1 WBN2Public Resource From:

Boyd, Desiree L [dlboyd@tva.gov]

Sent:

Monday, March 12, 2012 7:25 AM To:

Epperson, Dan; Poole, Justin; Milano, Patrick; Campbell, Stephen Cc:

Arent, Gordon; Bryan, Robert H Jr; Boyd, Desiree L; Crouch, William D; Templeton, Pamela J

Subject:

NRC PM Open Items List 03-14-12.docx Attachments:

NRC PM Open Items List 03-14-12.docx For next phone call, 03/04/12.

Thank You,

~*~*~*~*~*~*~*~*~*~*~

Désireé L. Boyd WBN Unit 2 Licensing dlboyd@tva.gov 423-365-8764

Hearing Identifier:

Watts_Bar_2_Operating_LA_Public Email Number:

675 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF29F9A958)

Subject:

NRC PM Open Items List 03-14-12.docx Sent Date:

3/12/2012 7:25:19 AM Received Date:

3/12/2012 7:29:35 AM From:

Boyd, Desiree L Created By:

dlboyd@tva.gov Recipients:

"Arent, Gordon" <garent@tva.gov>

Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov>

Tracking Status: None "Boyd, Desiree L" <dlboyd@tva.gov>

Tracking Status: None "Crouch, William D" <wdcrouch@tva.gov>

Tracking Status: None "Templeton, Pamela J" <pjtempleton@tva.gov>

Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov>

Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>

Tracking Status: None "Milano, Patrick" <Patrick.Milano@nrc.gov>

Tracking Status: None "Campbell, Stephen" <Stephen.Campbell@nrc.gov>

Tracking Status: None Post Office:

TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 237 3/12/2012 7:29:35 AM NRC PM Open Items List 03-14-12.docx 36227 Options Priority:

Standard Return Notification:

No Reply Requested:

Yes Sensitivity:

Normal Expiration Date:

Recipients Received:

NRC PM Open Items List 03/14/2012 (423) 751-7777 ID 4233658764#

1 l P a g e No.

Description Status Additional Comments Resp Org/Person

1.

Cyber Security Plan/Controls and Implementation NRC Table Top/Pilot May 7 - 10, 2012 Inspection 1st Qtr 2013 TVA Corp and NRC discussing date Look at dates after new schedule Heinrich/Snyder (Bryan)

2.

Complete Implementation (Hemmer)

Pump Relocation 5/30/12 Bldg Plan Align with upcoming order for Fukushima Inspection - Oct 2012 Substantial building - preliminary planning in process, (Fukushima NTTF item 4.2)

Provide document of mitigating equipment and location for unit 2.

Hemmer

3.

Fire Protection Report

1. 4/15/12
2. ~5/1/12
1. Submit Revised FPR per 12-21 Meeting, include commitment update
2. Meet with Staff following submittal ENG/Hilmes (Arent)
4.

Tech Spec Revisions from latest T/S markup and NRC Review comments

1. TBD/12
2. Submitted
3. 3/15/12
4. 3/15/12
5. 3/30/12
1. CSST A & B
2. I-131 DEI
3. Diesel Generator Frequency
4. AST FHA
5. Licensing Basis Amendment Hydrology Licensing/Elton (Bryan)

NRC PM Open Items List 03/14/2012 (423) 751-7777 ID 4233658764#

2 l P a g e No.

Description Status Additional Comments Resp Org/Person

5.

ACRS Sept., 2012 Project Status/Schedule Fire Protection Attachment HH item - #133/134 - Hydrology Cyber Security - Implementation Attachment HH items (#59 - Sump, #61 -PAD,

  1. 63/93 - Eagle 21, #91 - GDC 5, #132 - Boron Dilution)

Arent

6.

SSER 22/23/24/25 Open Items

Response

As needed Add individual item to matrix.

Licensing

7.

Transient Analysis issues Boron dilution RAI response 1/13/12 Question on RG revision and modes 3, 4, & 5. TVA to provide write-up explaining NRC acceptance (CLB) of unit 1 for modes 3, 4, & 5. See SSER OI 132.

ENG/Koontz WEC/Morgan

8.

Develop list of planned License Conditions, Exemptions and Relief Requests (Arent)

1. 1/20/12
2. TBD
3. TBD
4. TBD
1.

Review Unit 1 SER for exemptions. Sand baskets, cyber security, physical security, PAD 4.0

2.

NRR to review current exemptions

3.

Verify required notifications made

4.

Relief Requests needed for ISI/IST NRR/TVA (Bryan)

9.

Issue two Unit Offsite Dose Calculation Manual -

5/31/12 Chemistry/

Woods (Bryan)

10.

TMI action items 7/1/12 TVA to provide letter when TMI actions are field complete.

Licensing (Gordon)

11.

EP Drill Open Items

a. Duty Specialist
b. Commercial Dose Assessment TBD Determine NPG Schedule for Changes - Update AS-Built E-Plan.

EP -

Detchemendy

12.

Extend Construction Permit Extend Part 70 License 5/25/12 Lic (Arent)

13.

Info For Commissioner Drop-In 5/4/12 Lic (Arent)

14.

GSI-191 Resolution 3/22/12 4/16/12 Phone call with NRC - screen bypass TVA to provide letter Eng Koontz (Bryan)

NRC PM Open Items List 03/14/2012 (423) 751-7777 ID 4233658764#

3 l P a g e No.

Description Status Additional Comments Resp Org/Person

15.

Fukushima Letters 3/12

1. NRC issue letters
2. TVA/Industry response approach
3. TVA plan for WBN U2
4. Flood Report
16.

Exemption to 10CFR50.49 for some Category II cables?

3/24/12 Submit a proposed license condition.

Hilmes (Stockton)

17.

Next TVA NRC meeting Week of 3/13/12 Lic (Arent)

18.

Hydrology Public Mtg.

3/27/12 Licensing (Arent)/NRC (Poole)

19.

NRC Follow-up Items ASME N-801 & N-802 code cases Received NRC response to relief request submitted 9/1/11.

NRR Post ETC Updates Issue Unit 2 Completion Letter TBD Licensing/Arent Submit final as-constructed FSAR figures TBD Licensing/

Stockton Discuss Project Schedule 5/8/12 Skaggs/Arent Letter to terminate Part 30/40 License after receipt of Part 50 License TBD Licensing (Arent)

Combined U1/U2 FSAR (Stockton)

TBD Licensing ASME Section III N-3 report TBD Eng/Crouch Letter to notify NRC when Vital Area Boundary returned to original location TBD Security Plan Update - Boundary to be restored.

Lic/Arent