UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 March 5, 2012 Mr. Christopher L. Burton Vice President Carolina Power and Light Company Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, North Carolina 27562-0165
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR SHEARON HARRIS NUCLEAR POWER PLANT (NRC INSPECTION REPORT 05000400/2011007)
Dear Mr. Burton:
On February 15, 2012, the NRC staff completed its end-of-cycle performance review of the Shearon Harris Nuclear Power Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2011, through December 31, 2011. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRCs assessment of your performance in the Security Cornerstone and its security-related inspection plan.
The NRC determined that overall, the Shearon Harris Nuclear Power Plant operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Shearon Harris Nuclear Power Plant during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspection at your facility.
The enclosed inspection plan lists the inspections scheduled through June 30, 2013. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
CP&L 2
We also plan on conducting several infrequently performed inspections which include: licensed operator requalification, and TI 2515/182, Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 404-997-4603 with any questions you may have regarding this letter.
Sincerely,
/RA/
Randall A. Musser, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket No.
50-400 License No.
Enclosure:
Harris Inspection/Activity Plan
_PKG.: ML120650430_________
X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE JGW1 JSD RAM NAME JWorosilo JDodson RMusser DATE 02/23/2012 02/24/2012 03/05/2012 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO
CP&L 3
cc w/encl:
Brian C. McCabe Manager, Nuclear Oversight Shearon Harris Nuclear Power Plant Progress Energy Electronic Mail Distribution Robert J. Duncan II Vice President Nuclear Operations Progress Energy Electronic Mail Distribution Donald L. Griffith Training Manager Shearon Harris Nuclear Power Plant Progress Energy Electronic Mail Distribution R. Keith Holbrook Manager, Support Services Shearon Harris Nuclear Power Plant Electronic Mail Distribution David H. Corlett Supervisor Licensing/Regulatory Programs Progress Energy Electronic Mail Distribution David T. Conley Senior Counsel Legal Department Progress Energy Electronic Mail Distribution Donna B. Alexander Manager, Nuclear Regulatory Affairs (interim)
Progress Energy Electronic Mail Distribution John H. O'Neill, Jr.
Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128 Joseph W. Donahue Vice President Nuclear Oversight Progress Energy Electronic Mail Distribution W. Lee Cox, III, Section Chief Radiation Protection Section N.C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution Kelvin Henderson, General Manager Nuclear Fleet Operations Progress Energy Electronic Mail Distribution Public Service Commission State of South Carolina P.O. Box 11649 Columbia, SC 29211 Chairman North Carolina Utilities Commission Electronic Mail Distribution Terrence E. Slake, Manager Nuclear Plant Security Shearon Harris Nuclear Power Plant Electronic Mail Distribution Robert P. Gruber Executive Director Public Staff - NCUC 4326 Mail Service Center Raleigh, NC 27699-4326 Chair Board of County Commissioners of Wake County P.O. Box 550 Raleigh, NC 27602 cc w/encl. (continued next page)
CP&L 4
cc w/encl. (continued)
Ernest J. Kapopoulos Jr.
Plant General Manager Carolina Power and Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution Chair Board of County Commissioners of Chatham County P.O. Box 1809 Pittsboro, NC 27312 Senior Resident Inspector U.S. Nuclear Regulatory Commission Shearon Harris Nuclear Power Plant U.S. NRC 5421 Shearon Harris Rd New Hill, NC 27562-9998
CP&L 5
Letter to Christopher L. Burton from Randall A. Musser dated March 5, 2012
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR SHEARON HARRIS NUCLEAR POWER PLANT (NRC INSPECTION REPORT 05000400/2011007)
Distribution w/encl:
C. Evans, RII EICS L. Douglas, RII EICS OE Mail RIDSNRRDIRS PUBLIC ROP Reports Institute of Nuclear Power Operations (INPO)
RidsNrrPMShearonHarris Resource