ML12073A323

From kanterella
Jump to navigation Jump to search
Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information Inspection Report 05000305-12-003 (DRS)
ML12073A323
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 03/12/2012
From: Ann Marie Stone
NRC/RGN-III/DRS/EB2
To: Heacock D
Dominion Energy Kewaunee
Gerard O'Dwyer
References
Download: ML12073A323 (9)


See also: IR 05000305/2012003

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE ROAD, SUITE 210

LISLE, IL 60532-4352

March 12, 2012

Mr. David A. Heacock

President and Chief Nuclear Officer

Dominion Energy Kewaunee, Inc.

Innsbrook Technical Center

5000 Dominion Boulevard

Glen Allen, VA 23060-6711

SUBJECT: KEWAUNEE POWER STATION - NOTIFICATION OF AN NRC TRIENNIAL

HEAT SINK PERFORMANCE INSPECTION AND REQUEST FOR

INFORMATION INSPECTION REPORT 05000305/2012003(DRS)

Dear Mr. Heacock:

On May 14, 2012, the U. S. Nuclear Regulatory Commission (NRC) will begin the on-site

portion of the Triennial Heat Sink Performance Inspection at your Kewaunee Power Station.

This inspection will be performed in accordance with the NRC baseline inspection procedure

(IP) 71111.07T.

In order to minimize the impact that the inspection has on the site and to ensure a productive

inspection, we have enclosed a request for documents needed for the inspection. The

documents have been divided into three groups.

  • The first group of documents lists information necessary for our initial inspection

scoping activities. This information should be available to the lead inspector no later than

April 2, 2012. By April 12, 2012, the inspector will communicate the initial selected set of

approximately 2-3 risk significant heat exchangers.

  • The second group of documents requested, are those items needed to support our in-office

preparation activities. This set of documents, including the calculations associated with

the selected heat exchangers, should be available at the Regional Office no later than

May 2, 2012. This information should be separated for each selected component,

especially if provided electronically (e.g., folder with component name that includes

calculations, condition reports, maintenance history, etc.). During the in-office preparation

activities, the inspector may identify additional information needed to support the

inspection.

  • The last group of documents includes the additional information above, as well as plant

specific reference material. This information should be available on-site to the inspector on

May 14, 2012. It is also requested that corrective action documents and/or questions

developed during the inspection be provided to the inspector as the documents are

generated.

D. Heacock -2-

The lead inspector for this inspection is Mr. Gerard ODwyer. We understand that our regulatory

contact for this inspection is Mr. Jack Gadzala of your organization. If there are questions about

the material requested, or the inspection, please call Mr. ODwyer at (630) 829-9624. Please

send the information to the following e-mail address gerard.odwyer@nrc.gov. A hard-copy with

the required information is also an acceptable option.

It is important that these documents be as complete as possible, in order to minimize the

number of documents requested during the preparation week or during the on-site inspection.

All requested documents are to be for the time period from the on-site inspection period back to

the documents that were provided in response to the previous heat sink performance

inspection. If no activities were accomplished in that time period, then the request applies to

the last applicable document in the previous time period.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, control number 3150-

0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a

request for information or an information collection requirement unless the requesting

document displays a currently valid Office of Management and Budget control number.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC's document system

(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html

(the Public Electronic Reading Room).

Sincerely,

/RA by A. Dunlop for/

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-305

License No. DPR-43

Enclosure: TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT

REQUEST

cc w/encl: Distribution via ListServ'

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

Inspection Report: 05000305/2012003

Inspection Dates: May 14-18, 2012

Inspection Procedure: Inspection Procedure (IP) 71111.07T, Heat Sink

Performance

Lead Inspector: Gerard F. ODwyer

(630) 829-9624

gerard.odwyer@nrc.gov

Team Member: Larry J. Jones Jr.

(630) 829-9864

larry.jones@nrc.gov

I. Information Requested By April 2, 2012

1. List of the Generic Letter (GL) 89-13, Service Water System Problems Affecting

Safety-Related Equipment, heat exchangers in order of risk significance.

2. Copy of heat exchanger performance trending data tracked for each GL 89-13 heat

exchanger.

3. List of corrective action program documents (with a description) associated with any

GL 89-13 heat exchangers, heat sinks, silting, corrosion, fouling, or heat exchanger

testing for the previous three years or since the last corrective action program

document list was sent to the NRC for the previous heat sink performance

inspection. The list should include all corrective action program documents not on

the last corrective action program document list.

4. Copy of any self-assessment done on any GL 89-13 heat exchangers or the

GL 89-13 program.

5. Last two System health report(s) and maintenance rule system notebooks for all the

GL 89-13 heat exchangers.

6. List of engineering-related operator workarounds (with a short description)

associated with GL 89-13 heat exchangers. The requested documents are to be for

the time period from the on-site inspection period back to the documents that were

provided in response to the previous heat sink performance inspection.

1 Enclosure

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

7. List of permanent and temporary modifications (with a short description) associated

with GL 89-13 heat exchangers. The requested documents are to be for the time

period from the on-site inspection period back to the documents that were provided

in response to the previous heat sink performance inspection.

II. Information Requested By May 2, 2012

1. Copy of the UFSAR sections applicable to the GL 89-13 Heat Exchanger Program.

2. Copies of procedures developed to implement the recommendations of GL 89-13

(e.g., the GL 89-13 Heat Exchanger Program description).

3. For the specific heat exchangers selected:

a. Copies of the Updated Final Safety Analysis Report (UFSAR) sections applicable

for each heat exchanger.

b. Copy of system description and design basis document for the heat exchangers

(as applicable).

c. Provide a list of calculations (with a short description), which currently apply to

each heat exchanger.

d. Copy of any operability determinations or other documentation of degradation

associated with the heat exchangers or the systems that support the operation

for the selected heat exchangers.

4. For the ultimate heat sink (UHS) and the safety-related service water system (or

equivalent):

a. Copies of the applicable Updated Final Safety Analysis Report (UFSAR)

sections.

b. Copy of system description and design basis document (as applicable).

c. Copy of any operability determinations or other documentation of degradation

associated with the UHS and the safety-related service water system.

d. Copy of the document (e.g., UFSAR or Technical Requirements Manual) that

states the maximum cooling water system inlet temperature limit that still allows

full licensed power operation of the nuclear reactor.

5. A schedule of all inspections, cleanings, maintenance, or testing of any

safety-related plant heat exchanger to be performed during the on-site portion of the

inspection.

2 Enclosure

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

III. Information Requested to be Available on First Day of Inspection, May 14, 2012

1. For the specific heat exchangers selected.

a. Copy of the calculation which correlates surveillance testing results from these

heat exchangers with design basis heat removal capability (e.g., basis for

surveillance test acceptance criteria).

b. Copies of the two most recent completed tests and evaluation data confirming

thermal performance for those heat exchangers which are performance tested.

c. Documentation and procedures that identify the types, accuracy, and location of

any special instrumentation used for the two most recently completed thermal

performance tests for the heat exchangers (e.g., high accuracy ultrasonic flow

instruments or temperature instruments). Include calibration records for the

instruments used during these tests.

d. Information regarding any alarms which monitor on-line performance.

e. Copy of the document describing the inspection results of each heat exchanger.

The requested documents are to be for the time period from the on-site

inspection period back to the documents that were provided in response to the

previous heat sink performance inspection.

f. The cleaning and inspection maintenance schedule for each heat exchanger for

the next five years.

g. Copy of the design specification and heat exchanger data sheets for each heat

exchanger.

h. Copy of the vendor manuals including component drawings for each heat

exchanger.

i. Copy of the calculation which establishes the limiting (maximum) design basis

heat load, which is required to be removed by each of these heat exchangers.

j. Copy of the operating procedure that ensures that the maximum cooling water

system inlet temperature limit is not exceeded.

k. Copy of the calculations or documents which evaluate the potential for water

hammer in each heat exchanger or associated piping.

l. Copy of the calculations that evaluate excessive tube vibration in each heat

exchanger and the documents that describe the controls that prevent heat

exchanger degradation due to excessive flow induced vibration during operation.

3 Enclosure

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

m. Copy of the periodic flow testing at or near maximum design flow. The requested

documents are to be for the time period from the on-site inspection period back

to the documents that were provided in response to the previous heat sink

performance inspection.

n. Copy of the document which identifies the current number of tubes in service for

each heat exchanger and the supporting calculation, which establishes the

maximum number of tubes which can be plugged in each heat exchanger.

o. Copy of the document establishing the repair criteria (plugging limit) for degraded

tubes, which are identified in each heat exchanger.

p. Copies of the documents that verify the structural integrity of the heat exchanger

(e.g., eddy current summary sheets, ultrasonic testing results, and visual

inspection results).

q. Copies of those documents that describe the methods taken to control water

chemistry in the heat exchangers.

2. For the UHS:

a. Copies of the inspection procedures for the verification of the structural integrity

of underwater UHS and the associated results. The requested documents are to

be for the time period from the on-site inspection period back to the documents

that were provided in response to the previous heat sink performance inspection.

b. Copies of the maintenance and/or inspection procedures for underwater UHS

sediment intrusion and the associated results including underwater diving

inspections and/or sediment removal activities. The requested documents are to

be for the time period from the on-site inspection period back to the documents

that were provided in response to the previous heat sink performance inspection.

Copies of calculations and surveillances that determine the UHS reservoir

capacity and heat transfer capability.

c. Copies of surveillance procedures and testing results performed on the

instrumentation relied upon to determine UHS reservoir capability. The

requested documents are to be for the time period from the on-site inspection

period back to the documents that were provided in response to the previous

heat sink performance inspection.

3. For the review of the operation of the safety-related service water system (or

equivalent) and the UHS.

a. Copies of any design change performed on the UHS. The requested documents

are to be for the time period from the on-site inspection period back to the

documents that were provided in response to the previous heat sink performance

inspection.

4 Enclosure

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

b. Copies of any design change performed on the safety-related service water

system. The requested documents are to be for the time period from the on-site

inspection period back to the documents that were provided in response to the

previous heat sink performance inspection.

c. Copies of procedures for a loss of UHS.

d. Copies of procedures for a loss of service water system.

e. Inspections and/or maintenance related to preventing macrofouling (e.g., silt,

dead mussel shells, or debris) and biotic fouling (e.g., fish, algae, grass, or kelp).

The requested documents are to be for the time period from the on-site

inspection period back to the documents that were provided in response to the

previous heat sink performance inspection.

f. Copies of chemistry procedures that monitor for pH, calcium hardness, etc. Also,

provide copies of the associated results. The requested documents are to be for

the time period from the on-site inspection period back to the documents that

were provided in response to the previous heat sink performance inspection.

g. Copies of documents associated with the monitoring of pump performance for

potential strong-pump vs. weak-pump interaction.

If the information requested above will not be available, please contact Mr. Gerard ODwyer

soon as possible at (630) 829-9624 or email gerard.odwyer@nrc.gov.

.

5 Enclosure

D. Heacock -2-

The lead inspector for this inspection is Mr. Gerard ODwyer. We understand that our regulatory contact

for this inspection is Mr. Jack Gadzala of your organization. If there are questions about the material

requested, or the inspection, please call Mr. ODwyer at (630) 829-9624. Please send the information to

the following e-mail address gerard.odwyer@nrc.gov. A hard-copy with the required information is also an

acceptable option.

It is important that these documents be as complete as possible, in order to minimize the number of

documents requested during the preparation week or during the on-site inspection.

All requested documents are to be for the time period from the onsite inspection period back to the

documents that were provided in response to the previous heat sink performance inspection. If no

activities were accomplished in that time period, then the request applies to the last applicable document

in the previous time period.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements

were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not

conduct or sponsor, and a person is not required to respond to, a request for information or an

information collection requirement unless the requesting document displays a currently valid Office of

Management and Budget control number.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure

will be available electronically for public inspection in the NRC Public Document Room or from the

Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the

NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA by A. Dunlop for/

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-305

License No. DPR-43

Enclosure: TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

cc w/encl: Distribution via ListServ'

DISTRIBUTION:

See next page

DOCUMENT NAME: G:\DRSIII\DRS\Work in Progress\-Ltr 03__12 Kewaunee Heat Sink RFI

GFO.docx

9 Publicly Available 9 Non-Publicly Available 9 Sensitive 9 Non-Sensitive

To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl; E = Copy with attach/encl N = No copy

OFFICE RIII RIII

NAME ADunlop for GODwyer:ls ADunlop for AMStone

DATE 03/12/12 03/12/12

OFFICIAL RECORD COPY

Letter to Mr. David A. Heacock from Ms. Ann Marie Stone dated March 12, 2012.

SUBJECT: KEWAUNEE POWER STATION - NOTIFICATION OF AN NRC TRIENNIAL

HEAT SINK PERFORMANCE INSPECTION AND REQUEST FOR

INFORMATION INSPECTION REPORT 05000305/2012003(DRS)

DISTRIBUTION:

Breeda Reilly

RidsNrrDorlLpl3-1 Resource

RidsNrrPMKewaunee

RidsNrrDirsIrib Resource

Chuck Casto

Cynthia Pederson

Jennifer Uhle

Steven Orth

Jared Heck

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

Patricia Buckley

Tammy Tomczak