SEQUOYAH NUCLEAR PLANT JOB PERFORMANCE MEASURE 1201 NRC SIM A (ROISRO)
1201 NRC Simulator JPM A Page 2 of 9 ROISRO JOB PERFORMANCE MEASURE Task:
Reinstate source range detectors following a reactor trip.
Task#:
0000910501 Task Standard:
Source range detectors are manually reinstated following a reactor trip.
Alternate Path:
YES:
X NO:
Time Critical Task:
YES:
NO:
X KIA Reference!Ratings:
EPE 007 EA1.05 (4.0/4.1)
Method of Testing:
Simulated Performance:
Actual Performance:
X Evaluation Method:
Simulator X
In-Plant Classroom Main Control Room Mock-up Performer:
Trainee Name Evaluator:
I Name I Signature DATE Performance Rating:
SAT:
UNSAT:
Validation Time:
8 minutes Total Time:
Performance Time:
Start Time:
Finish Time:
COMMENTS
SPECIAL INSTRUCTIONS:
1.
Ensure Simulator Operator Checklist is complete 2.
ResettolC3ol 3.
If IC 301 is not available perform the following:
ResettolCl6 Trip the reactor Insert malfunction NIO4A f:40 Allow simulator to run until Channel 2 IRM is < 1 0%
4.
Ensure TD AFW pump LCV are CLOSED 5.
An extra operator will be required to acknowledge alarms.
6.
ACKNOWLEDGE ALARMS 7.
FREEZE SIMULATOR.
8.
Provide a copy of ES-0. 1, Reactor Trip Response 9.
Save as a temporary IC, if repeat runs of JPM will be desired.
- 10. PLACE SIMULATOR IN RUN
1201 NRC Simulator JPM A Page 3 of 9 ToolslEquipmentlProcedures Needed:
ES-0. 1, Reactor Trip Response
References:
Reference 1.
ES-0.1 L
Title Rev No.
I Reactor Trip Response 34
1201 NRC Simulator JPM A Page 4 of 9 DIRECTIONS TO TRAINEE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM.
I will provide initiating cues and reports on other actions when directed by you.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Ensure you indicate to me when you understand your assigned task. Assume all independent and concurrent verifications are completed when called for by the procedure. To indicate that you have completed your assigned task return the handout sheet I provided you.
HAND JPM BRIEFING SHEET TO EXAMINEE AT THIS TIME!
INITIAL CONDITIONS:
1.
Unit 1 is in MODE3 2.
ES-C. 1, Reactor Trip Response was entered and the crew just completed Step 13.
INITIATING CUES:
1.
The SRO has directed you to continue the performance of ES-C. 1, Reactor Trip Response starting at step 14.
2.
Inform the SRQ when step 14 is complete.
1201 NRC Simulator JPM A Page 5 of 9 Start Time STEP 1
Obtain a copy of ES-O. 1, Reactor Trip Response SAT UNSAT Standard:
Examinee obtains a copy of ES-0.1, Reactor Trip Response Provide a copy of ES-0. 1, Reactor Trip Response Comment STEP 2
14.
MONITOR tf source range ctanneIs SAT should be reinstated:
U NSAT a CHECK intermediate range flux less than 1O% power on operable channeis Standar&
Examinee checks Channel 2 IRM % power N-36 less than 10% on (1-XI-92-5004A)
If examinee recommends transitioning to AOP-L01 for IR NI failure, provide the following cue, Another operator will perform that procedure and continue restoring the SRNI.
Cue If examinee recommends transitioning to step 15 provide the following cue, Another operator will perform step 15.
Examiner Channel 1 IRM % N-35 is failed at greater than 10% on (1-Xl Note:
5003A)
Comment
1201 NRC Simulator JPM A Page 6 of 9 STEP 3
14.
MONITOR it source range ctannels SAT should be reinstated:
UNSAT b
CHECK source range channels REINSTATED Examinee checks both Source Range indicators N-31 (1-Xl-92-5001A)
Standard:
and N-32 (1-Xl-92-5002A) indicating low scale deflection (0) and transitions to the RNO Comment STEP 4
Standard:
Comment U NSAT Critical Step STEP 5
14.
MONITOR if source range channels SAT should be reinstated:
- c. ENSURE at least one SRM and IRM UNSAT displayed on NR-45 recorder Standard Examinee selects one SRM and IRM Channel N-36 are displayed on NR-45 recorder (1-XR-92-5001).
Cornment
14.
MONITOR if source range ctiannels should be reinstated:
- d. ENSURE audio count rate operation.
Examinee selects setting on Audio Multiplexer for a slow continuous beeping and adjusts volume as desired at Audio Count Rate Drawer, 1-XX-92-5039, on 1-M-13.
14.
MONITOR if source range channels should be reinstated:
e RESET shutdon monicr alarm sepoims. M-13J Examinee depresses RESET pushbutton located to the right of the ALARM SETPOINT LED indica r on
- IS-92-5002 el 1201 NRC Simulator JPM A Page 7 of 9 SAT U NSAT STEP 7
- e. RESET slnitdown monitor alarm setpoints. [M-1 31 Standard:
SAT UNSAT Critical Step Examiner Note:
JPM step 8 may be performed before JPM step 7.
Comment STEP 8
Standard:
SAT UNSAT Critical Step Comment
1201 NRC Simulator JPM A Page 8 of 9 Terminating The task is complete when the Examinee returns the JPM briefing STOP Cue:
sheet to the examiner.
STEP 10 14.
MONITOR if source range thannels should be reinstated:
SAT f
WHEN shutdown monitor ALARM LEDs dark AND HIGH FLUX AT SHUTDOWN bistable lights dark, THEN PLACE HIGH FWX AT SHUTDOWN alarm block switches in NORMAL
[M-1 3]
UNSAT Critical Step Standard:
Comment rangeC IM-i Stop Time
1201 NRC Simulator JPM A Page 9 of 9 JPM BRIEFING SHEET The examiner will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Assume all independent and concurrent verifications are completed when called for by the procedure.
INITIAL CONDITIONS:
1.
Unit 1 is in MODE3 2.
ES-O. 1, Reactor Trip Response was entered and the crew just completed Step 13.
INITIATING CUES:
1.
The SRO has directed you to continue the performance of ES-0. 1, Reactor Trip Response starting at step 14.
2.
Inform the SRO when step 14 is complete.
Acknowledge to the examiner when you are ready to begin.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
SEQUOYAH NUCLEAR PLANT JOB PERFORMANCE MEASURE 1201 NRC SIM B (ROISRO)
1201 NRC Simulator JPM B Page 2 of 15 ROISRO JOB PERFORMANCE MEASURE Task:
Shift CVCS Makeup Mode to Automatic Task#:
0040090101 Task Standard:
Chemical Volume Control System makeup selector switch is selected to AUTO and the blender controls are aligned to provide automatic blended makeup to the Volume Control Tank with a Boric Acid Flow Rate controller setpoint of between 13 and 14%.
Alternate Path:
YES:
NO:
X Time Critical Task:
YES:
NO:
X KIA Reference!Ratings:
004 A4.12 (3.8/3.3)
Method of Testing:
Simulated Performance:
Actual Performance:
X Evaluation Method:
Simulator X
In-Plant Classroom Main Control Room Mock-up Performer:
Trainee Name Evaluator:
/
Name I Signature DATE Performance Rating:
SAT:
UNSAT:
Validation Time:
14 minutes Total Time:
Performance Time:
Start Time:
Finish Time:
COMMENTS
1201 NRC Simulator JPM B Page 3 of 15 SPECIAL INSTRUCTIONS:
1.
Ensure Simulator Operator Checklist is complete 2.
ResettolCl6 3.
Align the following:
1-HS-62-140A normal after stop 1-HS-62-140B in MANUAL 1-HS-62-140D in closed position.
1-HS-62-144 in closed position.
1-HS-62-143 in closed position.
1-HS-62-128 in closed position.
1-FC-62-139 in MANUAL set at 85%
1-FC-62-142 in MANUAL set at 35%
4.
An extra operator will be required to acknowledge alarms.
5.
ACKNOWLEDGE ALARMS 6.
FREEZE SIMULATOR.
7.
Provide a copy of 0-SO-62-7, Boron Concentration Control and TI-44, Boron Tables.
8.
Save as a temporary IC, if repeat runs of JPM will be desired.
9.
PLACE SIMULATOR IN RUN
ToolslEquipmentlProcedures Needed:
SO-62-7, Boron Concentration Control and Tl-44, Boron Tables Calculator
References:
[
Reference
[1.
0-S0-62-7 E
TI-44 Title Rev No.
Boron Concentration Control 61 Boron Tables 12
1201 NRC Simulator JPM B Page 4 of 15 DIRECTIONS TO TRAINEE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM.
I will provide initiating cues and reports on other actions when directed by you.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Ensure you indicate to me when you understand your assigned task. Assume all independent and concurrent verifications are completed when called for by the procedure. To indicate that you have completed your assigned task return the handout sheet I provided you.
HAND JPM BRIEFING SHEET TO EXAMINEE AT THIS TIME!
INITIAL CONDITIONS:
1.
Unit 1 is MODE 1, 100% power.
2.
CVCS blender controls are in the OFF position.
3.
The reactor coolant system boron concentration is 620 ppm 4.
BAT A boron concentration is 6880 ppm.
5.
Boron 10 depletion value is 0.
6.
Manual makeup to the RWST was performed earlier in the shift and has been completed using SO 62-7, Boron Concentration Control section 8.3.1 through step 27.
7.
All prerequisites of SO-62-7, Boron Concentration Control section 4 are complete.
INITIATING CUES:
1.
The SRO has directed you to align the blender controls for AUTO makeup to the CVCS using 0-SO-62-7, Boron Concentration Control Section 5.1.
2.
Inform the SRO when complete.
1201 NRC Simulator JPM B Page 5 of 15 Start Time STEP i
Obtain a copy of S0-62-7, Boron Concentration Control SAT UNSAT Standard:
Examinee obtains a copy of S0-62-7, Boron Concentration Control.
Provide a copy of S0-62-7, Boron Concentration Control Cornment
1201 NRC Simulator JPM B Page 6 of 15 5.1 Automatic Makeup CAUTION Returning the Boric Acid Blender to service after unplugging, cleaning, or maintenance on the Boric Acid System could introduce debris, sludge, air or chunks of solidified boron into the CCP suction resuttmg in pump damage. Extreme care must be exercised to properly flush the Boric Acid Blender system following an outage. [C.2j NOTE I This is th.e :nomial mode of operation of the Rx. Makeup Control System. This allows for automatic makeup to VCT to compensate for leakage and/or temperature/density changes during transients/emergencies. However, Section 65 (Manual Makeup) is preferred for normal makeup in Modes I and 2.
NOTE 2 Nuclear instrumentation and reactor coolant temperature should be monitored following auto makeup to ensure dired response is obtained.
NOTE 3 it will take approximately 15 minutes before any changes to reactivity are indicated on nuclear instrumentation or RCS temperature indication.
NOTE 4 Flow oscillations and/or erratic controller response may require manual operation of Boric Acid Flow Controller tC42-i39] and Primary Water Flow Controller [FC-62-j2 until stable conditions exist.
STEP 2
1] ENSURE P:rerequisites Section 4.0 is complete.
SAT UNSAT Standard:
Examinee ensures Prerequisites Section 4.0 is complete.
Examiner All prerequisites of SO-62-7, Boron Concentration Control section 4 Note:
were complete in the initial conditions.
Examiner The following 5 JPM steps are from SO-62-7, Boron Concentration Note:
Control APPENDIX M.
Comment
t2 PERFORM Appendix M Calculation of Boric Acid integrator Setting for 4uto Makeup
[5]
CALULAIE B-ic; ccx!ecte 1x)ron icentraton r
STE!
STEP 13 B-1Ocoecwd bccon Standard:
xa late 0 c rrected boron concentration of 6 Comment 1201 NRC Simulator JPM B Page 7 of 15 STEP 3
[23 PERFORM Appendix M calculation ofBoric Acid Integrator SAT Setting for Auto Makeup.
U NSAT APPENDIX M Page 1 oft CALCULATION OF BORIC ACID CONTROLLER SETtING FOR AUTO MAKEUP
[1]
OBTAIN Current RCS Boric Acid Concentration
[2]
OBTAIN Current BAT Boric Acid Concentration
[31 OBTAIN B-I0 depletion vaiue from Rx Eng information page PPM Examinee obtains values for the following from the Initial Conditions.
RCS boron concentration 620 ppm Standard:
Boric Acid Tank A concentration 6880 ppm Boron Depletion 0 Comment STEP 4
PERFORM Appendix M Calculation ofBoric Acid Integrator Setting for Auto Makeup.
Standard:
14]
CALCULATE BAT Boflc Acid Concentration Ralio (BACR): 6820 ppm ÷ step [2] ppm =
SAT UNSAT Critical Step Cornment STEP 5
1201 NRC Simulator JPM B Page 8 of 15 STEP 6
[2]
PERFORM Appendix M Calculation of Boric Acid integrator SAT Setting for Auto Makeup.
ir
ttfr I
UNSAT 161 RECORD Corrected Boric Acid Controller Sett,g from 11-44 Appendix C Table 2;
Critical Step Standard Exainiflee records Cqrrected Boric Acid Controller Setting4rornTl-44 Appendix C Table 2 of 13.8 Comment STEP 7
PERFORM AppendixM Galculation OfBonc Acid Integrator fr SAT Setting for Auto Makeup.
UNSAT
(____
m 9)8ACRfromstep4)=
Critical Step CcTectedBonc A4 Coo1&Seng(Step6))) 3
Standard:
-Eamjnee Ca culatçs oçjAdd.doptroHer Setting of 13J!
Comment NOTE Due to eyeball interpolation the veritled calculation may slightly ditfer from the initial calculation. The foliong signoff indicates that any differences in the two results have been discussed and are close enough to be considered validated.
STEP 8
[3]
PERFORM Appendix N Independent Verification for SAT Calculation ofBoric Acid Integrator setting for Auto Maleup U NSAT Standard Examinee addresses receiving an independent verification for the Boric Acid Integrator setting Cue Provide the following cue, The SRO has performed independent verification and agrees with your calculation.
Comment
1201 NRC Simulator JPM B Paqe 9 of 15 STEP 9
Bone Acid Pump Speed Selector switches SAT jNS-62.230D] arid [HS-62-2320] are in the SLOW SPd POSIO1L U NSAT Standard:
Examinee verifiesl-HS-62-230D BA Transfer Pump 1A Speed Sel and 1-HS-62-232D lB BA Transfer Pump 1A Speed Sel are in SLOW.
Comment
[51 IF a Boric Acid Pump is not in service, THEN STEP 10 SAT ENSURE a Boic Acid Pump is aligned per 0-50-62-If) and start Boiic Acid Pump(s) using IHS-62-230A1 and/or UNSAT IHS-62-232A1.
Standard:
Examinee verifies a Boric Acid Pump is in service per 0-SO-62-10 and marks the step as N/A.
Comment STEP 1 1
[6]
IF a Boric Acid Pump(s) are in FAST speed, THEN SAT RETURN Boric Acid Transfer pumps to slow speed b cycling 1Hs42-230A] and/or [Hs-62-232A1.
UNSAT Standard Examinee cycles 1-HS-62-230A 1-HS-62-232A, Boric Acid Transfer pumps to slow speed.
Comment
[!Ii SURE F62-1. Blen routlet to Chargbig Pump Suion s CLOSED and IHS-62.4441 is in the P-AUTO riij iIIPcF 1201 NRC Simulator JPM B Page 10 of 15 TEP 13
[8]
ENSURE IFCV-62-1281, B1enderOuetVaIvetotheVCT SAT Inlet is CLOSED and IHS-62-1281 is in the P-AUTO UNSAT CriticaiStep Standard Comment STEP SAT UNSAT Critical Step Exammee pIces 1-HS-62-144 Aakeup toCharginPupp 4 -
4
1201 NRC Simulator JPM B Page 11 of 15 U N SAT Critical Step U NSAT Critical Step STEP 15
[10] ENSURE [Fcv-62$431, Primary WaterValveto the Blender SAT isCWSEDand[HS62-143]lsinthePAUTOposition.
I Standard:
H82443iPnti&y Wa1er uppiS1 Comment
[111 ENSURE [11542-1400] onc \\cid Valve to the 8Ienier s STEP 16 nthePAUTO pos:tlon.
plaáes 1-NS-62-l4OD.B6ric Acid Supry
4 STEP 17
[121 ENSURE fFQ-62-1391, Batch Integratocis set to zero.
SAT U NSAT Standard:
Examinee ensures I -FQ-62-1 39, Batch Acid Counter is set to zero.
Comment
1201 NRC Simulator JPM B Page 12 of 15
[141 ENSURE W42i39] Boric Acid Flow Co olleris in the AUTO Position.
Standard i%repac4s 1-p bri AcTdto BIende1ióCi(
to AUTO.
Comment
[15] ENSURE fFQ-62.j4], Batch Integrator, is set to zero.
STEP 20 SAT UNSAT Standard:
Examinee ensures 1-FQ-62-142, Primary Water Batch Counter is set to zero.
Comment SED 10
[13] ADJUST fFC-624], B)1ic Acid FlOW Controller to the I
I I
desired bnd solution, in accordance with Appendix M.
SAT to U N SAT Critical Step STEP 19 SAT UNSAT Critical Step
1201 NRC Simulator JPM B Page 13 of 15
[171 ENSURE ende STARTED us.n [i2-14CAl. Bcrc Ac.c To slender Row ccntro Swdch.
Ajy To Blej Standard:
NOTE Pilmary Water Flow Controfler [Fc.62-1 421, receives its makeup reference snal (70 pm) from a remote setpoint located th the racks.
The setpoint on me potentiometer (dial indicator) on M-6 has no etfed on the primary water fiowrate for AUTO makeup D
[16] ENSURE [EC-62-142], Pilmary Water to Blerer Flow ci 2
controller is in the AUTOpj SAT U NSAT Standard Examinee places 1-FC-62142, Primary Water to Blender Flow Controller in AUTO.
Comment STEP 22 SAT U NSAT Critical Step Comment TEP
[18]VERlFYB(wicAadvalvetotheBlenderWcV$2-I4fls SAT
.J OPEN by red liqht UT on IHS-62-140D1.
U NSAT Examinee verifies Boric Acid valve to the Blender 1-FCV-62-140 is Standard:
OPEN by observing red light above HS-62-140D Boric Acid valve to the Blender ON.
Comment
1201 NRC Simulator JPM B Page 14 of 15 STEP 24 iii VERIFY foIkiwirig SAT
[a] [H542-125} in the P-AUTO POSItlOIL UNSAT
[hI EHS-62-1441 n P-AUTO
[c] [HS-62-140D1 in the P-AUTO position.
[dl EHs-62-1431 n the P-AUTO position.
[e] [HS-62-141)8] in the AUTO pton Standard Examinee addresses the requirement to obtain independent verification for valve positions.
Cue Provide the following cue, Another operator will complete the remaining steps of this procedure.
Comment Terminating The task is complete when the Examinee returns the JPM briefing ue.
sheet to the examiner Stop Time
1201 NRC Simulator JPM B Page 15 of 15 JPM BRIEFING SHEET The examiner will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Assume all independent and concurrent verifications are completed when called for by the procedure.
INITIAL CONDITIONS:
1.
Unit 1 is MODE 1, 100% power.
2.
CVCS blender controls are in the OFF position.
3.
The reactor coolant system boron concentration is 620 ppm 4.
BAT A boron concentration is 6880 ppm.
5.
Boron 10 depletion value is 0.
6.
Manual makeup to the RWST was performed earlier in the shift and has been completed using SO-62-7, Boron Concentration Control section 8.3.1 through step 27.
7.
All prerequisites of SO-62-7, Boron Concentration Control section 4 are complete.
INITIATING CUES:
1.
The SRO has directed you to align the blender controls for AUTO makeup to the CVCS using 0-SO-62-7, Boron Concentration Control Section 5.1.
2.
Inform the SRO when complete.
Acknowledge to the examiner when you are ready to begin.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
SEQUOYAH NUCLEAR PLANT JOB PERFORMANCE MEASURE 1201 NRC SIM C (ROISRO)
1201 NRC Simulator JPM C Page 2 of 13 ROISRO JOB PERFORMANCE MEASURE Task:
Transfer to Hot Leg Recirculation Task#:
0000790501 Task Standard:
Realign RHR to cold leg injection with a failure of a RHR hot leg injection valve to open.
Alternate Path:
YES:
X NO:
Time Critical Task:
YES:
NO:
X KIA Reference/Ratings:
EPE 011 EA1.11 (4.2/4.2)
Method of Testing:
Simulated Performance:
Actual Performance:
X Evaluation Method:
Simulator X
In-Plant Classroom Main Control Room Mock-up Performer:
Trainee Name Evaluator:
/
Name I Signature DATE Performance Rating:
SAT:
UNSAT:
Validation Time:
15 minutes Total Time:
Performance Time:
Start Time:
Finish Time:
COMMENTS
1201 NRC Simulator JPM C Page 3 of 13 SPECIAL INSTRUCTIONS:
1.
Ensure Simulator Operator Checklist is complete 2.
ResettoIC300 3.
Ensure the following remote functions are inserted:
a.
IRE RHR14f:l (ECV-63-l) b.
IRE SIRO6 f:0 (ECV-63-22) (Verify power on during setup) c.
lOR ZDIHS63172A f:0 (Eails ECV-63-172 closed) 4.
If IC 300 is not available perform the following:
a.
Resetto 1024 b.
Ensure THOIAf:I0 is inserted c.
Trip RCPs d.
After automatic containment sump swapover is initiated, perform required alignment of ECCS to containment sump per ES-i.3.
e.
Place operating power on ECV-63-i (remote function IRE RHR14 f:i).
f.
When RWST level decreases to 8% realign containment spray pump suction to containment sump per ES-I.3.
g.
Ensure operating power ON ECV-63-22 (Check remote function main menu for IRE SIRO6 f:0, this task should have been performed in E-i).
h.
Insert override IORZDIHS63172Af:0 (Eails [ECV-63-i72] CLOSED) 5.
An extra operator will be required to acknowledge alarms.
6.
ACKNOWLEDGE ALARMS 7.
FREEZE SIMULATOR.
8.
Provide a copy of ES-i.4, Transfer to Hot Leg Recirculation 9.
Save as a temporary IC, if repeat runs of JPM will be desired.
ToolslEquipmentlProcedures Needed:
ES-i.4, Transfer to Hot Leg Recirculation
References:
Reference Title Rev No.
ES-i.4 Transfer to Hot Leg Recirculation 6
1201 NRC Simulator JPM C Page 4 of 13 DIRECTIONS TO TRAINEE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM.
I will provide initiating cues and reports on other actions when directed by you.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Ensure you indicate to me when you understand your assigned task. Assume all independent and concurrent verifications are completed when called for by the procedure. To indicate that you have completed your assigned task return the handout sheet I provided you.
HAND JPM BRIEFING SHEET TO EXAMINEE AT THIS TIME!
INITIAL CONDITIONS:
1.
Unit I in MODE 5 following an event.
2.
All ECCS components and Containment Spray pumps are aligned and taking suction from containment sump per ES-i.3, Transfer to RHR Containment Sump.
3.
RCS pressure is less than 180 psig.
4.
Both RHR pumps are in service.
5.
RHR spray is NOT in service.
6.
5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> have elapsed since the time of the event.
INITIATING CUES:
1.
You have been directed to transfer to hot leg recirculation using ES-I.4, Transfer to Hot Leg Recirculation.
2.
Inform the SRO when complete.
1201 NRC Simulator JPM C Page 5 of 13 Start Time STEP 1
Obtain a copy of ES-i.4, Transfer to Hot Leg Recirculation.
SAT UNSAT Standard:
Examinee obtains a copy of ES-i.4, Transfer to Hot Leg Recirculation.
b1 Provide a copy of ES-i.4, Transfer to Hot Leg Recirculation.
Cornment STEP 2
t DETERMINE if RHR spray SAT should be isolated:
- a. CHECK RHR spray IN SERVICE:
- a. GO TO Step 2.
UNSAT Train A RHR spray valve FCV-72-40 OPEN OR Train B RHR spray valve FCV-72-41 OPEN.
Examinee determines RHR spray is NOT in service from the initiating cue Standard or by observing green lights above i-HS-72-40A Train A RHR spray valve and i-HS-72-4iA Train B RHR spray valve are ON and transitions to step 2.
Corn ment STEP 3
2.
CHECKRHRpUrnpA-ARUNNING.
SAT U NSAT Standar&
Examinee verifies RHR pump iA-A running, by observing red light ON and green light OFF above 1-HS-74-iOA RHR pump IA-A.
Comment
1201 NRC Simulator JPM C Page 6 of 13 j
STEP 6
a AlIGN RHR Train A for hot leg recirculation:
c.
OPEN RHR Train A discharge crosstie valve FCV-74-33.
Standard:
Lminee places 1-HS-7!FHR HB crossis Comment STEP 4
ALlGNRHRTrainAforhotleg SAT recwculation:
VV a
CLOSE RHR Train A cold teg UNSAT isolation valve FCV-63-93, Critical Step T
Standard:
Exéminee places 1-fIS-6S-93A, RHR CL Inj to Loop 2&3toCLOSE.
V Examiner Alarm on M-6D, window E-6, Group 6 Monitor Lights Component Off Note:
Normal will come in when 1-FCV-63-93 is closed.
Comment STEP 5
3.
ALIGN RHR Train A for hot leg SAT recirculation:
U NSAT b.
ENSURE RHR Train B discharge crosslie valve FCV-74-35 CLOSED.
StandardS Examinee verifies 1-FCV-74-35 CLOSED by observing green lights above 1-HS-74-35A RHR HX lB crosstie valve are ON.
Comment SAT UNSAT Critical Step
1201 NRC Simulator JPM C Page 7 of 13 STEP 7
3 ALIGN RHR Twin A for hot SAT recircu1aton:
d.
OPEN RHR hot leg injection valve UNSAT FCV-63-i 72.
Examinee places 1-HS-63-172A, RHR HL lnj to Loops 1&3 to OPEN Standard:
observes green lights above 1-HS-63-172A remain ON and transitions to RNO.
Comment ALTERNATE PATH STEP 8
SAT 3.
ALIGN RHR Train A for hot leg recirculation:
U NSAT PERFORM the following:
- 1) ENSURE RHR hot leg injection ECV-63-172 CLOSED Standard:
Examinee observes green lights above 1-HS-63-172A are ON.
Comment
1201 NRC Simulator JPM C Page 8 of 13
- 3) ENSURE RHR Train A cold leç vaLve FCV-63-93 OPEN STEP 10 ALTERNATEPATh :
3.
ALIGN RHR Train A for hot leg recircuLation:
PERFORM the following:
SAT UNSAT Critical Step Alarm on M-6D, window E-6, Group 6 Monitor Lights Component Off Normal will clear when 1 -FCV-63-93 is open.
1201 NRC Simulator JPM C Page 9 of 13 ALTERNATE PATH I
ALIGN RHR Train A for hot leg redrcuIation:
PERFORM the fflowlng:
- 4) IF FCV-63-172 is known to be unavailable (NOT capable of opening from MCR),
THEN GO TO Step it Standard:
Examinee transitions to step 1 1.
Comment STEP 12 Ii.
CHECK SI pump A-A RUNNING SAT UNSAT Examinee verifies SI pump 1A running, by observing red light ON and Standard:
green light OFF above 1-HS-63-IOA SI pump 1A.
Comment STEP 13 Standard:
Comment
- 12.
ALIGN SI pump A-A for hot leg recirculation:
SAT U N SAT Critical Step STEP 11 SAT UN SAT
ALIGN Si pump A-A for hot leg recirculation:
b CLOSE SI Train A crosstie FCV-63--i 5Z 1201 NRC Simulator JPM C Page 10 of 13 xmineeptaces 1-HS63452Sl Pum1AC1nj1 Lan..iaftI.
E Examiner Alarm on M-6D, window E-6, Group 6 Monitor Lights Component Off Note:
Normal will come in when 1-FCV-63-152 is closed.
Comment 12, ALIGN SI pump A-A for hot leg recirculation:
ir c
WHEN FCV-63-152 dosed ThEN PERFORM the following:
- wvir
- 1) OPEN Si Train A hot leg injection
1201 NRC Simulator JPM C Page 11 ofl3 STEP 16 11 ALIGN Si pumpA-Aforhot leg SAT recirculation:
irbL UNSAT c.
WHEN FCV-63-152 closed, Critical Step PERFORM the following:
- 2) START SI pump Ak Standard:
Examhe 1ac pump 1A to Cue Provide the following cue, Another operator will complete the remaining steps in this procedure.
Comment Terminating The task is complete when the Examinee returns the JPM briefing STOP Cue:
sheet to the examiner.
Stop Time
Swapover is manually done by operators in the Main Control Room.
RHR Sequence:
Close A Train cold leg isolation valve FCV-63-93 Ensure RHR Train B discharge crosstie valve FCV-74-35 is closed Open Train A crosstie valve FCV-74-33 Open RHR hot leg recirculation valve FCV-63-172 Close B Train cold leg isolation valve FCV-63-94 SI Sequence: One train is completed at a time.
A Train Stop SI Pump A-A Close Tm A Crosstie FCV-63-152 Open Tm A HIL valve FCV-63-156 Start SI Pump A-A B Train Stop SI Pump B-B Close Tm B Crosstie FCV-63-153 Open Tm B HIL valve FCV-63-157 Start SI Pump B-B After both SI pumps aligned for Hot Leg Recirculation Close FCV-63-22 SI pump CL injection 1201 NRC Simulator JPM C e 12 of 13 Hot Leg Recirculation Swapover:
1201 NRC Simulator JPM C Page 13 of 13 JPM BRIEFING SHEET The examiner will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Assume all independent and concurrent verifications are completed when called for by the procedure.
1.
Unit 1 in MODE 5 following an event.
2.
All ECCS components and Containment Spray pumps are aligned and taking suction from containment sump per ES-I.3, Transfer to RHR Containment Sump.
3.
RCS pressure is less than 180 psig.
4.
Both RHR pumps are in service.
5.
RHR spray is NOT in service.
6.
5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> have elapsed since the time of the event.
INITIATING CUES:
1.
You have been directed to transfer to hot leg recirculation using ES-I.4, Transfer to Hot Leg Recirculation.
2.
Inform the SRO when complete.
Acknowledge to the examiner when you are ready to begin.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
SEQUOYAH NUCLEAR PLANT JOB PERFORMANCE MEASURE 1201 NRC SIM D (ROISRO)
1201 NRC Simulator JPM D Page 2 of 15 ROISRO JOB PERFORMANCE MEASURE Task:
Swap RHR Pumps (A Train to B Train) with Level in the Pressurizer Task#:
0050030101 Task Standard:
B Train RHR is placed in service injecting to Loops 1
& 4.
Alternate Path:
YES:
NO:
X Time Critical Task:
YES:
NO:
X KIA ReferencelRatings:
005 A4.01 (3.6/3.4)
Method of Testing:
Simulated Performance:
Actual Performance:
X Evaluation Method:
Simulator X
In-Plant Classroom Main Control Room Mock-up Performer:
Trainee Name Evaluator:
I Name I Signature DATE Performance Rating:
SAT:
UNSAT:
Validation Time:
11 minutes Total Time:
Performance Time:
Start Time:
Finish Time:
COMMENTS
1201 NRC Simulator JPM D Page 3 of 15 SPECIAL INSTRUCTIONS:
1 Ensure Simulator Operator Checklist is complete 2.
ResettolC302 3.
Ensure A Train RHR is in service with flow aligned through FCV-63-93 to Loops 2 & 3.
4.
An extra operator will be required to acknowledge alarms.
5.
ACKNOWLEDGE ALARMS 6.
FREEZE SIMULATOR.
7.
Provide a copy of 0-SO-74-1, Residual Heat Removal System Section 8.3.2 8.
Save as a temporary IC, if repeat runs of JPM will be desired.
9.
PLACE SIMULATOR IN RUN
Tools/EquipmentlProcedures Needed:
0-S0-74-1, Residual Heat Removal System Section 8.3.2 References
[
Reference F
0-SO-74-1 Title Rev No.
Residual Heat Removal System Section 79
1201 NRC Simulator JPM D Page 4 of 15 DIRECTIONS TO TRAINEE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM.
I will provide initiating cues and reports on other actions when directed by you.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Ensure you indicate to me when you understand your assigned task. Assume all independent and concurrent verifications are completed when called for by the procedure. To indicate that you have completed your assigned task return the handout sheet I provided you.
HAND JPM BRIEFING SHEET TO EXAMINEE AT THIS TIME!
INITIAL CONDITIONS:
1.
Unit 1 had been in Mode 5 for 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.
2.
RCS boron is 1400 ppm and the previous shift determined that B Train RHR boron concentration is 1450 ppm.
3.
Shutdown margin required boron concentration is 1200 ppm.
4.
A Train RHR pump needs to be shutdown to allow MEG to add oil to the motor.
5.
B Train RHR has been checked out locally by the Auxiliary Bldg. AUO and is ready for service.
INITIATING CUES:
1.
You have been directed by the SRO to place B Train RHR in service and take A Train RHR out of service using 0-SO-74-1, Residual Heat Removal System Section 8.3.2.
2.
All prerequisites for 0-SO-74-1, Residual Heat Removal System have been completed.
3.
Align B Train injection flowpath to loops I & 4.
4.
Inform the SRO when complete.
1201 NRC Simulator JPM D PageS of 15 Start Time STEP 1
Obtain a copy of 0-SO-74-1, Residual Heat Removal System Section SAT 8.3.2 U NSAT Standar&
Examinee obtains a copy of 0-SO-74-1, Residual Heat Removal System Section 8.3.2 Cue Provide a copy of 0-SO-74-1, Residual Heat Removal System Section 8.3.2 Comment
&3..2 Placing Train B in Service and Removing Train A from Service.
CAUTION CCS flow should be adjusted to provide adequate flow through the RHR Hx to prevent RI-IR Hx CCS outlet temperature from exceeding 145°F. The RHR lix CCS outlet temperature alarm will come in a 115°F.
NOTE The following steps may require operators in both heat exchanger rooms and one outside the pump rooms.
STEP 2
[1]
IF adjustment is required on CCS flow through RHR Hxs, SAT THEN ENSURE IFCV-70-1531 RHR Hx B CCS ouDet is UNSAT THROTTLED.
Examinee verifies 1-FCV-70-153 RHR Hx B CCS outlet throttled by Standard:
observing red and green lights above 1-HS-70-153A RHR HX lB OUTLET ISOL is ON Exmker Operator may decide to keep 1 -FCV-70-1 53 Open Comment
Simulator JPM D Page 6 of 15 1201 NRC STEP 3
[2}
ENSURE [FCV-74-28] RHR Hx B Outlet is CLOSED SAT UNSAT Examinee verifies 1-FCV-74-28 RHR Hx B Outlet is CLOSED by Standard:
observing 100% output on 1-HIC-74-28A RHR Hx lB Outlet Flow Control.
Comment CAUTIONS 1)
Failure to maintain shutdown cooling flow rate for an RHR pump at the maximum possible could result in reduced thrust bearing life. tC.3]
2)
If RHR pressure downstream of pumps exceeds 600 psig with RHR aligned for Shutdown Cooling, then RHR discharge pressure must be reduced below 600 psig or RKR isolated from the RCS within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.
NOTE RHR motor lower bearing oil level will rise after pump is started and may rise above sightglass. The presence of oil can be verified by a golden tint or a milk color (two different oils approved) in sightglas&
STEP 4
[31 START RHR Pump R-B with rHS-7420A1 Standard:
Comment SAT UNSAT Critical Step
1201 NRC Simulator JPM D Page 7 of 15 STEP 4]
VERIFY IFCV-74-241 RHR Pump B-B miniflow OPENS SAT OR greater than 500 gpm is indicated on Fl-74-24.
UNSAT Examinee verifies 1-FCV-74-24 by observing red light above 1-HS Standard:
24A RHR Pump I B miniflow is ON or checks with AUO locally to verify
>500 gpm flow indicated on local flow indicator 1-Fl-47-24.
Cue:
If asked provide the following cue, 1-Fl-74-24 indicates -550 gpm.
Comment CAUTIONS 1)
To reduce vibration across FCV-74-16 and FCV-74-28 (RHR lix Outlet Valves, RI-IR must be aligned to only two cold legs with one train in service.
2>
Operating RHR pumps in parallel (HCV-74-36 and HCV-7447 OPEN or 74-530 and 74431 OPEN) and on minifiow for> 10 minutes may result in pump damage due to one pump dead-heading. [C.2] [C13]
NOTE Step 8.3.2[52] and &3.2[5..3] may be performed together to ensure continuous flow delivered to RCS.
STEP 6
Standard:
UN SAT Critical Step Comment
[5]
IF aligning Train B RHR cooling th loops I and 4, STEP 7
THEN SAT PERFORM the following:
I
[&2]
ADJUST IFCV-74-281 to establish How from Train B RHR Standard:
[5]
IF aligning Train B RHR cooling to loops I and 4, STEP 9
THEN SAT PERFORM the following:
UNSAT
[5-41 VERIFY IFCV-74-121 RHR Pump A-A minillow OPENS OR greater than 500 gpm is indicated on F[-74-24 Examinee verifies 1-FCV-74-24 RHR Pump A-A miniflow OPENS by Standard:
observing red light above 1-HS-74-24A ON or checks with AUO locally to verify >500 gpm flow indicated on local flow indicator 1-Fl-47-24.
Comment If asked provide the following cue, 1-Fl-74-24 indicates 550 gpm.
1201 NRC Simulator JPM D Page 8 of 15 Comment UNSAT Critical Step STEP 8
Standard:
[51 IF aligning Train B RHR cooling to loops 1 and 4, THEN PERFORM the following:
[5.3]
ADJUST [FCV-74-1] AND [FCV-74-32] to reduce Train A RHR flow I
ro es
-HI 4-16A RHR HX IA Outle ow counter clockwise reduce flow e
bc e
e SAT UNSAT Critical Step Comment
j i RHR tj ?
THEN PERFORM the following:
[55]
CLOSE [FCV-744*31 RHR Hx A Crosstie Isol.
x 1201 NRC Simulator JPM D Page 9 of 15
[5]
IF aligning Train B RHR cooling to loops I and 4, STEP 11 THEN SAT PERFORM the following:
UNSAT
[&6]
ENSURE FFCV-74451 RHR Hx B Crosstie Isol OPEN.
Examinee verifies 1-FCV-74-35, RHR Hx B Crosstie Isol to OPEN by Standard:
observing red light above 1-HS-74-35A RHR Hx lB Crosstie Isol is ON.
Comment
[5]
IF aligning Train B RHR cooling to loops I and 4 SAT STEP 12 THEN PERFORM the following:
UNSAT
[5-71 OPEN IVLV-74-5311 RHR Hx B to Letdown Fix.
Standard:
Examinee directs an AUO to OPEN 1-HCV-74-531 RHR Hx B to Letdown Hx.
Cue:
If asked provide the following cue, An AUO will manually open 1-HCV-74-531 RHR Hx B to Letdown Hx.
Examiner Direct the Booth Operator to modify remote function RHRO4 to 100 note:
Comment STEP 10 Standard:
Comment SAT UNSAT Critical Step
1201 NRC Simulator JPM D Page 10 of 15
[5 IF aligning Train B RF-4R cooling to loops 1 and 4, STEP 14 THEN SAT PERFORM the following:
U NSAT
[59]
OPEN [KCV-74-371 RHR Hx B Bypass.
Standard:
Examinee directs an AUO to OPEN 1-HCV-74-37, RHR Hx B Bypass Cue:
if asked provide the following cue, An AUO will manually open 1-HCV-74-37, RHR Hx B Bypass.
Examiner Direct the Booth Operator to modify remote function RHRO7 to 100 note:
Cornment
1201 NRC Simulator JPM D Page 11 ofl5
[5]
IF aligning Train B RHR cooling to loops 1 and 4 STEP 15 THEN SAT PERFORM the following:
UNSAT 5.1QJ CLOSE LHCV-74461 RHR Hx A Bypass Standard:
Examinee directs an AUO to CLOSE 1-HCV-74-36, RHR Hx A Bypass Cue If asked provide the following cue, An AUO will manually close 1-HCV-74-36, RHR Hx A Bypass.
Examiner note:
Direct the Booth Operator to modify remote function RHRO6 to 0 Comment
[5]
IF aligning Train B RHR cooling to loops I and 4, STEP 16 THEN SAT PERFORM the following:
UNSAT
[511]
CLOSE WLV-74-5301 RHR Hx A to Letdown Hx.
Standar&
Examinee directs an AUO to CLOSE 1-HCV-74-530, RHR Hx A to Letdown Hx Cue If asked provide the following cue, An AIJO will manually close 1-HCV-74-530, RHR Hx A to Letdown Hx.
Examiner Direct the Booth Operator to modify remote function RHRO3 to 0 Comment
1201 NRC Simulator JPM D Page 12 of 15
. ff51 tFaiigning Train B RRR coding to loops land 4, STEP 17
. I THEN SAT PERFORM the following:
- j[5121 ENSURE [FCV-63-931 CLOSED 311W UNSAT 31 Critical Step Standard:
qft%p1j2(d 4
- RHCLJNJoLOOb4Ij Comment
[5]
IF aligning Train B RHR cooling to loops I and 4, STEP 18 THEN SAT PERFORM the foilonng:
UNSAT
[5131 INDEPENDENTLY VERIFY the following valves:
Standard:
Examinee addresses procedure step.
Comment
1201 NRC Simulator JPM D Page 13 of 15 CAUTIONS 1)
To reduce vibration across FCV-74-1 and FCV-74-28 (RKR Hx Outlet Valves),
RKR must be aligned to only two cold legs with one train in servIce.
2)
Operating RHR pumps in parallel (HCV-74-36 and HCV-7447 OPEN OR 74-530 and 74431 OPEN): and on minifiow for> 10 minutes may result in pump damage due to one pump dead-heading. C.21 [Ci 3]
NOTE Step 8.3.2[6.4] and 8.a.2[6.5] may be performed together to ensure continuous flow delivered to ROS.
NOTE One or both of the valves in the next step may be throttled to maintain RCS at desired temperature
[1]
THROTTLE one or both of the following to maintain desired STEP 20 cooling rate (NJA if not Throttled):
SAT VALVE NO.
FUNCTION INITIALS UNSAT FCV-74-28 RHR Hx B Outlet FCV-74-32 RHR Fix Bypass Examinee positions 1-HIC-74-28A, RHR Hx lB Outlet Flow Control Standard:
and 1-HIC-74-32A, RHR Hx 1A & lB Bypass flow Control to obtain desired cooldown rate.
Comment STEP 19 Standard:
Comment
[6]
IF aligning Train B RHR cooling to loops 2 and 3, THEN PERFORM the following:
Examinee determines this procedure step is not applicable from the initiating cue and proceeds to step 8.2.3.7.
SAT UNSAT
1201 NRC Simulator JPM D Page 14 of 15 STEP 21
[8]
WHEN injection flow is> 1250 gpm, SAT VERIFY [FCV-74-241 RHR Pump B-B miniflow is CLOSED.
UNSAT Standard Examinee verifies 1-FCV-74-24 RHR Pump B-B, miniflow is CLOSED by observing green light above 1-HS-74-24 ON.
Comment STEP 22 8.32 Placing Train B in Service and Removing Train A from Service.
SAT (continued)
[9]
IF cooling water is to be removed from Train A Hx UNSAT THEN CLOSE IFCV-70-i 561 Standard:
Examinee determines this procedure step is not applicable from the cue.
Cue:
If asked provide the following cue, Cooling water will not be removed from Train A Hx.
Comment Terminating The task is complete when the Examinee returns the JPM briefing STOP Cue:
sheet to the examiner.
Stop Time
1201 NRC Simulator JPM D Page 15 of 15 JPM BRIEFING SHEET The examiner wiN explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
ssume all independent and concurrent verifications are completed when called for by the procedure.
INITIAL CONDITIONS:
1.
Unit I had been in Mode 5 for 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.
2.
RCS boron is 1400 ppm and the previous shift determined that B Train RHR boron concentration is 1450 ppm.
3.
Shutdown margin required boron concentration is 1200 ppm.
4.
A Train RHR pump needs to be shutdown to allow MEG to add oil to the motor.
5.
B Train RHR has been checked out locally by the Auxiliary Bldg. AUO and is ready for service.
INITIATING CUES:
1.
You have been directed by the SRO to place B Train RHR in service and take A Train RHR out of service using 0-SO-74-1, Residual Heat Removal System Section 8.3.2.
2.
All prerequisites for 0-SO-74-1, Residual Heat Removal System have been completed.
3.
Align B Train injection flowpath to loops 1 & 4.
4.
Inform the SRO when complete.
Acknowledge to the examiner when you are ready to begin.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
SEQUOYAH NUCLEAR PLANT JOB PERFORMANCE MEASURE 1201 NRC SIM E (ROISRO)
1201 NRC Simulator JPM E Page 2 of 8 ROISRO JOB PERFORMANCE MEASURE Task:
Place 1 B H2 Analyzer In Service Task#:
0280030101 Task Standard:
Place Ui B Train H2 Analyzer in service for a post maintenance test.
Alternate Path:
YES:
NO:
X Time Critical Task:
YES:
NO:
X KIA Reference/Ratings:
028 A4.03 (3.1/3.3)
Method of Testing:
Simulated Performance:
Actual Performance:
X Evaluation Method:
Simulator X
In-Plant Classroom Main Control Room Mock-up Performer:
Trainee Name Evaluator:
/
Name I Signature DATE Performance Rating:
SAT:
UNSAT:
Validation Time:
18 minutes Total Time:
Performance Time:
Start Time:
Finish Time:
COMMENTS
SPECIAL INSTRUCTIONS:
1.
Ensure Simulator Operator Checklist is complete 2.
ResettolCl6 3.
Place the following handswitches to CLOSE or OFF HS-43-210A HS-43-207 HS-43-208.
4.
An extra operator will be required to acknowledge alarms.
5.
ACKNOWLEDGE ALARMS 6.
FREEZE SIMULATOR.
7.
Provide a copy of 0-SO-43-4, Hydrogen Analyzer Section 5.2 & 5.4 8.
Save as a temporary IC, if repeat runs of JPM will be desired.
9.
PLACE SIMULATOR IN RUN
1201 NRC Simulator JPM E Page 3 of 8 ToolslEquipmentlProcedures Needed:
0-S0-43-4 Section 5.2 & 5.4
References:
Reference 0-S0-43-4 Title Rev No.
Hydrogen Analyzer 6
1201 NRC Simulator JPM E Page 4 of 8 DIRECTIONS TO TRAINEE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be Derformed for this JPM.
I will provide initiating cues and reports on other actions when directed by you.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Ensure you indicate to me when you understand your assigned task. Assume all independent and concurrent verifications are completed when called for by the procedure. To indicate that you have completed your assigned task return the handout sheet I provided you.
HAND JPM BRIEFING SHEET TO EXAMINEE AT THIS TIME!
INITIAL CONDITIONS:
1.
Unit 1 is in MODEl.
2.
Maintenance has been completed on the Train B H2 Analyzer remote panel.
3.
The clearance for the Train B H2 Analyzer has been released.
4.
Post maintenance test requires placing the analyzer in service for a period of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
INITIATING CUES:
1.
The SRO has directed you to place the Train B H2 Analyzer in standby in preparation for the PMT using 0-SO-43-4 Hydrogen Analyzer, section 5.2 starting at step 5.
2.
All prerequisites are complete 3.
Inform the SRO when complete.
1201 NRC Simulator JPM E Page 5 of 8 Start Time STEP I
Obtain a copy of 0-SO-43-4 Hydrogen Analyzer SAT U NSAT Standard:
Examinee obtains a copy of 0-S0-43-4 Hydrogen Analyzer Provide a marked up copy of 0-SO-43-4 Hydrogen Analyzer, section 52 Comment STEP 2
SAT U NSAT Critical Step Standard:
Comment STEP 3
6j IF placing Unit 1 Hydrogen Analyzer in STANDBY. THEN SAT PLACE Analyzer inlet valve handswitch 11415-43-4521 for UNSAT
[1.FSV43452j and [1-FSV43-453J in the P-AUTO position
(located in 480V Shutdown Boardroom 1A2 near Hydrogen Analyzer).
Standard:
Examinee directs an AUO to perform the procedure step If asked provide the following cue, AUO acknowledges and reports ue.
the procedure step is complete.
ENSURE Cntmt Il2 Analyzer inlet valve EFSV-43-2O in the P-AUTO position (located on M-1 0)
Comment
1201 NRC Simulator JPM E Page 6 of 8 STEP 5
[8]
VERIFY Low Analyzer Temperature light on remote panel SAT goes out.
U NSAT Standard:
Examinee directs an AUO to perform the procedure step Cue If asked provide the following cue, AUO acknowledges and reports the Low Analyzer Temperature light on remote panel OUT.
Comment
1201 NRC Simulator JPM E Page 7 of 8 STEP 7
[10]
PERFORM Independent Verification for the following:
SAT UNSAT Standard:
Examinee addresses the procedure step.
Comment Terminating The task is complete when the Examinee returns the JPM briefing ue:
sheet to the examiner.
Stop Time
1201 NRC Simulator JPM E Page 8 of 8 JPM BRIEFING SHEET The examiner will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
ssume all independent and concurrent verifications are completed when called for by the procedure.
INITIAL CONDfl1ONS:
1.
Unit I is in MODE 1.
2.
Maintenance has been completed on the Train B H2 Analyzer remote panel.
3.
The clearance for the Train B H2 Analyzer has been released.
4.
Post maintenance test requires placing the analyzer in service for a period of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
INITIATING CUES:
1.
The SRO has directed you to place the Train B H2 Analyzer in standby in preparation for the PMT using 0-SO-43-4 Hydrogen Analyzer, section 5.2 starting at step 5.
2.
All prerequisites are complete 3.
Inform the SRO when complete.
Acknowledge to the examiner when you are ready to begin.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
SQN HYDROGEN ANALYZER Unit 0 Unit 1
Date KD,VS 5.2 Placing Hydrogen Analyzer Train B in STANDBY The Hydrogen Analyzers should normally be in STANDBY. They are only required to be operable in modes 1 and 2.
IF placing Unit 1 Hydrogen Analyzer in STANDBY, THEN VERIFY 480V Reactor MOV Boards 1A2-A and 1B2-B ENERGIZED.
IF placing Unit 2 Hydrogen Analyzer in STANDBY, THEN VERIFY 480V Reactor MOV Boards 2A2-A and 2B2-B ENERGIZED.
Power and Valve Checklists NOT performed in steps 5.2[3] and 5.2[4] may be N/Ad.
ENSURE Power Checklist complete for the appropriate unit.
Unit 1 Power Checklist 0-43-4.01.
Unit 2 Power Checklist 0-43-4.02.
ENSURE Valve Checklist complete for the appropriate unit.
Unit 1 Valve Checklist 0-43-4.03.
Unit 2 Valve Checklist 0-43-4.04.
ENSURE Cntmt H2 Analyzer inlet valve [FSV-43-2071 in the P-AUTO position (located on M-10).
[6]
IF placing Unit 1 Hydrogen Analyzer in STANDBY, THEN PLACE Analyzer inlet valve handswitch [1-HS-43-4521 for 11 -FSV-43-4521 and 11 -FSV-43-4531 in the P-AUTO position (located in 480V Shutdown Boardroom 1A2 near Hydrogen Analyzer).
l2oi tRL ffi,t E 0-SO-43-4 Rev. 0006 Page 9 of 21
SEQUOYAH NUCLEAR PLANT JOB PERFORMANCE MEASURE 1201 NRC SIM F (RO/SRO)
1201 NRC Simulator JPM F Page 2 of 18 ROISRO JOB PERFORMANCE MEASURE Task:
Perform DIG Load Test on lA-A D/G and initiate a shutdown when a high crankcase condition develops.
Task#:
0640020101 Task Standard:
The examinee will perform a D/G Operability Test using 1-Sl-OPS-082-007.A and emergency stop D/G when a high crankcase condition develops.
Alternate Path:
YES:
X NO:
Time Critical Task:
YES:
NO:
X KIA ReferencelRatings:
064 A4.01 (4.0/4.3)
Method of Testing:
Simulated Performance:
Actual Performance:
X Evaluation Method:
Simulator X
In-Plant Classroom Main Control Room Mock-up Performer:
Trainee Name Evaluator:
I Name I Signature DATE Performance Rating:
SAT:
UNSAT:
Validation Time:
20 minutes Total Time:
Performance Time:
Start Time:
Finish Time:
COMMENTS
1201 NRC Simulator JPM F Page 3 of 18 SPECIAL INSTRUCTIONS:
1.
Ensure Simulator Operator Checklist is complete 2.
ResettolCl6 3.
An extra operator will be required to acknowledge alarms.
4.
ACKNOWLEDGE ALARMS 5.
FREEZE SIMULATOR.
6.
Provide a copy of 1-Sl-OPS-082-007.A, Electrical Power System Diesel Generator IA-A, Appendix C AMBIENT MANUAL START METHOD.
7.
Save as a temporary IC, if repeat runs of JPM will be desired.
8.
PLACE SIMULATOR IN RUN 9.
At step 12 Booth Operator insert remote function EGRO7 f:1 to reset 86LOR
- 10. At step 27, Booth Operator insert annunciator override AN_OV_923 f:2.
ToolslEquipmentlProcedures Needed:
1-Sl-OPS-082-007.A, Electrical Power System Diesel Generator lA-A, Appendix C AMBIENT MANUAL START METHOD Stopwatch
References:
Reference Title Rev No.
1-Sl-OPS-082-007.A Electrical Power System Diesel Generator lA-A 50 O-AR-M26-B Annunciator O-XA-55-26B 28
1201 NRC Simulator JPM F Page 4 of 18 DIRECTIONS TO TRAINEE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be Derformed for this JPM.
I will provide initiating cues and reports on other actions when directed by you.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Ensure you indicate to me when you understand your assigned task. Assume all independent and concurrent verifications are completed when called for by the procedure. To indicate that you have completed your assigned task return the handout sheet I provided you.
HAND JPM BRIEFING SHEET TO EXAMINEE AT THIS TIME!
INITIAL CONDITIONS:
1.
Unit 1 and Unit 2 are in MODE 1.
2.
lA-A DIG is INOPERABLE due to maintenance 3.
Maintenance has been completed on the IA-A D/G and the clearance has been removed.
4.
All Section 4.0 PREREQUISITE ACTIONS of 1-SI-OPS-082-007.A are complete.
5.
Section 6.1 of 1-SI-OPS-082-007.A has been completed through step 7.c.
INITIATING CUES:
I.
The SRO has directed you to complete 1-SI-OPS-082-007.A Appendix C AMBIENT MANUAL START METHOD 2.
Inform the SRO when complete.
1201 NRC Simulator JPM F Page 5 of 18 Start Time STEP 1
Obtain a copy of 1 -Sl-OPS-082-007.A, Electrical Power System Diesel SAT Generator lA-A, Appendix C AMBIENT MANUAL START METHOD U NSAT Examinee obtains a copy of 1-Sl-OPS-082-007.A, Electrical Power Standard:
System Diesel Generator lA-A, Appendix C AMBIENT MANUAL START METHOD Cue Provide a copy of 1-Sl-OPS-082-007.A, Electrical Power System Diesel Generator lA-A, Appendix C AMBIENT MANUAL START METHOD Comment NOTE All steps in this Appendix REFER TO 1 A-A Diesel Generator (DiG) and are perfolmed from Main Control Room Panel O-M26A unless otherwise sped1cally noted
[1]
ENSURE 10-115-82481, DIG lA-A Mode Selector Switch in the STEP 2
UN((posion.
SAT U N SAT Examinee verifies 0-HS-82-18 D/G IA-A Mode Selector Switch is in Standard:
the UNIT position.
Comment
JG1A-ASynchronizeSthith
$YNosition.
4:
r STEP 3
1 [2]
PLACE fI-HS-57-471, DIG lA-A Schronze Switch in the SYN position.
1201 NRC Simulator JPM F Page 6 of 18 SAT UNSAT Critical Step El-82-35 and 0-Xl-82-33 will indicate running voltage & frequency.
NOTES 1)
ClOse communication arid coordination with held personnel is required to accomplish the 1oIkwing step. Parts tO[3.1], 1.0(3.2], and l.O[3.31 are to be performed such that D!G-DAQ is started just prior to the DIG start actuation, if used.
2)
Asopwatchnistbeusedasabac1ciqtotheD/GONilfthereisanythning discrepancy between the two, the DAQ should take precedence due to its senor accUracy.
3)
Ifthe DIG DAQ is NOT used, two stopwatches must be used to tinie the DIG start 4)
To ensure consistency and accuracy when timing OG starts the following guidelines are provided:
1 -Start stopwatch when emergency start bandswitdi depressed (manual start).
2 -Monitor voltage until the meter indicates >6800 volts (voltage stabilizes before freruency).
3-Monitor frequencyunt meter indicates >58.8 Hz STOP the watch.
STEP 4
[31 PERFORM the foflowing to initiate the DIG start signal:
SAT 111]
IF the DIG-DAQ is to be used, THEN NOTIFY D/G-DAO Operator to UNSAT START DIG-DAO.
13.2]
PROCEED with the countdown: 3,2, 1, START.
Standard Examinee notifies AUO to start the D/G-DAQ and performs a countdown Cue If asked provide the following cue, Acknowledge as AUO that the DIG-DAQ is running.
Cue If asked provide the following cue, Another operator will be operating the stopwatch.
Comment
Standard:
Examiner Note Comment 1201 NRC Simulator JPM F
[3]
PERFORM the foflwing to initiate the DIG start signal:
DEPRESS [O.HS42-16A3 DG IA-A Emergency Start Switch. AND START stopwatch 0-XA-55-26A window A-5 DIG running alarm is ON to indicate DIG > 40 rpm. Incoming voltage and frequency are verified on 0-El-82-34 and 0-Xl-82.32.
Page 7 of 18 STEP 6
PERFORM Ihe folling to initiate the DIG start signal:
[3-41 WHEN voltage> 6800 volts AND frequency> 588 Hz, THEN STOP stopwatch.
UNSAT Standard:
Examinee addresses the procedure step Cue If asked provide the following cue, The other operator stopped the stopwatch.
Comment STEP 7
Start of Critical Step(s)
[4]
VERIFY 11-FCV-67-661, ERCW cooling water supply valve is UNSAT OPEN.
End of Critical Step(s)
Examinee verifies [1-FCV-67-66], ERCW cooling water supply valve Standard:
OPEN by observing red light above 1-HS-67-66A ERCW HDR IA SUP TO DG lA-A HXAl&2 is ON.
Comment STEP 5
[33]
SAT UNSAT Critical Step 3
fl, tfl t
1201 NRC Simulator JPM F Page 8 of 18 Acceptance Criteria:
DIG IA-A starts from ambient condition and achieves, in less than or equal to 10 seconds, generator voltage 8800 volts and frequency of 58.8 Hz.
STEP 8
[5]
RECORD the time from the Stopwatch(es)
SAT Seconds Stopwatch ID Number UNSAT Seconds Stopwatch ID Number Standard Examinee obtains the data from the cue and determines acceptance criteria is MET If asked provide the following cue:
Cue STOP WATCH I TIME 948 SECONDS STOP WATCH 2 TIME 9.53 SECONDS.
Comment NOTE in order to ensure the assumptions in the safety analysis are met engineering has provided an administrative limit for steady state DiG frequency of 599 to 601 Hz. which is more restrictive than the Tech. Spec. limit of 588 to 81 2 Hz. D/G operability is based upon the Tech Spec. limit NOT this administrative limit.
Acceptance Criteria:
DIG I A-A achieves steady state generator voltage of 6800 and 7260 volts and frequency of 599 Hz and 6Q.1 Hz.
STEP 9
[6]
RECORD steady state values for following:
SAT A
fO-EI-82-41, DG IA-A Incoming Voltage UNSAT B.
[0X14221, DG lA-A Incoming Frequency Examinee obtains the data from 0-EI-82-4, DG lA-A Incoming Voltage Standard:
and 0-XI-82-2, DG IA-A Incoming Frequency and determines acceptance criteria is MET Comment
1201 NRC Simulator JPM F Page 9 of 18 NOTE Voltage Regulator Current Ammeter is in panel I of exciter cabinet Acceptance Criteria:
Voltage Regulator Control Current between ii) 2.5 dc amps. The Voltage regulator card must be functioning properly to consider DG operable.
STEP 10
[71 RECORD Voltage Regulator Control Current SAT U NSAT Standar&
Examinee obtains the data from the cue and determines acceptance criteria is MET Cue If asked provide the following cue, Voltage Regulator Control Current is 1.8 dc amps.
Comment STEP 11 rSI ENSURE DIG IA-A 186L0R1 red light NOT ILLUMINATED, at SAT DIG local relay panel.
U NSAT Standarc[
Examinee verifies DIG lA-A 86L0R red light OFF, at DIG local relay panel by local verification.
Cue If asked provide the following cue, DIG IA-A 86L0R red light at local panel in OFF.
Comment
1201 NRC Simulator JPM F Page 10 of 18 NOTE Do NOT hold [86L0R1 in RESET position if it does NOT latch on first attempt. Coil failure may result if relay is held in RESET position.
STEP 12 E9]
RESET 186L0R1, Lockout Relay, on DIG Local relay panel.
SAT UNSAT StandardS Examinee directs operator to RESET 86L0R relay, Lockout Relay, on D/G local relay panel.
Cue If asked provide the following cue, Acknowledge reset DIG 1AA 86L0R Examiner Direct the booth operator insert remote function EGRO7 to reset the DIG Note lA-A 86L0R relay Comment STEP 13
[iQj VERIFY 186L0R1 is reset by amber light 1O-Xl42-191 SAT ILLUMINATED on 0-M-26A.
UNSAT Standar&
Examinee verifies 86L0R is reset by observing amber light 0-Xl-82-19 on 0-M-26A is ON.
Comment
1201 NRC Simulator JPM F Page 11 of 18 Acceptance Criteria:
DIG IA-A starts from ambient condition and achieves, in less than or equal to 10 seconds, generator voltage 6800 volts and frequency of 58.8 Hz.
STEP 14
[111 IF DIG-DAD was used, ThEN SAT RECORD following from D/G-DAD trace:
Time required during startup to achieve 58.8 Hz. and 6800 UNSAT volts.
Seconds DO-DAD Operator Standard:
Examinee addresses the procedure step.
Cue If asked provide the following cue, Time was 95 seconds for DIG DAQ and another operator will record the data.
Comment STEP 15
[121 tE step tO6J frequency is < 59.9 Hz. or> 60.1 Hz, THEN SAT INITIATE a SR.
UNSAT Standard:
Examinee addresses the procedure step as not applicable.
Comment
1201 NRC Simulator JPM F Page 12 of 18
[ STEP 16
[13j RECORD start as Ambient Start in 0-St-OPS-082-007.M.
SAT UNSAT Standard:
Examinee addresses logging the start in 0-Sl-OPS-082-007.M.
Cue If asked provide the following cue, Another Operator will record DIG start in 0-SI-OPS-082-007.M, continue with the procedure.
Comment STEP 17
[14]
RETURN to Section 6.1 [101 of this Instruction.
SAT UNSAT Standard:
Examinee returns to Section 6.1 step 10 Comment STEP 18 Arnbiett Start Pertonnance (continued)
[101 PERFORM the foflcming to wipe the Automatic Votage Control Rheostat UNSAT (101]
RECORD voltageflom fO-El-9241.
Volts Standar&
Examinee records voltage from 0-El-82-4, DG IA-A INCOMING VOLTAGE.
Comment
1201 NRC Simulator JPM F Page 13 of 18 STEP 19
[101 PERFORM the foDcng to pe the Automatic Voltage Control SAT 110.2]
ENSURE f0-HS-82-121 DO IA-A Voltage Regulator UNSAT SMtch in the PULL-P-AUTO position.
Standard Examinee verifies 0-HS-82-12 DG lA-A VOLTAGE REGULATOR is in the PULL-P-AUTO position.
Comment STEP 20
[10]
PERFORM the foing: to iMpe the Automatic Voltage Control SAT Rheostat:
[i(L3)
LOWER voltage to 6700 volts on [O-EI-82-4] USING UNSAT
[0-HS-82-121.
Standard Examinee places 0-HS-82-12 DG IA-A VOLTAGE REGULATOR to LOWER (COUNTER-CLOCKWISE) and attains 6700 volts on El-82-4.
Comment STEP 21
[10]
PERFORM the touowing to Wipe the Automatic Voltage Control SAT Rfleostat
[104]
RAISE voltage to 7300 volts on [0-EL-824] USING UNSAT
[04-15-82-121.
Standard Examinee places 0-HS-82-12 DG lA-A VOLTAGE REGULATOR to RAISE (CLOCKWISE) and attains 7300 volts on EI-82-4.
Comment
1201 NRC Simulator JPM F Page 14 of 18 STEP 22
[101 PERFORM the foflowig to v4pe the Mtomatfc Vtae Contiol Rheostat
[1O51 RETURN voltage to value recorded in 6i[iO.1].
SAT U NSAT Standard:
Examinee places 0-HS-82-12 to LOWER (COUNTER-CLOCKWISE) and lowers voltage to the step 10.1 value.
Comment STEP 23 Standard:
Comment SAT U NSAT Critical Step
[12]
ADJUST 1O-HS-82-13l, OG IA-A Speed Ccitro4 Switct to STEP 24 onasc woscope indication ofsity rotating in the SAT
[FAST] chrection.
U NSAT Examinee adjusts 0-HS-82-13 DG IA-A Speed Control Switch such that Standard:
synchroscope (XI-82-31) is moving slowly in the fast direction (slowly clockwise).
Comment
1201 NRC Simulator JPM F Paqe 15 of 18 MW Mv Amps
{O-El..8240A)
(0..EI-8241A)
(O-E[829B) 0.5 MW 0.5 Mvar 60 Mips 1.0MW 0.75 Mvar 100 Ans 2.0 MW 1.0 Mvar 185 Amps 3.0 MW 1.0 Mvar 260 Amps 4.0 MW 1.5 Mvar 350 Amps 4.0 MW 2.0 Mvar 370 Amps 4.2MW 1.5Mvar 370 Amps 4,2MW 2.OMvar 385Amps 4.4 MW 1.5 Mvar 385 Amps 4.4 MW 2.0 Mvar 400 Amps 4.8 MW.
1.5 Mi 415 AI1)S 4.2 MWo 2,0 Mvar 430 Amps STEP 25 Standard:
[131 ENSURE [O-HS-82-121, DG IA-A Voltage Regulator Switch in PUll-P-AUTO position, AND ADJUST to match incoming voltage vith running voltage.
NOTES 1)
With Ambient Start being perfomed. the generator must be loadeti between 3.96 and 4.4 MW immediately after breaker 1912 is closed.
2)
Duiing steps 6.11151 and &1[161 the Load vs. VAR huiiits of Attachment 1 must be observed when bading the Diesel Generator. The bad requirements of between 3.96 to 4.4 MW may be reduced to 22MW ii both units are in MODE 5 andlor 6.
3)
When closing the Diesel Generator Output Breaker at the 12 oclock position, consideration Should be given to the speed of rotation of the s,qichroscope needle and the response time it takes to close the breaker.
4)
The following table provides an approximation of expected values at various DG loading plateaus. These values shall be monitored to provide alternative M-26 indications thus ensuring proper diesel generator loading. The values given are calculated approximations and may valy due to system variebles (e.g. If amps are 370 and Mvar have been adjusted to 20 Mvar then MW Should be approx. 4M.)
2 Hr rating limitations apply 5)
CST C LTC V. Tap Position indication on 0-ECB-4 should be observed prior to and during paralleling to the &9 kv Shotdown Board. Tap changer operation during this time can cause a DIG voltage change.
SAT UNSAT Examinee adjusts DIG voltage such that incoming voltage (El-82-4) and running voltage (El-82-5) are approximately equal.
Comment
1201 NRC Simulator JPM F Page 16 of 18 I
I SDS NOTE Steps 61[1J and 61j16] must be completed within 60 seconds.
STD
)7
[15J IMMEDIATELY LOAD DIG IA-A to 1.0 MW by pertorming LF thelollowing:
SAT 115.1]
PLACE [-HS..82..131, DG IA-A Speed Control Switch in RAISE and ottain ii) MW on IO-.E1-82-IUAI DG IA-A U NSAT Megawatts.
Examinee places 0-HS-13 DG IA-A Speed Control Switch to RAISE Standard:
CLOCKWISE) and attains 1.0 MWon 0-EI-82-1OA DG IA-A Megawatts in less than 60 seconds Examiner When the examinee raises EDG load direct the Booth Operator insert Note:
annunciator override AN_OV_923 f:2.
Comment STEP 26 I StartotCritical Step(s)
[141 WHEN the Snchroscope DG IA-A [0-XI-82-I1 indicates 12 oc1ock position, THEN CLOSE breaker 11912] via 11-HS-57-48A1, 1912 DG lA-A to SD GD IA-A, AND START stoçywatcti.
End of Critical SAT UNSAT Critical Step
1201 NRC Simulator JPM F Page 17 of 18 SAT U NSAT Critical Step I
O-XA-55-26A DIESEL GEN IA-A CRANKCASE PRESS HIGH ENGINE I OR 2 Terminating The task is complete when the Examinee depresses emergency STOP Cue:
stop pushbutton O-HS-82-17A, DG IA-A EMERGENCY STOP.
STEP 28 Standard:
Comment Stop Time
1201 NRC Simulator JPM F Page 18 of 18 JPM BRIEFING SHEET The examiner will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
ssume all independent and concurrent verifications are completed when called for by the procedure.
INITIAL CONDITIONS:
1.
Unit I and Unit 2 are in MODEl.
2.
lA-A DIG is INOPERABLE due to maintenance 3.
Maintenance has been completed on the IA-A D/G and the clearance has been removed.
4.
All Section 4.0 PREREQUISITE ACTIONS of 1-SI-OPS-082-007.A are complete.
5.
Section 6.1 of 1-SI-OPS-082-007.A has been completed through step 7.c.
INITIATING CUES:
1.
The SRO has directed you to complete 1-SI-OPS-082-007.A Appendix C AMBIENT MANUAL START METHOD 2.
Inform the SRO when complete.
Acknowledge to the examiner when you are ready to begin.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
SEQUOYAH NUCLEAR PLANT JOB PERFORMANCE MEASURE 1201 NRC SIM G (ROISRO)
1201 NRC Simulator JPM G Page 2 of 12 ROISRO JOB PERFORMANCE MEASURE Task:
Emergency Mode Control Room Isolation due to High Radiation Task#:
0880980101 Task Standard:
The examinee will manually place one train of Emergency Control Room Ventilation in service and isolate Normal Control Room Ventilation.
Alternate Path:
YES:
X NO:
Time Critical Task:
YES:
NO:
X KIA ReferencelRatings:
APE 061 AA1.01 (3.6/3.6)
Method of Testing:
Simulated Performance:
Actual Performance:
X Evaluation Method:
Simulator X
In-Plant Classroom Main Control Room Mock-up Performer:
Trainee Name Evaluator:
I Name I Signature DATE Performance Rating:
SAT:
UNSAT:
Validation Time:
15 minutes Total Time:
Performance Time:
Start Time:
Finish Time:
COMMENTS
1201 NRC Simulator JPM G Page 3 of 12 SPECIAL INSTRUCTIONS:
1.
Ensure Simulator Operator Checklist is complete 2.
ResettolCl6 3.
Insert the following:
IMF CHO7A, failure of Train A Control Room Isolation IMF CHO7B, failure of Train B Control Room Isolation IMF RM90125 to 10000 ramp 300 to set RM-90-125, Control Room Rad monitor, to a high rad condition.
IMF RM90126 to 10000 ramp 300 to set RM-90-126, Control Room Rad monitor, to a high rad condition.
Override AN_OV_1 255 to ON ramp 10 to set Control Room Isolation Train A alarm Override AN_OV_1 262 to ON ramp 10 to set Control Room Isolation Train B alarm 4.
An extra operator will be required to acknowledge alarms.
5.
ACKNOWLEDGE ALARMS 6.
FREEZE SIMULATOR.
7.
Save as a temporary IC, if repeat runs of JPM will be desired.
8.
PLACE SIMULATOR IN RUN when directed by the Lead Examiner 9.
After JPM is complete, delete the temporary IC, if used.
ToolslEquipmentlProcedures Needed:
0-SO-30-2 Control Room Isolation
References:
Reference Title Rev No.
O-SO-30-2 Control Room Isolation 14 1-AR-M6-C CVCS-HEAT TRACE-UHI 34 0-AR-M12-B COMMON RADIATION MONITOR 29
1201 NRC Simulator JPM G Page 4 of 12 DIRECTIONS TO TRAINEE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be
)erformed for this JPM.
I will provide initiating cues and reports on other actions when directed by you.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Ensure you indicate to me when you understand your assigned task. Assume all independent and concurrent verifications are completed when called for by the procedure. To indicate that you have completed your assigned task return the handout sheet I provided you.
HAND JPM BRIEFING SHEET TO EXAMINEE AT THIS TIME!
INITIAL CONDITIONS:
1.
Unit 1 is in MODE 1.
2.
You are the Unit 1 CR0.
INITIATING CUES:
1.
Respond to plant conditions.
1201 NRC Simulator JPM G Page 5 of 12 Start Time CONTROL ROOM CONTROL ROOM ISOLATION ISOLATION TRAIN A TRAIN B STEP 1
Correctwe
[1] ENSURE C*d Room sdation:
Actions REFER TO Section 51 of 0-50-30-2, Emergency Mode Control SAT Room soiatiot fC.41 U N SAT Standard Examinee responds to alarm using l-AR-M6C window E-5 or E-6 and refers to 0-SO-30-2 Control Room Isolation.
Examiner The examinee may place HS 31A-7A and HS 31A-38A Control Bldg Isol Note Train A and B to ACTUATE in an attempt to manually actuate a Control Bldg Isolation.
Examiner Inserted simulator malfunction disables the Control Building Isolation Note:
automatic and manual isolation signals.
Examiner Examinee may address the M12B alarms in the next JPM step, if not Note:
proceed to JPM step 3 on the next page.
Comment
1201 NRC Simulator JPM G Page 6 of 12 O-RA-90-125A O-RA-90-126A MAIN CNTL RM MAIN CNTL RM INTAKE MON INTAKE MON HIGH RAD HIGH RAD Q
ID corrective
[11 IF ContnI Room Iso4ation ia 1-XA-55-6C ndcw E-S
.TEr 2
Actions or E-6 in alarm, ThEN SAT REFER TO O-SO-30-2, Contrvl Room iso4atión.
121 REQUEST RADON to survey for acftlogical hazards.
UNSAT
[3J PERFORM O-SO-30-2, Coot,ti Room Isofation, to recover from control room isolalion, Standard Examinee responds to alarm using 0-AR-M12B window C-7 or D-5 and refers to 0-SO-30-2 Control Room Isolation.
çJ If asked acknowledge communication to Radcon.
Examiner Note:
May have been previously performed.
Comment STEP 3
Obtain a copy of 0-SO-30-2 Control Room Isolation SAT U NSAT Standard:
Examinee obtains a copy of 0-S0-30-2 Control Room Isolation i&
Provide a copy of 0-SO-30-2 Control Room Isolation Section 8.1 Cue If asked provide the following cue, O-SO-30-2 Control Room Isolation section 4 is complete.
Comment
1201 NRC Simulator JPM G Page 7 of 12 STEP 4
[1]
ACKNOWLEDGE Control Room Ventilation Isolation alarm.
Examinee acknowledges CR1 alarm.
Comment STEP 5
[2]
IF CR1 is from a valid SIS or High Radiation signal, THEN SAT NOTIFY RADCON to monitor Control Building el. 732 WOrk UNSAT areas for habitability impact.
Examinee determines that alarm is valid by observing RM-90-1 25 and Standard:
126 alarms or by verification in ICS and notifies the Radcon to take air samples and determine if the MCR must be evacuated.
cid If asked acknowledge communication to the Radcon.
Comment
[3]
ENSURE either Control Building NC AHU RUNNING and STEP 6
assodated AHU inlet OPEN:
UNSAT CONTROL BLDG RUNNING AHU INLET OPEN AICAHU Si A
D 0-FCO-31 1-20 C
B 0-FCO-31 1-23 C
Examinee verifies that B Train Control Building NC AHU is running and Standar&
0-FCO-31 123 is open by observing red light on XI-31 1-23A (Panel 1-M-
- 6) or red light above 0-HS-23A is ON and red light for indicator 0-XI-31 1-23 (Panel 1-M-1 1) is ON Comment
1201 NRC Simulator JPM G Page 8 of 12 STEP 7
[4]
1F Control Building A/C AHIJs stopped THEN SAT DISPATCH personnel to:
UNSAT 14.11 OPEN Mechanical equipment room door C-39
[4:21 OPEN MCR door C-48 or C-56.
Standard Examinee verifies Control Building A/C AHUs are running and addresses the step as not applicable.
Comment
[5]
ENSURE either Electrical Board Room Chiller RUNNING and STEP 8
assodated AHU thlet OPEN:
SAT UNSAT ELECTRICAL RUNNING AHU INLET OPEN BOARD ROOM NC 1
AHU A
O-FCO-311-27 D
B C
O-FCO-31 1-28 Examinee verifies that B Train Electrical Board Room A/C AHU is running Standard and 0-FCO-31 1-28 is open by observing red light above 0-HS-31 1-28A ELECT BD ROOM NC AHU B is ON and red light for indicator 0-Xl-31 1-28 ELECT GD RM AHU B INLET is ON.
Comment
1201 NRC Simulator JPM G Page 9 of 12 NAJE*1j 16]
ENSURE either Control Building Emergency Air Cleanup fan RUNNING and associated tan inlet OPEN:
CONTROL BLDG RUNNING FAN INLET OPEN EMERGENCY AIR CLEANUP FAN A
C O-FCO-311-9 C
Examinee verifies damper 0-FCO-31 1-9 is open by observing red light for indicator 0-XI-31 1-27 ON OR Examinee verifies damper 0-FCO-31 1-11 is open by observing red light for indicator O-Xl-31 1-28 ON Examiner Note:
The damper position indication verification is not critical Comment STEP 9
SAT UNSAT Critical Step B
C O-FCO-31 I-i I C
Standard:
1201 NRC Simulator JPM G Page 10 of 12 CONTROL BLDG EMERGENCY AIR CLEANUP FAN A
B RUNNING
.q C
C FAN IN LET 0-FCO-31 1-108 0-FCO-31 1-109 OPEN q
C a
Examinee verifies damper 0-FCO-311-108 is open by observing red light Standard:
for indicator 0-Xl-31 1-27 ON OR Examiner I
Note:
I The damper position indication verification is not critical Comment I STEP 10
[7]
ENSURE at least one Emergency Air Pressurizing Fan RUNNING and associated fan inlet OPEN:
A1 ri. rrr i iiiriwis SAT UN SAT Critical Step Examinee verifies damper 0-FCO-311-109 is open by observing red light for indicator 0-XI-31 1-28 ON STEP 11
[ (8]
E MCR and Spreading Room..
STOPPED:
j:;
c;:ii&a.
[&1]
Air Fans SAT U N SAT Critical Step Spreachng Room Supply Fan
Simulator JPM G Page 11 of 12 SAT UNSAT Critical Step 1201 NRC STEP 12
[8]
ENSURE MCR and Spreading Room Fresh Air Fans SAT STOPPED:
UNSAT 8.2J Spreading Room Exhaust Fan A Critical Step Standar&
Examinee verifies Spreading Room Exhaust Fan A is stopped by observing green lights above HS-31 1-79A ON.
Comment STEP 13 Standard:
Comment Terminating Provide the following cue, another operator will complete the STOP Cue:
remaining steps of this procedure.
Stop Time
1201 NRC Simulator JPM G Page 12 of 12 JPM BRIEFING SHEET The examiner will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
ssume all independent and concurrent verifications are completed when called for by the procedure.
INITIAL CONDITIONS:
1.
Unit 1 is in MODE 1.
2.
You are the Unit 1 CR0.
INITIATING CUES:
1.
Respond to plant conditions.
Acknowledge to the examiner when you are ready to begin.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
SEQUOYAH NUCLEAR PLANT JOB PERFORMANCE MEASURE 1201 NRC SIM H (ROISRO)
1201 NRC Simulator JPM H Page 2 of 14 ROISRO JOB PERFORMANCE MEASURE Task:
Respond to a Leak in the Component Cooling Water System.
Task#:
0000260501 Task Standard:
Examinee manually trips the Reactor and manually trips the Reactor Coolant Pumps.
Alternate Path:
YES:
X NO:
Time Critical Task:
YES:
NO:
X KIA ReferenceiRatings:
APE 026 AM.05 (3.1/3.1)
Method of Testing:
Simulated Performance:
Actual Performance:
X Evaluation Method:
Simulator X
In-Plant Classroom Main Control Room Mock-up Performer:
Trainee Name Evaluator:
I Name I Signature DATE Performance Rating:
SAT:
UNSAT:
Validation Time:
12 minutes Total Time:
Performance Time:
Start Time:
Finish Time:
COMMENTS
SPECIAL INSTRUCTIONS:
1.
Ensure Simulator Operator Checklist is complete 2.
ResettolCl6 3.
Insert the following malfunctions:
CC2O, 1-FCV-70-63 fails to open automatically.
CCO1 35, Component Cooling Line Break 4.
An extra operator will be required to acknowledge alarms.
5.
ACKNOWLEDGE ALARMS 6.
FREEZE SIMULATOR.
7.
Save as a temporary IC, if repeat runs of JPM will be desired.
6.
PLACE SIMULATOR IN RUN 9.
After JPM is complete, delete the temporary IC, if used.
ToolslEquipmentiProcedures Needed:
O-AR-M27-B-B Component Cooling AOP-M.03 Loss Of Component Cooling Water
References:
Reference O-AR-M27-B-B AOP-M.03 1201 NRC Simulator JPM H Page 3 of 14 Title Rev No.
Component Cooling 17 Loss Of Component Cooling Water 14
1201 NRC Simulator JPM H Page 4 of 14 DIRECTIONS TO TRAINEE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be erformed for this JPM.
I will provide initiating cues and reports on other actions when directed by you.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Ensure you indicate to me when you understand your assigned task. Assume all independent and concurrent verifications are completed when called for by the procedure. To indicate that you have completed your assigned task return the handout sheet I provided you.
HAND JPM BRIEFING SHEET TO EXAMINEE AT THIS TIME!
INITIAL CONDITIONS:
1.
Unit I is in MODE 1.
2.
You are the Unit I CRC INITIATING CUES:
1.
Respond to plant conditions.
1201 NRC Simulator JPM H Page 5 of 14 Start Time UNIT I CCS SURGE TK LVL LO AUTO MAKEUP INITIATED STEP 1
(1] CHECK surge tark eveI by er1ng T44J-70-63A1.
SAT UNSAT Examinee checks CCS surge tank level decreasing by observing I -LI Standard:
99A CCS SURGE TKA OUTLET LEVEL B Header and 1-LI-70-63A CCS SURGE TK A INTLET LEVEL A Header.
Examiner The examinee may address alarm window C-2 which starts on JPM step Note:
4 on the next page.
Comment STEP 2
SAT UNSAT Standarc[
Examinee places 1-HS-70-63A CCS Surge Tank A Inlet Isolation to OPEN.
Comment
1201 NRC Simulator JPM H Page 6 of 14 STEP 3
operator for local inspection to detemine protlem.
[4] VERIFY proper vae alignment in accorrice th 1-SO-70-i, Component Cooling WaferSystem Train A, and U-SO-70-1 Component Coding Water System Train B UNSAT
[51 MON[OR level in both surge tanks to termine:J lege return problems.
(6] MONITOR level rise in packet sump for possible CCS leak inside containment
[7] IF suflicient level cannot be maintained, ThEN GO TO AOP-M.03, Loss of Component Cooling Water for emergency makeup instructions. [C.1I Standard Examinee dispatches an operator to investigate the leak and transitions to AOP-M.03 Loss Of Component Cooling Water.
If asked acknowledge the direction to investigate the leak.
Comment UNIT I CCS SURGE TANK LEVEL ABNORMAL
[1]: CHECK surge tak level on O-M-278 by observing STEP 4
I1-U-70-99N51 SAT UNSAT Examinee checks CCS surge tank level decreasing by observing 1-Ll Standard:
99A CCS SURGE TK A OUTLET LEVEL B Header and 1-LI-70-63A CCS SURGE TK A INTLET LEVEL A Header.
Comment
1201 NRC Simulator JPM H Page 7 of 14 STEP 5
SAT UNSAT Standard:
Examinee addresses the step as not applicable and goes to step 3.
Comment STEP 6
[31 SAT
[a] DISPATCH operator to inves1gate probe4m M IF SUffICiflt be THEN UNSAT GO TO AOP-MJ03, Loss I Component Cooling Water.
StandardS Examinee dispatches an operator to investigate the leak and transitions to AOP-M.03 Loss Of Component Cooling Water.
If asked acknowledge the direction to investigate the leak.
Comment STEP 7
Obtain a copy of AOP-M.03 Loss Of Component Cooling Water SAT U N SAT Standard Examinee obtains a copy of AOP-M.03 Loss Of Component Cooling Water Q!L Provide copy of AOP-M.03 Loss Of Component Cooling Water Comment
U NSAT Critical Step STEP 8
1.
DIAGNOSE the failure:
1201 NRC Simulator JPM H Page 8 of 14 SAT GO TO IF..
SECTION PAGE Tram A Surge Tank level lowering below 61%
[1(2)-Ll-70-63A]
Tram A CCS Headers high or low 110w RxBldgHeacler 23 16 Misc Equipment Header SFP HX Supply Header Tram A ESF Header Train A temperatures rising in conjunction with abnormal 110w Examinee observes Train A Surge Tank level lowering below 61% on 1-Standard:
Ll-70-63A CCS SURGE TK A INTLET LEVEL A Header and selects section 2.3 Comment CAUTION If Train A CCS flow is lost and CANNOT be restored promptly OR if RCP motor thrust bearing temp alarm (M-5B, E4) is received, then RCPs must be stopped in Step I to prevent damage.
If any Containment Spray Pump is running with NO CCS cooling, spray pump may experience bearing failure after 10 minutes.
NOTE If reactor must be tripped, the CR0 or an extra US shouki be assigned to continue with this ASP STEP 9
I MONITOR the 1olIowing:
SAT a
REACTOR COO1..ANT PUMPS MOTOR THRUST BEARING TEMP UNSAT HIGH annunciator DARK. [M5B, E-31 CCS 110w established to Rx Bldg Supply Header. [FI-70-142, OM-27B]
Examinee monitors REACTOR COOLANT PUMPS MOTOR THRUST BEARING TEMP HIGH annunciator DARK. [M-5B, E-3]
Standard:
AND CCS flow established to Rx Bldg Supply Header by observing 1-FI 142, Rx BLDG SUPPLY HDR FLOW on panel 0-M-27B Comment
1201 NRC Simulator JPM H Page 9 of 14 STEP 10 2.
DISPATCH operators with radios to Aux SAT Bldg to locate failure and perlorm valve manipulations.
UNSAT Standard:
Examinee dispatches operators with radios to Auxiliary Building.
Cue If asked acknowledge the direction to locate failure and perform valve manipulations.
Comment STEP 11 DISPATCH an operator with radio to SAT pertorm Appendix A, Operation o App. R Valves Required by Section 23.
U NSAT Standard Exarninee dispatches operators with radios to perform Appendix A, Operation of App. R Valves Required by Section 2.3.
If asked acknowledge the direction to perform Appendix A.
Comment
NOTE When Train A CCS is out of service, the affected units Train A CCPs, SI Pumps, and RHR Pumps are INOPERABLE for ECCS purposes due to not being able to fulilli their design function for sump recirculation (due to loss of CCS to RI-fR HX) if necessary, the affected CCP5, Si Pumps. and RHR Pumps can be operated without CCS cooling water to mechanical seal HXs. [CA]
STEP 12 EVALUATE Tech Specs and EPIP-i SAT USING Appendix H U NSAT Standard:
Examinee addresses the procedure step If asked acknowledge the direction to evaluate Tech Specs and EPIP-1.
Comment STEP 13 5.
CHECK ERcWfls NORMAL SAT for present plant conditions:
1-Fl-67-61, IA Supply Header UNSAT 1-F1-6T-62, lB Supply Header 2-FI-67-61, 2A Supply Header 2-H.-67-62.. 26 Supply Header Examinee checks ERCW flows normal by observing the following indicators:
1-Fl-67-61, 1A Supply Header 1-FI-67-62, lB Supply Header 2-Fl-67-61, 2A Supply Header 2-Fl-67-62, 2B Supply Header 1201 NRC Simulator JPM H Page 10 of 14 Standard:
Comment
1201 NRC Simulator JPM H Page 11 ofl4 NOTE In the event of a W train line break, the surge tank baffle prevents the S train from dratning to less than 57% indicated level.
Appendix G lists expected responses to vaiious CCS surge tank leve1s STEP 14 ALTERNATE PATH SAT MONITOR Train A CCS surge tank level UNSAT between 65% and 85%:
a i(2)-LI-7r3-63A, Unit 1(2) A CCS Surge Tank Level.
Standar&
Examinee observes 1-Ll-70-63A CCS SURGE TKA INTLET LEVEL Header A, less than 65% and transitions to the RNO step Comment
[
STEP 15 ALTERNATE PATH SAT IF CCS surge tank level is less than 64%,
AT THEN UNS ENSURE surge tank auto makeup starts.
Examinee observes CCS surge tank level is less than 64% and Standard:
manually places 1-HS-70-83A CCS Surge Tank A Inlet Isolation to OPEN.
Examiner Note:
May have been previously performed.
Comment
Train A CCS sage tank level greater than 20%
atleastoneTrainACcSpump running and dehvering stable flow.
1201 NRC Simulator JPM H Page 12 of 14 STEP 16 ALTERNATE PATH 7.
MONITOR Train A CCS:
SAT UNSAT Standard Examinee monitors Train A CCS surge tank level trending to or less than 20% and transitions to the RNO step.
Examiner If CCS Surge Tank level is > 20%, the examinee will continue with steps Note:
8, 9, and 10 and return to step 7 (this step) to perform the RNO actions..
Comment STEP 17 Standard:
UNSAT Critical Step Comment
STEP 18 Standard:
Comment 1201 NRC Simulator JPM H Page 13 of 14 Terminating Provide the following cue, Another operator will complete the STOP Cue:
remaining steps in this procedure.
I IF Train A CCS flow is lost, THEN PERFORM the following for affected unit: :
IF affected unit in Model or 2, THEN:
1)
TRiP reactor SAT UNSAT Critical Step STEP 19 Standard:
Comment Stop Time
1201 NRC Simulator JPM H Page 14 of 14 JPM BRIEFING SHEET The examiner will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
ssume all independent and concurrent verifications are completed when called for by the procedure.
INITIAL CONDITIONS:
1.
Unit I is in MODE 1.
2.
You are the Unit I CRC INITIATING CUES:
1.
Respond to plant conditions.
Acknowledge to the examiner when you are ready to begin.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
SEQUOYAH NUCLEAR PLANT JOB PERFORMANCE MEASURE 1201 NRC INPLANT I (ROISRO)
1201 NRC Plant JPM I Page 2 of 9 ROISRO JOB PERFORMANCE MEASURE Task:
Local Control of Charging Flow (2-FCV-62-93)
Task#:
0040390104 Task Standard:
2-FCV-62-93 placed in local manual control and charging/seal flow has been adjusted to nominal values.
Alternate Path:
YES:
NO:
X Time Critical Task:
YES:
NO:
X KIA ReferencelRatings:
APE 028 AA1.07 (3.3/3.3)
Method of Testing:
Simulated Performance:
X Actual Performance:
Evaluation Method:
Simulator In-Plant X
Classroom Main Control Room Mock-up Performer:
Trainee Name Evaluator:
/
Name I Signature DATE Performance Rating:
SAT:
UNSAT:
Validation Time:
10 minutes Total Time:
Performance Time:
Start Time:
Finish Time:
COMMENTS
1201 NRC Plant JPM I Page 3 of 9 SPECIAL INSTRUCTIONS TO EVALUATOR:
ToolslEquipmentlProcedures Needed:
2-SO-62-1, section 8.4
References:
Reference Title Rev No.
2-SO-62-1 CVCS 62 READ TO OPERATOR HAND JPM BRIEFING SHEET TO EXAMINEE AT THIS TIME!
DIRECTIONS TO EXAMINEE:
I will explain the initial conditions, and state the task to be performed. All steps shall be simulated for this JPM. WHEN ENTERING A UNIT TRIP HAZARD ZONE ENSURE YOU DO NOT TOUCH ANY SWITCHES WITHIN THAT ZONE. I will provide initiating cues and indicate any steps to be discussed.
When you complete the task successfully, the objective for this job performance measure will be satisfied. Ensure you indicate to me when you understand your assigned task. Assume all independent and concurrent verifications are completed when called for by the procedure. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
1.
Unit2isinModel 2.
Pressurizer level is on program.
3.
Normal letdown and charging are in service with 2A-A CCP running 4.
Plant conditions require local control of 2-FCV-62-93 (charging) for maintenance on the normal controller.
5.
All prerequisite actions are completed.
6.
2-HIC-62-93 charging flow controller is failing to properly control pressurizer level in automatic.
7.
Troubleshooting has revealed that the flow modifier (2-FM-62-93B) must be replaced/repaired.
INITIATING CUES:
1.
The Unit 2 RO has directed to establish local control of 2-FCV-62-93 using 2-SO-62-1, CVCS section 8.4.
2.
Adjust charging flow as necessary to as determined by the control room operator.
3.
Inform the RO when complete.
1201 NRC Plant JPM I
Page 4 of 9 Start Time STEP i
Obtain a copy of 2-SO-62-1, CVCS section 8.4.
SAT UNSAT Standard:
Examinee obtains a copy of 2-SO-62-1, CVCS section 8.4.
JLL Provide a copy of 2-SO-62-1, CVCS section 8.4.
Comment STEP 2
[1]
OBTAIN permission from the Unit 2 US/SRO to locally SAT control 2-FCV-62-93.
UNSAT Standard:
Examinee obtains permission from Unit 2 SRO to locally control 2-FCV-Cue If asked provide the following cue, The Unit 2 RO has given you permission to locally control 2-FCV-62-93.
Examiner note:
Permission was implied during the initiating cue Cornment
1201 NRC Plant JPM I
Page 5 of 9 STEP
[2]
ESTABLISH communication between the local operator at SAT panel 2-L-1 12A and the Unit operator.
UNSAT Standar&
Examinee simulates establishing radio communications between UO and local operator.
Cue If asked acknowledge establishing communications with the Control Room Comment STEP 4
[3]
ENSURE that a CCP is in service and that 12-FCV-62-981 SAT and 12-FCV-62-991 are OPEN.
U NSAT Examinee simulates contacting the Control Room and determines Standard:
CCP is in service and that [2-FCV-62-98} and [2-FCV-62-99] are OPEN.
Cue If asked provide the following cue, A charging pump is in service and [2-FCV-62-98] and [2-FCV-62-99] are OPEN.
Comment
1201 NRC Plant JPM I Page 6 of 9 NOTE Charging flow abnormal Annunciator may actuate during transfer.
Standard:
U NSAT Critical step 1S
STEP 5
[4]
MATCH the setpoint (red pen) and the actual reading SAT (black pen) using 12-HIC-62-93B1 FLOW 1eSel When the examinee locates 2-HIC-62-93B CHARGING HEADER Cue:
FLOW CONT. provide the following cue, The black indicator is 34%
and the red indicator is 0%.
After the examinee simulates rotating 2-HIC-62-93B CHARGING Cue:
HEADER FLOW CONT. clockwise provide the following cue, The black indicator is 34% and the red indicator is 34%.
Examiner Turning knob clockwise will raise setpoint. (Direction to turn during note JPM depends on as found position of red pen in relation to black pen)
Comment STEP 6
Standard:
g flow contrJANUAL.i Critical step SAT U NSAT CueS When the examinee simulates rotating 2-HIC-62-93B provide the following cue, 2-HIC-62-93B is in MANUAL.
Comment
1201 NRC Plant JPM I
Page 7 of 9 UNSAT Critical step STEP 7
[6]
VERIFY [2XI-62-931 on panel 2-M-5 is illuminated.
SAT UNSAT Standard Examinee simulates contacting the Control Room and determines 2-XI-62-93 on panel 2-M-5 is illuminated.
Cue If asked provide the following cue, 2-Xl-62-93 on panel 2-M-5 is illuminated.
Comment NOTE Charging header flow can be monitored on 2-Fl-62-93B on panel 2-Li 12A.
STEP 8
SAT Standard:
Cue When asked provide the following cue, The Unit 2 RO reports charging flow is 80 gpm and directs you to raise flow to 87 gpm.
Cue After the flow adjustment provide the following cue, Another operator will complete the remaining steps of this procedure.
Examiner Turning knob for 2-HIC-62-93B CHARGING HEADER FLOW CONT.
note:
clockwise will raise flow, counterclockwise will reduce flow.
Examiner Examinee may observe 2-FI-62-93B CHARGING HEADER FLOW note:
while monitoring flow.
Comment
1201 NRC Plant JPM I
Page 8 of 9 Terminating The task is complete when the Examinee returns the JPM briefing STOP sheet to the examiner Stop Time
1201 NRC Plant JPM I
Page 9 of 9 JPM BRIEFING SHEET DIRECTIONS TO EXAMINEE:
All steps shall be simulated for this JPM. WHEN ENTERING A UNIT TRIP HAZARD ZONE ENSURE YOU DO NOT TOUCH ANY SWITCHES WITHIN THAT ZONE. You will be provided initiating cues and indicate any steps to be discussed. When you complete the task successfully, the objective for this job performance measure will be satisfied. Ensure you indicate to me when you understand your assigned task. Assume all independent and concurrent verifications are completed when called for by the procedure. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
1.
Unit2isinModel 2.
Pressurizer level is on program.
3.
Normal letdown and charging are in service with 2A-A CCP running 4.
Plant conditions require local control of 2-FCV-62-93 (charging) for maintenance on the normal controller.
5.
All prerequisite actions are completed.
6.
2-HIC-62-93 charging flow controller is failing to properly control pressurizer level in automatic.
7.
Troubleshooting has revealed that the flow modifier (2-FM-62-93B) must be replaced/repaired.
INITIATING CUES:
1.
The Unit 2 RD has directed to establish local control of 2-FCV-62-93 using 2-SO-62-1, CVCS section 8.4.
2.
Adjust charging flow as necessary to as determined by the control room operator.
3.
Inform the RD when complete.
Acknowledge to the examiner when you are ready to begin.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
SEQUOYAH NUCLEAR PLANT JOB PERFORMANCE MEASURE 1201 NRC INPLANT J (ROISRO)
1201 NRC Plant JPM J Page 2 of 8 ROISRO JOB PERFORMANCE MEASURE Task:
Local Manual Control of a SIG PORV Task#:
0000010504 Task Standard:
The Examinee establishes local manual control of Unit 1 SIG #1 PORV by use of the local manual handwheel.
Alternate Path:
YES:
X NO:
Time Critical Task:
YES:
NO:
X KIA Reference/Ratings:
EPE 038 EA1.16 (4.4/4.3)
Method of Testing:
Simulated Performance:
X Actual Performance:
Evaluation Method:
Simulator In-Plant X
Classroom Main Control Room Mock-up Performer:
Trainee Name Evaluator:
I Name! Signature DATE Performance Rating:
SAT:
UNSAT:
Validation Time:
10 minutes Total Time:
Performance Time:
Start Time:
Finish Time:
COMMENTS
SPECIAL INSTRUCTIONS TO EVALUATOR:
1201 NRC Plant JPM J Page 3 of 8 ToolslEq uipmentlProcedures Needed:
EA-1 -2 Local Control of SIG PORVS
References:
Reference Title Rev No.
EA-1 -2 Local Control of SIG PORVS 4
READ TO OPERATOR HAND JPM BRIEFING SHEET TO EXAMINEE AT THIS TIME!
DIRECTIONS TO EXAMINEE:
I will explain the initial conditions, and state the task to be performed. All steps shall be simulated for this JPM. WHEN ENTERING A UNIT TRIP HAZARD ZONE ENSURE YOU DO NOT TOUCH ANY SWITCHES WITHIN THAT ZONE.
I will provide initiating cues and indicate any steps to be discussed.
When you complete the task successfully, the objective for this job performance measure will be satisfied. Ensure you indicate to me when you understand your assigned task. Assume all independent and concurrent verifications are completed when called for by the procedure. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
1.
Uniti isinMODE3 2.
E-3, Steam Generator Tube Rupture is in progress.
INITIATING CUES:
1.
The Unit 1 RD has directed you, the Unit I Control Bldg AUO to take local control and open SIG #1 atmospheric relief using EA-1-2, Local Control of S/G PORVs.
2.
Inform the RD when complete.
1201 NRC Plant JPM J Page 4 of 8 Start Time 3.0 PRECAUTIONS AND LiMITATIONS 3.1 Precautions B.
When using the atmospheric relief dog handwheel to open the PORV, turning the dog handwheel clockwise opens the atmospheric relief and turning the dog handwheel counterclockwise allows the atmospheric relief to close.
STEP I
Obtain a copy of EA-1-2, Local Control of SIG PORVs SAT U NSAT Standard:
Examinee obtains a copy of EA-1-2, Local Control of SIG PORVs c!
Provide a copy of EA-1-2, Local Control of SIG PORVs Comment STEP 2
4.1 Section Applicability SAT 1.
SELECT applicable unit:
UNSAT Uniti Unit2 Standard:
Examinee selects Unit 1 as the applicable unit.
Comment
1201 NRC Plant JPM J Page 5 of 8 STEP 3
2.
SELECT SIG(s) requiring local control of its atmospheric relief:
SAT SIG 1 UNSAT S/G2 S/G3 SIG4 Standar&
Examinee selects S/G I as the SIG requiring local control of its atmospheric relief.
Comment STEP 4
3.
IF throttling of atmospheric reHef(s) desired, SAT THEN GO TO Section 4.2.
UNSAT Standard:
Examinee transitions to section 4.2 Comment
1201 NRC Plant JPM J Page 6 of 8 4.2 Throttling Atmospheric Reliefs NOTES PCV-1-5 (SIG 1) and PCV-1-23 (SIG 3) fail closed on loss of Train A air.
PCV-1-12 (S/G 2) and PCV-1-3Q (S/G 4) fail closed on loss of Train B air.
Unit 2 Only: Cheater wrench (staged locally) may be needed to throttle 2-PCV-1-30 (SIG #4).
STEP 5
1.
ESTABLISH radio communications between UO and local operator.
SAT U NSAT Standard Examinee simulates establishing radio communications between UO and local operator.
Cue If asked acknowledge establishing communications with the Control Room Comment ALTERNATE PATH STEP 6
SAT 2.
IF control air available, UNSAT THEN PERFORM the following for selected S/G(s):
d d
Examinee determines control air is not available and proceeds to step anar.
When the examinee locates 1-HCV-1-6 controller for 1-PCV-1-5,
provide the following cue, Air pressure is 0.
If the examinee looks at air pressure coming from main header (on
pressure regulator), provide the following cue, Air pressure is 0.
Cue If examinee contacts the control room, acknowledge communication.
Comment
1201 NRC Plant JPM J Page 7 of 8 IF control air NOT available, THEN USE dog handwheel(s) to control atmospheric relief(s) as directed by UD by performing the following as necessary:
TURN dog haridwheel clockwise to open atmospheric relief.
V 4;
rrminating The task is complete when the Examinee returns the JPM briefing STOP Cue:
sheet to the examiner.
STEP 7
4LJERNAT PATH, L
3.
Standard:
SAT UNSAT Critical step
,pheric r_..
After the examinee has located the local operator for 1-PCV-1-5 provide the following cue, The Unit 2 RO has directed you to open I -PCV-I -5.
After the examinee has simulated opening 1 -PCV-1 -5 provide the foHowing cue, Time has been compressed, the Unit 2 RO has directed you to close I-PCV-I-5.
Comment STEP PATH J
3.
IF control air NOT available, THEN USE dog handwheel(s) to control atmospheric relief(s) as directed by UO by performing the following as necessary:
SAT relief.
TURN dog handwheel counterclockwise to close atmospheric UNSAT Critical step After the examinee has simulated closing 1-PCV-1-5, provide the following cue, Another operator will perform the remaining steps of this procedure.
Stop Time
1201 NRC Plant JPM J Page 8 of 8 JPM BRIEFING SHEET DIRECTIONS TO EXAMINEE:
All steps shall be simulated for this JPM. WHEN ENTERING A UNIT TRIP HAZARD ZONE ENSURE YOU DO NOT TOUCH ANY SWITCHES WITHIN THAT ZONE. You will be provided initiating cues and indicate any steps to be discussed. When you complete the task successfully, the objective for this job performance measure will be satisfied. Ensure you indicate to me when you understand your assigned task. Assume all independent and concurrent verifications are completed when called for by the procedure. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
1.
Unit 1 is in MODE 3 2.
E-3, Steam Generator Tube Rupture is in progress.
INITIATING CUES:
1.
The Unit I RO has directed you, the Unit I Control Bldg AUO to take local control and open S/G #1 atmospheric relief using EA-1-2, Local Control of S/G PORVs.
2.
Inform the RO when complete.
Acknowledge to the examiner when you are ready to begin.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
SEQUOYAH NUCLEAR PLANT JOB PERFORMANCE MEASURE 1201 NRC INPLANT K (ROISRO)
1201 NRC Plant JPM K Page 2 of 9 RO!SRO JOB PERFORMANCE MEASURE Task:
Refilling the Spent Fuel Pit (EA-78-1)
Task#:
0330330104 Task Standard:
The examinee refills the spent fuel pit during a Spent Fuel Pit Level Low level event.
Alternate Path:
YES:
NO:
X Time Critical Task:
YES:
NO:
X KIA Reference/Ratings:
033 A2.02 3.2/3.5 Method of Testing:
Simulated Performance:
X Actual Performance:
Evaluation Method:
Simulator In-Plant X
Classroom Main Control Room Mock-up Performer:
Trainee Name Evaluator:
I Name I Signature DATE Performance Rating:
SAT:
UNSAT:
Validation Time:
17 minutes Total Time:
Performance Time:
Start Time:
Finish Time:
COMMENTS
SPECIAL INSTRUCTIONS TO EVALUATOR:
ToolslEquipmentlProcedures Needed:
EA-78-1, Refilling the Spent Fuel Pit 1201 NRC Plant JPM K Page 3 of 9
References:
Reference Title Rev No.
EA-78-1 Refilling the Spent Fuel Pit 4
READ TO OPERATOR HAND JPM BRIEFING SHEET TO EXAMINEE AT THIS TIME!
DIRECTIONS TO EXAMINEE:
I will explain the initial conditions, and state the task to be performed. All steps shall be simulated for this JPM. WHEN ENTERING A UNIT TRIP HAZARD ZONE ENSURE YOU DO NOT TOUCH ANY SWITCHES WITHIN THAT ZONE.
I will provide initiating cues and indicate any steps to be discussed.
When you complete the task successfully, the objective for this job performance measure will be satisfied. Ensure you indicate to me when you understand your assigned task. Assume all independent and concurrent verifications are completed when called for by the procedure. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
1.
Unit I is in MODE I 2.
The Spent Fuel Pit level is dropping abnormally.
3.
Spent Fuel Pit level is 725 5.5.
4.
Demineralized water storage tank level is 85%.
5.
Alarm M-15-B-E3 LS-59-I8OAIB DEM WTR AND CASK DECON SYS ABN CONDITION is DARK 6.
Radiological conditions for the area have been assessed and are acceptable for personnel entry.
INITIATING CUE:
1.
The Unit 1 RO has directed you, the Unit 1 Auxiliary Bldg AUO to refill the spent fuel pit to above 726.5 from the demineralized water system using EA-78-1.
2.
Inform the RO when complete.
1201 NRC Plant JPM K Page 4 of 9 Start Time CAUTION SF! area habitability and expected radiological conditions shall be considered prior to dispatching personnel for local actions.
NOTE EDMG-2 Appendix J provides alternative guidance for makeup if personnel CANNOT safely reach the SEP area.
1.
REFER TO Appendix A for determining SEP level.
NOTE SFP refill should only be initiated when directed by MCR or TSC.
STEP i
Obtain a copy of EA-78-1, Refilling the Spent Fuel Pit SAT U NSAT Standard:
Exarninee obtains a copy of EA-78-1, Refilling the Spent Fuel Pit Provide a copy of EA-78-1, Refilling the Spent Fuel Pit Cornrnent STE P
2 SAT 2.
IF SFP is to be refilled using Demin Water, UNSAT THEN GO TO Section 4.2.
Standard:
Examinee transitions to section 4.2 Cornrnent
1201 NRC Plant JPM K Page 5 of 9 4.2 Refilling Spent Fuel Pit From Demineralized Water System CAUTION I Performing this section could reduce SFP boron concentration to below 2000 ppm.
CAUTION 2 During Dry Cask loading Iunloading, Spent Fuel Pit Boron concentration shall be maintained in accordance with the restrictions in 0-GO-17. An alternate means of borated makeup must be established prior to reducing the boron concentration to less than the limit due to Demln Water makeup.
NOTE A M-5 and Breakaway lock key will be required to unlock valves.
STEP 3
1.
VERIFY dernineralized water AVAILABLE.
SAT UNSAT Standard Examinee reviews initial conditions and determines alarm M-15-B-E3 LS-59-18OAIB is DARK or requests Control Room to get level Cue If asked provide the following cue, Demin Water Head tank Level is 85%.
Comment STEP 4
2.
ESTABLISH communications between operators, SAT if possible, prior to commencing flow.
UNSAT Standard:
Examinee establishes communications with the Control Room Cue If asked acknowledge establishing communications with the Control
w 3.
UNLOCK and OPEN demineralizer water makeup to SFP, I
[Aux Bldg. elev 714, by SFP heat exchanger]
When the examinee locates the valve provide the foUowing cue, The valve stem follower is down.
Provide the following cue the examinee simulates positioning the Cue valve, HW turned several times in the counter clockwise direction and is now snug and the valve stem follower is up.
Comment SPENT FUEL PIT LEVEL INDICATOR WATER WATER ABOVE ABOVE RACKS FUEL EL 727.5 26-7 27-8
EL 726.5 25.7 26-8
EL 725.5 24-7 25-B
EL 724.5 23-7 24-B STEP 6
Determine desired SEP level.
SAT UNSAT Examinee refers to EA-78-1, Appendix A Determining Spent Fuel Pit Standard:
Level and determines Spent Fuel Pit Level is adequate using the initiating cue.
Cue Is asked, provide the following cue, Point to 726.5 on EA-78-1, Appendix A Determining Spent Fuel Pit Level.
Examiner Location of the Spent Fuel Pit Level indicator is on the West wall of the Note:
SFP and is viewed from the east side of the SFP elevation 734.
Comment STEP 5
1201 NRC Plant JPM K Page 6 of 9 Standard:
p Critical step
iw STEP 7
4.
WHEN desired SFP level established, THEN CLOSE and LOCK 1201 NRC Plant JPM K Page 7 of 9 STEP 8
5.
VERIFY SFP boron concentration:
SAT a.
NOTIFY Chem Lab to sample SFP boron concentration.
UNSAT b.
IF SEP boron concentration less than 2000 ppm OR less than applicable limit from 0-GO-i 7 (if cask limits in effect),
THEN CONSULT Chem Lab and RAISE SFP boron concentration as required.
Standard:
Examinee simulates contacting the Chem Lab to sample the SFP.
Cue If asked acknowledge establishing communications with the Chem Lab.
Comment demineralizer water makeup to SEP tO-VLV-78-5141.
FAux BIdg, elev 714, by SFP heat exchanger]
SAT UNSAT When the examinee locates the valve provide the following cue, The valve stem follower is up.
Provide the following cue the examinee simulates positioning the valve, HW turned several times in the clockwise direction and is now snug and the valve stem follower is down.
1201 NRC Plant JPM K Page 8 of 9 UNSAT STEP 9
6.
GO TO Section 4.1, step in effect.
SAT END OF SECTION Standard:
Examinee returns JPM BRIEFING SHEET to the examiner.
Comment Terminating The task is complete when the Examinee returns JPM BRIEFING Cue:
SHEET to the examiner.
Stop Time
1201 NRC Plant JPM K Page 9 of 9 JPM BRIEFING SHEET DIRECTIONS TO EXAMINEE:
All steps shall be simulated for this JPM. WHEN ENTERING A UNIT TRIP HAZARD ZONE ENSURE YOU DO NOT TOUCH ANY SWITCHES WITHIN THAT ZONE. You will be provided initiating cues and indicate any steps to be discussed. When you complete the task successfully, the objective for this job performance measure will be satisfied. Ensure you indicate to me when you understand your assigned task. Assume all independent and concurrent verifications are completed when called for by the procedure. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
1.
Unit I is in MODE I 2.
The Spent Fuel Pit level is dropping abnormally.
3.
Spent Fuel Pit level is 725 5.5.
4.
Demineralized water storage tank level is 85%.
5.
Alarm M-15-B-E3 LS-59-18OAIB DEM WTR AND CASK DECON SYS ABN CONDITION is DARK 6.
Radiological conditions for the area have been assessed and are acceptable for personnel entry.
INITIATING CUE:
1.
The Unit 1 RO has directed you, the Unit I Auxiliary Bldg AUO to refill the spent fuel pit to above 726.5 from the demineralized water system using EA-78-1.
2.
Inform the RO when complete.
Acknowledge to the examiner when you are ready to begin.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.