and accessibility of equipment and controls on

- 4 storage locations. The licensee states that at the time of its second response there were no outstanding inventory deficiencies that would render the strategies not viable.

The NRC staff verified that the licensee inventoried equipment which was relied upon to make conclusions in the SE or commonly needed to implement the mitigating strategies. In its second response, the licensee stated that procured non-permanently installed B.5.b equipment is inventoried at least annually in accordance with station procedures. Most of the specific items listed in response to Question 3 are inventoried more frequently. The second response specifically states that the following items are included in the inventory: portable pump; tow truck; portable power supply; hoses; communications equipment; connectors; and firefighter turnout gear. The licensee also identified other items that support the mitigating strategies that are inventoried.

Based upon the information above, the NRC staff finds that the licensee for Brunswick has provided the information requested by Question 3.

3.3 Question 4: Configuration and Guidance Management Question 4 of the 50-day request required licensees to describe in detail how configuration and guidance management is assured so that the strategies remain feasible.

The NRC staff verified that the licensee described its measures to evaluate plant configuration changes for their effects on the mitigating strategies and to ensure its procedures are current.

In its second response, the licensee stated that plant configuration changes are procedurally required to be evaluated against the licensing basis, which includes the B.5.b mitigating strategies. The licensee states that the design change process requires a review of affected procedures and that procedure changes are validated to ensure that the B.5.b mitigating strategies remain viable.

The NRC staff verified that the licensee described measures it has taken to validate the procedures or guidelines developed to support the mitigating strategies. In its second response, the licensee identified testing in response to Question 2 that demonstrated the ability to execute some strategies. The licensee also states that "initially, B.5.b mitigating strategies were validated by walkdowns, engineering evaluations, and/or table top reviews" and they were similarly revalidated in 2011.

The NRC staff verified that the licensee described the training program implemented in support of the mitigating strategies and how its effectiveness is evaluated. In its second response, the licensee identified the training provided to its operations personnel; emergency response organization, including key decision makers; security personnel; and fire brigade. The licensee for Brunswick also identified the frequency with which each type of training is provided and the methods for training evaluating.

Based upon the information above, the NRC staff finds that the licensee for Brunswick has provided the information requested by Question 4.

- 5 3.4 Question 5: Offsite Support Question 5 of the 50-day request required licensees to describe in detail how offsite support availability is assured.

The NRC staff verified that the licensee listed the offsite organizations it relies upon for emergency response, including a description of agreements and related training. The NRC staff compared the list of offsite organizations that the licensee provided in its second response with the information relied upon to make conclusions in the SE. The licensee stated that it maintains memorandum of understanding or letters of agreements with these offsite organizations, which are reviewed annually, and that these agreements were current at the time of its second response. The licensee also described the training and site familiarization it provides to these offsite organizations. The licensee stated that it reviewed its corrective action program back to 2008 and did not identify any lapsed agreements related to offsite support for B.5.b events.

Based upon the information above, the NRC staff finds that the licensee for Brunswick has provided the information requested by Question 5.

4.0 CONCLUSION

As described above, the NRC staff has verified that the licensee for Brunswick has provided the information requested in Bulletin 2011-01. Specifically, the licensee responded to each of the questions in the bulletin as requested. The NRC staff concludes that the licensee has completed all of the requirements of the bulletin and no further information or actions under the bulletin are needed.

M. Annacone

- 2 If you have any questions regarding this letter, please contact me at (301) 415-1447.

Sincerely.

IRA!

Farideh E. Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-325 and 50-324

Enclosure:

Summary of NRC Bulletin 2011-01 Response Review cc w/encl: Distribution via ListServ Distribution:

PUBLIC LPL2-2 R/F RidsNrrDorlLpl2-2 RidsNrrPMBrunswick Resource RidsOgcRp RidsNrrLABTully (Hard Copy)

RidsAcrsAcnw_MailCTR RidsRgn2MailCenter RidsNrrDorlDpr TMcGinty BPurnell SBahadur EBowman RidsNrrDprPgcb ADAMS Accession No.: ML12181A070 OFFICE LPL2-2/PM LPL2-2/LA DPR/PGCB/BC(A)* LPL2-2/BC FSaba BTully KMorgan-Butler 07/02112 07102/12 112 OFFICIAL AGENCY RECORD