ML121360706
Letter Sequence Approval | |
---|---|
TAC:ME6360, Allow 7 Day Completion Time for a TURBINE-DRIVEN AFW Pump Inoperable, Provide Actions for One Steam Supply to Turbine Driven Afw/Efw Pump Inoperable, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO (Approved, Closed) TAC:ME6361, Allow 7 Day Completion Time for a TURBINE-DRIVEN AFW Pump Inoperable, Provide Actions for One Steam Supply to Turbine Driven Afw/Efw Pump Inoperable, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO (Approved, Closed) | |
Initiation Administration | |
MONTHYEARML1120300652011-07-21021 July 2011
[Table View]Acceptance Review Email, Request to Revise Technical Specifications Related to Auxiliary Feedwater System to Adopt TSTF-245, Rev. 1, TSTF-340, Rev. 3, TSTF-412, Rev. 3, and TSTF-439, Rev. 2 Project stage: Acceptance Review ML1200504882012-01-0505 January 2012 Request for Additional Information, Round 2, Revise Technical Specifications Related to Auxiliary Feedwater System to Adopt TSTF-245, Rev. 1, TSTF 340, Rev. 3, TSTF-412, Rev. 3, and TSTF-439, Rev. 2 (TAC ME6360-ME6361) Project stage: RAI DCL-11-059, Response to NRC Request for Additional Information Regarding PG&E Letter DCL-11-059, License Amendment Request 11-04, Revision to Technical Specification 3.6.6, 'Containment Spray and Cooling Systems,' ...2012-02-0606 February 2012 Response to NRC Request for Additional Information Regarding PG&E Letter DCL-11-059, License Amendment Request 11-04, Revision to Technical Specification 3.6.6, 'Containment Spray and Cooling Systems,' ... Project stage: Response to RAI ML1213607062012-05-21021 May 2012 Memo to File, Summary of 5/11/12 Telephone Conference Issues Associated TSTF-412, Rev. 3 and Effect on Staff Review of Request to Revise Technical Specifications Related to Auxiliary Feedwater System (TAC ME6360-ME6361) Project stage: Approval DCL-12-057, Supplement to PG&E Letter DCL-12-017, Response to NRC Request for Additional Information: NRC Question 12012-05-31031 May 2012 Supplement to PG&E Letter DCL-12-017, Response to NRC Request for Additional Information: NRC Question 1 Project stage: Supplement DCL-12-076, Response to NRC Second Request for Additional Information Regarding PG&E Letter DCL-11-059, License Amendment Request 11-04, Revision to Technical Specification (TS) 3.6.6, 'Containment Spray and Cooling Systems,' Ts..2012-08-0606 August 2012 Response to NRC Second Request for Additional Information Regarding PG&E Letter DCL-11-059, License Amendment Request 11-04, Revision to Technical Specification (TS) 3.6.6, 'Containment Spray and Cooling Systems,' Ts.. Project stage: Request DCL-12-107, Supplement to PG&E Letter DCL-11-059, License Amendment Request 11-04, Revision to Technical Specification (TS) 3.6.6, 'Containment Spray and Cooling Systems,' TS 3.7.5, 'Auxiliary Feedwater (AFW) System,' TS 3.8.1, 'Ac.....2012-11-0101 November 2012 Supplement to PG&E Letter DCL-11-059, License Amendment Request 11-04, Revision to Technical Specification (TS) 3.6.6, 'Containment Spray and Cooling Systems,' TS 3.7.5, 'Auxiliary Feedwater (AFW) System,' TS 3.8.1, 'Ac..... Project stage: Supplement ML12352A0672013-01-31031 January 2013 Issuance of Amendment Nos. 215 and 217, Revise Technical Specifications Related to Auxilary Feedwater System to Adopt TSTF-245, Rev. 1, TSTF-340, Rev. 3, TSTF-412, Rev. 3, and TSTF-439, Rev. 2 Project stage: Approval 2012-02-06 |
ML121360706 | |
Person / Time | |
---|---|
Site: | Diablo Canyon |
Issue date: | 05/21/2012 |
From: | Joseph Sebrosky Plant Licensing Branch IV |
To: | Plant Licensing Branch IV |
References | |
TAC ME6360, TAC ME6361 | |
Download: ML121360706 (3) | |
Similar Documents at Diablo Canyon | |
---|---|
Category:Memoranda
MONTHYEARML24297A6392024-10-30030 October 2024
[Table view]Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML24275A2162024-10-25025 October 2024 Summary of Meeting Between the U.S. Nuclear Regulatory Commission and the Yak Tityu Tityu Yak Ti?Hini Northern Chumash Tribe Related to the Proposed License Renewal (Lr) for Diablo Canyon Power Plant Units 1 and 2 ML24157A0252024-07-0101 July 2024 Memo to Michelle Rome Summary of 4/4/2024 Meeting with CA SHPO ML24143A1202024-06-0303 June 2024 Memo to Michelle Rome Summary of 4/5/2024 Meeting with Ytt ML24108A1482024-05-0707 May 2024 February 2024 Environmental Scoping Meetings Related to the Diablo Canyon LRA - Memo ML24067A1572024-03-0707 March 2024 Memorandum from the Secretary Referring Hearing Request to the Atomic Safety and Licensing Board Panel ML23265A1902023-09-26026 September 2023 Meeting Summary: September 13, 2023 Diablo Canyon, Units 1 and 2 License Renewal Application Pre-Application Meeting ML23143A2262023-06-0101 June 2023 May 3, 2023, Summary of Public Meeting to Discuss the End of Cycle Assessment and Pre-Submittal License Renewal Process Overview for Diablo Canyon Power Plant, Units 1 and 2 ML23046A0292023-02-23023 February 2023 Timely Renewal Exemption 5 Day Memorandum ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22131A1592022-05-11011 May 2022 Reply to the NRCs Response to the Office of the Inspector Generals (OIG) Event Inquiry Into the NRCs Oversight of the Auxiliary Feedwater System at Diablo Canyon Nuclear Power Plant, OIG Case No. 20-025 ML22109A1792022-05-0303 May 2022 Response OIG Special Inquiry Into NRCs Oversight AFW at Diablo Canyon (OIG Case No. 20-025) ML22108A1672022-05-0303 May 2022 Staff Assessment of OIG Event Inquiry Into the NRCs Oversight AFW at Diablo Canyon (OIG Case No. 20-025) ML21146A1852021-06-28028 June 2021 DC RFI 2021401 ML21146A185 ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML21060B1822021-03-0101 March 2021 Memorandum: 1-26-21 Diablo Canyon Renewal Pre-Application Meeting Summary ML19318F5272019-11-15015 November 2019 Summary of the August 27, 2019, Public Meeting Near the Diablo Canyon Nuclear Power Plant Regarding the Establishment and Operation of Community Advisory Boards ML19182A3562019-07-23023 July 2019 Quarterly Report on the Status of Public Petitions Under Title 10 of the Code of Federal Regulations, Section 2.206 - April 1 to June 30, 2019 ML18298A0762018-10-26026 October 2018 Notice of Forthcoming Closed Meeting with Pacific Gas and Electric Company to Discuss Security-Related Information for Diablo Canyon Power Plant, Units 1 and 2 ML18173A0082018-06-20020 June 2018 Cancelling Numerous Inspection Report Numbers ML18131A0482018-05-11011 May 2018 Memorandum to File Environmental Assessment and Finding of No Significant Impact for Pacific Gas and Electric Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) for the Diablo Canyon Independent Spent Fuel S ML16119A5002016-04-29029 April 2016 Notice of Forthcoming Closed Meeting with Pacific Gas & Electric Company to Discuss Proposed Change to Defensive Strategy and 10 CFR 50.54(p) Documentation for Reduction in Minimum Staffing Requirements at Diablo Canyon ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16029A2322016-03-16016 March 2016 LTR-15-0337-1 - Diablo Canyon Power Plant, Units 1 and 2 - Closure of 10 CFR 2.206 Petition from Bullard High School Students (CAC Nos. MF6515 and MF6516) ML15125A1862015-05-27027 May 2015 April 28, 2015, Summary of Category 1 Public Meeting with Pacific Gas and Electric Company to Discuss Diablo Canyon'S Seismic Hazard Reevaluation Associated with Implementation of Japan Lessons-Learned Near-Term Task Force Recommendation 2. ML14344A6302014-12-15015 December 2014 Close-out letter-California Facilities Preemption Safety Evaluation ML14167A4922014-07-0303 July 2014 Summary of June 5, 2014, Conference Call to Discuss the Status of the License Renewal Application Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML14022A1202014-06-23023 June 2014 Memorandum to File, Review of Revision 21 of Final Safety Analysis Report Update ML14162A4582014-06-12012 June 2014 Pacific Gas and Electric Company Diablo Canyon Power Plant Units 1 and 2, Regulatory Audit in Support of the License Amendment Request to Implement Risk-Informed, Performance-Based, Fire Protection Program as Allowed by Title 10 of the Code ML13339A4282014-04-28028 April 2014 Transmittal Memorandum for Regulatory Audit Report for the August 6, 2013 Through August 8, 2013 Cyber Security Pilot Study at Dcnpp Avila Beach, CA ML13312A6462013-11-25025 November 2013 Meeting Notice with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13290A2272013-10-18018 October 2013 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13263A1922013-09-24024 September 2013 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13260A0052013-09-18018 September 2013 10/2/13 Notice of Pre-Application Meeting with Pacific Gas and Electric Company to Discuss Upcoming Structural Weld Overlay Relief Request to Use an Alternative to Disposition Detected Laminar Indications at Diablo Canyon, Unit 2 ML13246A4262013-09-0505 September 2013 Notice of Meeting to Discuss Amendment Request to Adopt Technical Specifications Task Force TSTF-505, Provide Risk-Informed Extended Completion Times, RITSTF Initiative 4B at Diablo Canyon, Units 1 and 2 ML13246A4072013-09-0505 September 2013 9/25/13 Notice of Forthcoming Pre-Application Meeting to Discuss Emergency Core Cooling System Evaluations for License Amendment Request at Diablo Canyon, Units 1 and 2 ML13246A4162013-09-0505 September 2013 9/24/13 - Notice of Pre-Application Meeting to Discuss License Amendment Request for Technical Specification 3.8.1 Diesel Generator Surveillance Requirements at Diablo Canyon, Units 1 and 2 ML13246A2622013-09-0404 September 2013 9/18/13 Notice of Forthcoming Closed Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13179A0622013-07-0909 July 2013 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13163A0242013-06-12012 June 2013 6/26/13 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13126A0872013-05-0707 May 2013 Notice of Forthcoming 5/29/13 Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13101A2782013-04-24024 April 2013 Transmittal Memo for Regulatory Audit Report for the February 11-14, 2013 Cyber Security Pilot Study at the CS Innovation Facility in Scottsdale, Arizona ML13081A0742013-04-11011 April 2013 Summary Conference Call Between Pacific and Electric Co., and NRC Regarding Verbal Authorization of Relief Request Rep-1 U2, Revision 2 ML13074A1182013-03-15015 March 2013 3/27/13 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13052A5512013-02-21021 February 2013 Preapplication Meeting with Pacific Gas and Electric, License Amendment Request to Adopt NFPA-805 Performance-Based Standard for Fire Protection for LWR Generating Plants, at Diablo Canyon, Units 1 and 2 ML13028A2022013-02-0404 February 2013 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13030A2462013-01-30030 January 2013 2/12/13 Forthcoming Preapplication Meeting with Pacific Gas and Electric Company to Discuss License Amendment Requests for Degraded Voltage Protection and Control Room Dose Analysis of Record at Diablo Canyon, Units 1 and 2 ML13017A1572013-01-15015 January 2013 Diablo Canyon - January Hearing File Update ML12354A5392012-12-20020 December 2012 1/24/2013 - Notice of Meeting with Pacific Gas and Electric to Discuss Diablo Canyon, Units 1 and 2 License Amendment Request to Revise FSAR Update Related to Delayed Access Offsite Power Circuit to Conform with GDC 17 2024-07-01 Category:Note to File incl Telcon Record MONTHYEARML12297A2432012-10-31031 October 2012
[Table view]Summary of 10/17/2012 Teleconference Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML12240A3222012-09-0707 September 2012 Summary of Audit to Review Calculations That Support License Amendment Request Related to Main Steam Safety Valves ML1213607062012-05-21021 May 2012 Memo to File, Summary of 5/11/12 Telephone Conference Issues Associated TSTF-412, Rev. 3 and Effect on Staff Review of Request to Revise Technical Specifications Related to Auxiliary Feedwater System (TAC ME6360-ME6361) DCL-11-023, Response to Summary of Telephone Conference Call Held on 02/28/2011, Between U.S. Nuclear Regulatory Commission & PG&E Co. Concerning Responses to Requests for Additional Info. for Renewal Application2011-03-25025 March 2011 Response to Summary of Telephone Conference Call Held on 02/28/2011, Between U.S. Nuclear Regulatory Commission & PG&E Co. Concerning Responses to Requests for Additional Info. for Renewal Application ML1106103842011-03-0202 March 2011 Conversation Record Between Bill Pelle, Usfws and Richard Bulavinetz NRC, Regarding Protected Species List for Diablo Canyon Power Plant ML1019005582010-07-16016 July 2010 Summary of Telephone Call Pertaining to the LRA of the Diablo Canyon Nuclear Power Plant, Units 1 & 2 ML1001508442009-12-17017 December 2009 Conversation Record with J Strickland, Et Al., Pg&E, and T Morin, Et Al., Holtec, Subject: Diablo Canyon Amend 1, Draft Rsis ML0930601972009-10-0707 October 2009 Conversation Record: Diablo Canyon Site Specific ISFSI, TAC L24210, Docket No. 72-26, Held on October 7, 2009 ML0913402922009-05-14014 May 2009 Conversation Record, D. Sokolsky/Pg&E Humboldt Bay (Hb) Independent Spent Fuel Storage Installation (ISFSI) License Amendment 2, Held on May 13, 2009 2012-09-07 Category:Verbal Comm MONTHYEARML12297A2432012-10-31031 October 2012
[Table view]Summary of 10/17/2012 Teleconference Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML12240A3222012-09-0707 September 2012 Summary of Audit to Review Calculations That Support License Amendment Request Related to Main Steam Safety Valves ML1213607062012-05-21021 May 2012 Memo to File, Summary of 5/11/12 Telephone Conference Issues Associated TSTF-412, Rev. 3 and Effect on Staff Review of Request to Revise Technical Specifications Related to Auxiliary Feedwater System (TAC ME6360-ME6361) DCL-11-023, Response to Summary of Telephone Conference Call Held on 02/28/2011, Between U.S. Nuclear Regulatory Commission & PG&E Co. Concerning Responses to Requests for Additional Info. for Renewal Application2011-03-25025 March 2011 Response to Summary of Telephone Conference Call Held on 02/28/2011, Between U.S. Nuclear Regulatory Commission & PG&E Co. Concerning Responses to Requests for Additional Info. for Renewal Application ML1106103842011-03-0202 March 2011 Conversation Record Between Bill Pelle, Usfws and Richard Bulavinetz NRC, Regarding Protected Species List for Diablo Canyon Power Plant ML1019005582010-07-16016 July 2010 Summary of Telephone Call Pertaining to the LRA of the Diablo Canyon Nuclear Power Plant, Units 1 & 2 ML1001508442009-12-17017 December 2009 Conversation Record with J Strickland, Et Al., Pg&E, and T Morin, Et Al., Holtec, Subject: Diablo Canyon Amend 1, Draft Rsis ML0930601972009-10-0707 October 2009 Conversation Record: Diablo Canyon Site Specific ISFSI, TAC L24210, Docket No. 72-26, Held on October 7, 2009 ML0913402922009-05-14014 May 2009 Conversation Record, D. Sokolsky/Pg&E Humboldt Bay (Hb) Independent Spent Fuel Storage Installation (ISFSI) License Amendment 2, Held on May 13, 2009 2012-09-07 Category:Meeting Summary MONTHYEARML24278A0422024-11-0808 November 2024
[Table view]Environmental Scoping Summary Report for V.C. Summer Subsequent License Renewal ML24275A2162024-10-25025 October 2024 Summary of Meeting Between the U.S. Nuclear Regulatory Commission and the Yak Tityu Tityu Yak Ti?Hini Northern Chumash Tribe Related to the Proposed License Renewal (Lr) for Diablo Canyon Power Plant Units 1 and 2 ML24157A0252024-07-0101 July 2024 Memo to Michelle Rome Summary of 4/4/2024 Meeting with CA SHPO ML24143A1202024-06-0303 June 2024 Memo to Michelle Rome Summary of 4/5/2024 Meeting with Ytt ML24108A1472024-05-0707 May 2024 February 2024 Diablo Canyon Public Scoping Meetings - Summary ML24108A1482024-05-0707 May 2024 February 2024 Environmental Scoping Meetings Related to the Diablo Canyon LRA - Memo ML24081A3362024-03-22022 March 2024 Summary of March 7, 2024, Closed Presubmittal Meeting with Pacific Gas and Electric Company Alternative Security Measures for Early Warning System License Amendment and Exemption Requests for Diablo Canyon Units 1 and 2 ML23268A4072023-09-27027 September 2023 Summary of September 19, 2023, Closed Public Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML23265A1902023-09-26026 September 2023 Meeting Summary: September 13, 2023 Diablo Canyon, Units 1 and 2 License Renewal Application Pre-Application Meeting ML23143A2262023-06-0101 June 2023 May 3, 2023, Summary of Public Meeting to Discuss the End of Cycle Assessment and Pre-Submittal License Renewal Process Overview for Diablo Canyon Power Plant, Units 1 and 2 ML22272A5072022-09-29029 September 2022 Summary of September 27, 2022, Closed Meeting with Pacific Gas and Electric Company Regarding Planned Security Plan Changes for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22126A0162022-05-0909 May 2022 Summary of April 27, 2022, Closed Teleconference with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML21246A0202021-09-0808 September 2021 Summary of August 30, 2021, Pre-Submittal Teleconference with Pacific Gas and Electric Company Regarding a Post-Shutdown Emergency Plan License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML20332A1802020-12-0101 December 2020 Summary of November 24, 2020, Pre-Submittal Teleconference with Pacific Gas and Electric Company a Permanently Defueled Technical Specification License Amendment Request ML20231A6522020-08-24024 August 2020 Summary of Teleconference with Pacific Gas & Electric Company Regarding an Exigent Amendment Request to Modify Diablo Canyon Power Plant, Units 1 & 2, Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System EPID L-2020-LLA-017 ML20189A2832020-07-0707 July 2020 Summary of Region IV Annual Assessment Public Meeting ML19318F5272019-11-15015 November 2019 Summary of the August 27, 2019, Public Meeting Near the Diablo Canyon Nuclear Power Plant Regarding the Establishment and Operation of Community Advisory Boards ML19196A0742019-07-22022 July 2019 Summary of Meeting with Pacific Gas and Electric Company Regarding Forthcoming Activities Associated with Diablo Canyon Nuclear Power Plant, Units 1 and 2 Planned Decommissioning ML19064B2652019-03-14014 March 2019 Summary of February 28, 2019, Public Meeting with Pacific Gas and Electric Company to Discuss the Proposed Relief Request Concerning Reactor Vessel Internal Visual Examination for the Diablo Canyon Nuclear Power Plant, Units 1 & 2 ML18348A4202018-12-31031 December 2018 Summary of Meeting with Pacific Gas & Electric Co. to Discuss Exemption Request to Withdraw Funds from the Nuclear Decommissioning Trusts to Fund Decommissioning Planning Activities at Diablo Canyon Nuclear Power Plant ML18207A7332018-08-10010 August 2018 Summary of Pre-Licensing Meeting with PG&E Co. to Discuss the Proposed LAR to Implement WCAP-16996-A, Revision 1, Realistic LOCA Evaluation Methodology Applied to the Full Spectrum of Break Sizes at Diablo Canyon ML17198A6032017-07-17017 July 2017 Summary of Annual Assessment Meeting Regarding Diablo Canyon Power Plant 2016 Performance ML16190A1782016-07-0808 July 2016 Summary of Annual Assessment Town Hall Meeting and Public Outreach Regarding Diablo Canyon Power Plant 2015 Performance ML16011A2042016-01-14014 January 2016 Summary of Conference Call on January 7, 2016, Between the U.S. NRC and Pacific Gas and Electric Co. Concerning the Responses to RAI for the Review of the Diablo Canyon Power Plant, Units 1 and 2, License Renewal Application (CAC Nos. MF401 ML15343A1272015-12-24024 December 2015 Summary of Meeting with Pacific Gas and Electric to Discuss Diablo Canyon, Units 1 and 2 Amendment Request to Revise UFSAR for Beacon Power Distribution Monitoring System Methodology and TS 5.6.5 (COLR) Paragon and Nexus Methodologies ML15348A1702015-12-17017 December 2015 Summary of Telephone Conference Call Held Between NRC and Pacific Gas and Electric Co., Concerning the RAI Responses Pertaining to the Diablo Canyon Power Plant LRA Environmental Review ML15280A2842015-10-20020 October 2015 Summary of Meeting with Pacific Gas & Electric to Discuss Diablo Canyon, Units 1 and 2 Request to Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition), ML15279A4222015-10-0909 October 2015 Summary of 8/25/15 Meeting with Pacific Gas and Electric to Discuss Diablo Canyon Units 1 and 2 Amendment Request to Adopt Risk-Informed Completion Times, TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times-RITSTF Initiati ML15275A1302015-10-0707 October 2015 Summary of the Site Audit Related to the Diablo Canyon Power Plant, Units 1 and 2 License Renewal Environmental Review ML15275A0942015-10-0707 October 2015 Summary of the Severe Accident Mitigation Alternatives Site Audit Related to the Diablo Canyon Power Plant, Units 1 and 2 License Renewal Review ML15233A0062015-09-10010 September 2015 Summary of Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML15233A0052015-09-0909 September 2015 Summary of Meeting with Pacific Gas and Electric to Discuss Diablo Canyon, Units 1 & 2 License Amendment Request to Adopt Risk-Informed Completion Times, TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times-RITSTF. Initiati ML15233A4912015-09-0101 September 2015 August 5, 2015, Public Scoping Meetings for the Environmental Review of the Diablo Canyon Power Plant, Units 1 and 2 License Renewal Application ML15209A9442015-07-28028 July 2015 June 24, 2015, Summary of Annual Assessment Meeting with Pacific Gas and Electric and Public Open House Regarding Diablo Canyon Power Plant 2014 Performance ML15125A1862015-05-27027 May 2015 April 28, 2015, Summary of Category 1 Public Meeting with Pacific Gas and Electric Company to Discuss Diablo Canyon'S Seismic Hazard Reevaluation Associated with Implementation of Japan Lessons-Learned Near-Term Task Force Recommendation 2. ML15134A2572015-05-18018 May 2015 5/7/15 Summary of Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML15092A0792015-04-16016 April 2015 July 14-17, 2014 - Summary of Diablo Canyon, Units 1 and 2, Audit to Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) ML15069A0952015-03-24024 March 2015 Summary of Telephone Conference Call Held on March 4, 2015 Between the U.S. Nuclear Regulatory Commission and Pacific Gas and Electric Company Concerning the Diablo Canyon Power Plant, Units 1 and 2, License Renewal Application ML15043A1992015-02-19019 February 2015 2/3/2015 Summary of Meeting with Pacific Gas and Electric Regarding Presubmittal Discussion on Alternate Source Term License Amendment Request for Diablo Canyon Power Plant, Units 1 and 2 ML15037A2482015-02-0505 February 2015 Summary of Regulatory Conference to Discuss Safety Significance of Diablo Canyon Power Plant Protective Action Recommendations for Areas of the Ocean Finding ML14350A2712014-12-22022 December 2014 Summary of 12/11/14 Preapplication Meeting with Pacific Gas and Electric Company to Discuss License Amendment Request to Support Installation of 500 Kilovolt Output Generator Breakers at Diablo Canyon, Units 1 and 2 ML14029A4502014-12-10010 December 2014 Summary of 12/18/13 Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML14295A7332014-11-17017 November 2014 9/24/14 Summary of Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML14197A3522014-07-22022 July 2014 7/9/14 Summary of Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML14157A0912014-06-17017 June 2014 Summary of 5/21/14 Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML14155A3742014-06-0404 June 2014 May 22, 2014, Summary of Annual Assessment Meeting with Pacific Gas and Electric Regarding Diablo Canyon Power Plant 2013 Performance ML14113A4932014-05-0606 May 2014 Summary of Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML14113A4222014-04-23023 April 2014 Public Meeting with Pacific Gas & Electric (Pg&E)To Discuss the Operating Performance for Diablo Canyon Power Plant for the Period January 1 - December 31, 2013 2024-07-01 |
Text
May 21, 2012 MEMORANDUM TO: FILE FROM: Joseph M. Sebrosky /RA/
Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
SUBJECT:
DIABLO CANYON POWER PLANT, UNIT NOS. 1 AND 2 -
SUMMARY
OF TELEPHONE CONFERENCE RE: ISSUES ASSOCIATED WITH TECHNICAL SPECIFICATION TASK FORCE TRAVELER 412 AND THE EFFECT ON THE STAFF REVIEW OF A JUNE 1, 2011, LICENSE AMENDMENT REQUEST (TAC NOS. ME6360 AND ME6361)
This memorandum summarizes a telephone discussion on May 11, 2012, between the U.S. Nuclear Regulatory Commission (NRC) staff and Pacific Gas and Electric (PG&E, the licensee). The discussion was in regard to the results of a May 8, 2012, public meeting associated with Technical Specification Task Force (TSTF) change traveler TSTF-412, and the effect the outcome of this meeting would have on the NRC staffs review of a June 1, 2011, license amendment request from PG&E that references this TSTF. Participants in the discussion included PG&E representatives J. Bailey, J. Nelson, M. Richardson, and P. Soenen, and NRC staff Stan Gardocki and Joe Sebrosky.
By letter dated June 1, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML111530114), PG&E submitted a license amendment request that proposed changes to several Technical Specifications (TSs) including changes to TS 3.7.5, Auxiliary Feedwater (AFW) System. The license amendment request included changes to be consistent with TSTF-412, Revision 3, Allow 7 Day Completion Time for a Turbine-driven AFW Pump Inoperable.
During a public meeting on May 8, 2012, TSTF-412 was discussed, including the NRC staffs issues associated with the portion of the TSTF traveler associated with a provision for 24-hour completion time for an inoperable motor-driven AFW pump coincident with one inoperable steam supply to the steam-driven AFW pump. The NRC staffs issues are documented in an April 12, 2012, memorandum from Greg Casto to Robert Elliot (ADAMS Accession No. ML111530114).
Because of the issues with TSTF-412 identified during the May 8, 2012, meeting and in the memorandum dated April 12, 2012, PG&E proposed amending the response to question number 1 provided in its letter dated February 6, 2012 (ADAMS Accession No. ML12038A041),
associated with the June 1, 2011, license amendment request. Specifically, the NRC staff had included the following note in question 1:
Note: the licensee can limit the proposed condition, where the inoperable steam supply could only exist on the SG [steam generator] that can be fed by the operable MDAFWP [motor-driven auxiliary feedwater pump].
During the phone call on May 11, 2012, PG&E stated that it would revise its response dated February 6, 2012, to question number 1 to remove the 24-hour limiting condition for operation (LCO) in accordance with the above note and replace it with a 48-hour LCO when the conditions in the above note are met. The NRC staff indicated it would review the revised response when it was provided by PG&E.
Docket Nos. 50-275 and 50-323
ML121360706 OFFICE NRR/LPL4/PM NRR/LPL4/LA NRR/LPL4/BC NRR/LPL4/PM NAME JSebrosky JBurkhardt MMarkley JSebrosky DATE 5/21/12 5/16/12 5/21/12 5/21/12