2011 Davis-Besse Nuclear Power Station Initial Examination Proposed Admin JPMs
ML12020A264
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 12/27/2011
From:
Operations Branch III
To:
Shared Package
ML11354A075 List:
References
ES-C-1
Download: ML12020A264 (46)


Text

Appendix C Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 1 Administrative JPM NA - 1 REACTOR OPERATOR SRO - I SRO - U

Appendix C Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 1 Facility: Davis-Besse Task No: 004-006-01-0100 Task

Title:

Calculate Boron Concentration for SDM of 1%k/k with 2 stuck rods K/A

Reference:

2.1.37 Job Performance Measure No: NEW Examinee:

NRC Examiner: Date:

Method of testing:

Simulated Performance ___ Actual Performance _X_

Classroom __X_ Simulator __ Plant ___

Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.

When you complete the task successfully, the objective for this job performance measure will be satisfied.

Initial Conditions:

This JPM is not dependant on any specific simulator initial conditions since the task is administrative in nature.

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Task Standard:

Determine the boron concentration needed to ensure 1% shutdown margin Required Materials:

DB-NE-06201, Reactor Operators Curve Book (ROCB), Rev 12 DB-NE-06202, Reactivity Balance Calculation, Rev 7 Calculator General

References:

Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Time Critical Task No Validation Time: 30 minutes

Appendix C Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 1 SIMULATOR INSTRUCTIONS INITIAL CONDITION:

This JPM is not dependant on any specific simulator initial conditions since the task is administrative in nature.

The plant conditions are specified in the Initial Conditions and Initiating Cues.

ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION:

If this JPM is not conducted in the simulator, the following references need to be available to the examinee:

MALFUNCTIONS/FAILURE TO INSERT:

None ACTION/CUES:

JPM STEP NUMBER CUE See body of JPM

Appendix C Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 1 EXAMINER COPY INITIAL CONDITIONS:

The plant is in Mode 3 following a reactor trip.

Two control rods failed to insert on the trip.

The START program is not available.

The following conditions exist:

Burnup: 500 EFPD Tave: 552°F The Reactor Engineer reports the following values:

Reactivity worth due to transient poisons is - 2.6 %K/K Correction factor for Boron 10 depletion is 0.96 Reactivity Anomaly is zero.

INITIATING CUES:

The Unit Supervisor directs you to determine the boron concentration needed to ensure 1%

shutdown margin is adequate in accordance with Section 14 of DB-NE-06202, Reactivity Balance Calculations, and DB-NE-06201, Reactor Operator Curve Book.

(Provide Candidate a copy of Section 14 and Attachment 10 of DB-NE-06202 and a copy of DB-NE-06201)

Appendix C Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 1 CANDIDATE COPY INITIAL CONDITIONS:

The plant is in Mode 3 following a reactor trip.

Two control rods failed to insert on the trip.

The START program is not available.

The following conditions exist:

Burnup: 500 EFPD Tave: 552°F The Reactor Engineer reports the following values:

Reactivity worth due to transient poisons is - 2.6 %K/K Correction factor for Boron 10 depletion is 0.96 Reactivity Anomaly is zero.

INITIATING CUES:

The Unit Supervisor directs you to determine the boron concentration needed to ensure 1%

shutdown margin is adequate in accordance with Section 14 of DB-NE-06202, Reactivity Balance Calculations, and DB-NE-06201, Reactor Operator Curve Book.

Appendix C Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 1 PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is assumed unless denoted in the "Comments".

START TIME: _______

1. PERFORMANCE STEP: Determine RCS Boron Concentration Shutdown Margin,.

........C........ B (ROCB SDM)

STANDARD: Determine B(ROCB SDM) from Figure 6C. Determines the value to be 1460 to 1475 ppmB and enters this value on Attachment 10.

COMMENT: Actual value is 1470 ppmB %K/K.

COMMENT: Sequence NOT required for this JPM except for last step CUE: None.

SAT UNSAT

2. PERFORMANCE STEP: Determine CF(B10)

STANDARD: Enters 0.96 value for CF(B10) value from Initial Conditions CUE: None.

SAT UNSAT

3. PERFORMANCE STEP: Determine Reactivity Worth of HFP Anomaly STANDARD: Enters 0 for anomaly value from Initial Conditions CUE: None.

SAT UNSAT

4. PERFORMANCE STEP: Determine the Differential Boron Worth (DBW).

........C........

STANDARD: Determine DBW value from Figure 5A. Determines value of - 0.00715 to

- 0.00714 %K/K.

COMMENT: Actual value is -0.007145 %K/K.

CUE: None.

SAT UNSAT

Appendix C Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 1

5. PERFORMANCE STEP: Determine Transient Poison worth, (tp), for Transient Reactivity Boron Equivalent (B(tr)

STANDARD: Enters - 2.6 %K/K for (tp) value from the Initial Conditions CUE: None.

SAT UNSAT

6. PERFORMANCE STEP: Determine Pu-239 worth, (PU-max), for Transient Reactivity

........C........ Boron Equivalent (B(tr)

STANDARD: From Figure 20B, determines a value of 0.137 to 0.139 %K/K for (PU-max)

COMMENT: Actual value is 0.138 %K/K CUE: None.

SAT UNSAT

7. PERFORMANCE STEP: Determine Transient Poison Conversion Factor for Transient

........C........ Reactivity Boron Equivalent, B(tr)

STANDARD: Determines a value of 86 from Table 1 of the ROCB CUE: None.

SAT UNSAT

8. PERFORMANCE STEP: Determine CF(B10) for Transient Reactivity Boron Eqivalent, B(tr)

STANDARD: Enters 0.96 value for CF(B10) value from Initial Conditions CUE: None.

SAT UNSAT

9. PERFORMANCE STEP: Determine Transient Reactivity Boron Equivalent, B(tr)

........C........

STANDARD: Performs calculation for B(tr) on Attachment 10. Determine value of 220.46 to 220.64 ppmB Comment: Actual value is 220.55 CUE: None.

SAT UNSAT

Appendix C Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 1

10. PERFORMANCE STEP: Determine Minimum RCS Boron Concentration for 1% SDM

........C........

STANDARD: Performs calculation on Attachment 10. Determine value of 1313 to 1330 ppmB COMMENT: Actual value is 1324 ppmB CUE: None.

SAT UNSAT TERMINATING CUES: This JPM is complete. (The evaluator will terminate.)

END TIME EVALUATOR NOTE: Multiple errors may provide a correct final answer.

Rounding off values may make the answer different from key.

Evaluator discretion required.

Appendix C Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 1 Verification of Completion Job Performance Measure No. A-1 Examinees Name:

Examiners Name:

Date Performed:

Facility Evaluator:

Number of Attempts:

Time to Complete:

Question Documentation:

Question:_____________________________________________________________

Response:_____________________________________________________________

Result: Satisfactory/Unsatisfactory Examiners signature and date: _______________________________________

Appendix C Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 1 ATTACHMENT 10: ANSWER KEY Page 1 of 1 EFPD= __500___ CF(B10)= _0.96_ Tave = _552_°F Number of known stuck rods? __2 __ Data: Date Today Time Now CAUTION If Transient Poison is to be credited, take appropriate actions to ensure the 1%k/k Shutdown Margin is not lost as Transient Poison decrease Minimum RCS Boron Concentration for 1%k/k Shutdown Margin

[( 1470 / 0.96 ) - ( 0 / -0.007145 ) - 220.55 ] x (1 + .01) = _1324 ppmB B(ROCB SDM) CF(B10) (anom) DBW B(tr) Minimum Measured B(RCS)

Where:

B(ROCB SDM) is from Figure 6 based on Tave, EFPD, and stuck rod condition (anom) is Reactivity Worth of HFP Anomaly from the Reactor Operating Guidanc (For conservatism, a value of 0 may be used in place of a negative HFP anomaly for calculations of Shutdown Margin. See Step 4.2.8.)

DBW is Differential Boron Worth from Figure 5A based on B(ROCB SDM) and EFPD B(tr) is Transient Reactivity Boron Equivalent*

[( __-2.6___ + __0.138__ ) x __86___ ] / __0.96_____ x [ -1 ] = _220.55_

(tp) (Pu-max) TPCF CF(B10) B(tr)

Where:

(tp) is Transient Poison Worth from START program at time of data (Pu-max) is Maximum Excess Pu-239 Worth from Figure 20B based on EFPD TPCF is Transient Poison Conversion Factor from Table 1 of ROCB

  • If no credit is to be taken for transient poison, enter zero for B(tr)

.01 is the Boron Concentration Measurement Uncertainty (1+.01) is the Boron Concentration Measurement Correction Factor Calculated by Date Time Checked by Date

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 2 Administrative JPM NA - 2 REACTOR OPERATOR SRO - I SRO - U 1 of 11

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 2 Facility: Davis-Besse Task No: 115-004-02-0100 Task

Title:

Control of Locked Valves During Post-Maintenance Testing K/A

Reference:

2.1.18 Job Performance Measure No: JPM 261 Examinee:

NRC Examiner: Date:

Method of testing:

Simulated Performance ___ Actual Performance _X_

Classroom ___ Simulator _X Plant ___

Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.

When you complete the task successfully, the objective for this job performance measure will be satisfied.

Initial Conditions:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Task Standard:

Perform Post Maintenance Testing and Control Valve Required Materials:

DB-PF-03272, Post Maintenance Valve Test ISTB3, Pump and Valve Basis Document, Volume III, Section C Lock Valve Log Sheet Stop Watch General

References:

Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Time Critical Task: No Validation Time: 40 minutes 2 of 11

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 2 SIMULATOR INSTRUCTIONS TASK DESCRIPTION:

Control of Locked Valves During Post-Maintenance Testing INITIAL CONDITION:

Any IC ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION:

None MALFUNCTIONS/FAILURE TO INSERT:

DH2736 Malfunction to open faster than 45.71 seconds ACTION/CUES:

3 of 11

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 2 EXAMINER COPY INITIAL CONDITIONS:

Maintenance has completed a packing adjustment on valve DH2736, DH Aux. Spray Throttle Valve, to stop a packing leak per Order 200001155.

INITIATING CUES:

The Unit Supervisor directs you to perform post maintenance valve testing of DH2736 in accordance with DB-PF-03272, Post Maintenance Valve Test beginning with Section 3.2.

DB-PF-03272, Section 3.1 is complete.

The Shift Manager has given his permission to stroke DH2736, DH Aux. Spray Throttle Valve.

An equipment operator is standing by in the Auxiliary Building.

The Locked Valve Log is in the Control Room.

The Unit Supervisor has completed the first eight columns in the Locked Valve Log.

(Provide the Candidate a copy of DB-PF-03272 and a copy of the Locked Valve Log) 4 of 11

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 2 CANDIDATE COPY INITIAL CONDITIONS:

Maintenance has completed a packing adjustment on valve DH2736, DH Aux. Spray Throttle Valve, to stop a packing leak per Order 200001155.

INITIATING CUES:

The Unit Supervisor directs you to perform post maintenance valve testing of DH2736 in accordance with DB-PF-03272, Post Maintenance Valve Test beginning with Section 3.2.

DB-PF-03272, Section 3.1 is complete.

The Shift Manager has given his permission to stroke DH2736, DH Aux. Spray Throttle Valve.

An equipment operator is standing by in the Auxiliary Building.

The Locked Valve Log is in the Control Room.

The Shift Manager has completed the first eight columns in the Locked Valve Log.

5 of 11

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 2 PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT assumed unless denoted in the "Comments".

START TIME: _______

1. PERFORMANCE STEP: Complete Section 3.2 of DB-PF-03272.

STANDARD: Check/verify Section 3.1 is complete.

CUE: None.

SAT UNSAT

2. PERFORMANCE STEP: Complete Section 3.2 of DB-PF-03272.

STANDARD: Verify an RWP is available.

CUE: (If asked) A special RWP is not required for this test.

SAT UNSAT

3. PERFORMANCE STEP: Obtain stroke times from the Pump and Valve Basis

........C........ Document and record.

STANDARD: Enter the maximum close time of 59.70 seconds; the maximum open time of 59.62 seconds; the expected close time range of 33.83 seconds to 45.77 seconds; and the expected open time range of 33.79 seconds to 45.71 seconds in Step 3.2.3 of DB-PF-03272.

CUE: None.

SAT UNSAT

4. PERFORMANCE STEP: Complete Section 3.2 of DB-PF-03272.

STANDARD: Obtain Shift Manager's permission to perform the test.

CUE: (If asked) The Shift Manager has given permission to stroke test DH 2736 and no actions need to be taken.

SAT UNSAT 6 of 11

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 2

5. PERFORMANCE STEP: Record test equipment data.

STANDARD: Record the M&TE number for the stopwatch and the calibration due date.

CUE: (If asked) A special NOP-OP-1014 lineup is NOT required.

SAT UNSAT

6. PERFORMANCE STEP: Verify the Equipment Operator is at DH 2736.

STANDARD: Communicate via Gai-Tronics or radio.

CUE: An Equipment Operator is standing by to verify local valve position.

SAT UNSAT

7. PERFORMANCE STEP: Stroke DH 2736 open and record time.

........C........

STANDARD: Depress and hold the OPEN pushbutton and stroke time using the stopwatch. Record the stroke time.

COMMENT: DH 2736 is a throttle valve, which requires the OPEN pushbutton to be depressed while the valve is stroking.

DH 2736 will stroke faster than the expected time.

CUE: None SAT UNSAT

8. PERFORMANCE STEP: Contact the Equipment Operator to check local indication.

STANDARD: Communicate via Gai-Tronics or radio.

CUE: (I/F) The Equipment Operator reports local valve position indicates DH 2736 is open.

SAT UNSAT 7 of 11

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 2

9. PERFORMANCE STEP: Complete the "Position To" column in the Locked Valve Log.

........C........

STANDARD: Enter "Open".

COMMENT: The Locked Valve Log may be updated after the stroke test is complete.

CUE: None.

SAT UNSAT

10. PERFORMANCE STEP: Complete the "Position By" column in the Locked Valve Log.

........C........

STANDARD: Enter initials.

COMMENT: The Locked Valve Log may be updated after the stroke test is complete.

CUE: None.

SAT UNSAT

11. PERFORMANCE STEP: Stroke DH 2736 closed and record time.

........C........

STANDARD: Depress and hold the CLOSED pushbutton and stroke time using the stopwatch. Record the stroke time.

CUE: None. __________

SAT UNSAT

12. PERFORMANCE STEP: Contact the equipment operator to check local indication.

STANDARD: Communicate via Gai-Tronics or radio.

CUE: (I/F) The Equipment Operator reports local valve position indicates DH 2736 is closed.

SAT UNSAT

13. PERFORMANCE STEP: Complete the "Restored By" column in the Locked Valve Log.

........C........

STANDARD: Enter initials.

COMMENT: The Locked Valve Log may be updated after the stroke test is complete.

CUE: None.

SAT UNSAT 8 of 11

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 2

14. PERFORMANCE STEP: Recognize the stroke times are not within the expected times.

STANDARD: Compare valve stroke times to the expected range of stroke times.

CUE: None.

SAT UNSAT

15. PERFORMANCE STEP: Restroke DH 2736 and record times.

........C........

STANDARD: Recognize the test requires the valve to be stroke timed a second time.

CUE: DH 2736 has been stroked open and closed a second time. The stroke times are the same as recorded in Step 4.2.2 SAT UNSAT

16. PERFORMANCE STEP: Inform the Unit Supervisor or Shift Manager the stroke times are

........C........ not within the expected range.

STANDARD: Communicate to a shift SRO the need to write a Condition Report and perform an Operability Justification.

CUE: The Shift Manager will write the Condition Report and document the Operability Justification.

SAT UNSAT

17. PERFORMANCE STEP: Complete acceptance criteria.

........C........

STANDARD: Sign off Steps 5.2 and 5.3.

CUE: None.

SAT UNSAT TERMINATING CUES: This JPM is complete. (Terminated by the evaluator)

END TIME 9 of 11

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 2 Verification of Completion Job Performance Measure No.

Examinees Name:

Examiners Name:

Date Performed:

Facility Evaluator:

Number of Attempts:

Time to Complete:

Question Documentation:

Question:_____________________________________________________________

Response:_____________________________________________________________

Result: Satisfactory/Unsatisfactory Examiners signature and date: _______________________________________

10 of 11

DB-OP-00008 YEAR________ PAGE________

LOCKED VALVE LOG SHEET CHANGE FROM NORMAL POSITION RESTORATION TO NORMAL POSITION Appendix C, Rev. 9 Shift Manager Operator Operator 2nd Oper Shift Mgr Valve/ Normal Reason For Position Elec/ Local Relief SM Time Position Positioned Restored Restoration SM Time Compnonet Position Change Pneu Lock Valve Permission & To By By IVd By Review &

Number Isol Date Date DH 2736 Closed DB-PF-03272 ATTACHMENT 1:

JCH JCH Today/

Now Job Performance Measure 11 of 11 SAMPLE LOCKED VALVE LOG SHEET Worksheet Page 1 of 1 ADMIN JPM - 2 Form ES-C-1

  • If AS 138, CC 609, or WG 19, Refer to Attachment 4 Completed Sheet Reviewed By Operations Superintendent _____________________ Date__________

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet Admin JPM 3 (RO)

Administrative JPM NA - 3 REACTOR OPERATOR 1 of 6

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet Admin JPM - 3 (RO)

Facility: Davis-Besse Task No: 119-023-03-0100 Task

Title:

Determine a safety tagout for Containment Spray Pump 1 with eSOMS unavailable K/A

Reference:

2.2.13 Job Performance Measure No: NEW Examinee:

NRC Examiner: Date:

Method of testing:

Simulated Performance ___ Actual Performance _X_

Classroom _X_ Simulator __ Plant ___

Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.

When you complete the task successfully, the objective for this job performance measure will be satisfied.

Initial Conditions:

This JPM is not dependant on any specific simulator initial conditions since the task is administrative in nature.

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Task Standard:

Prepare a safety tagout manually Required Materials:

NOBP-OP-1001, Clearance Program, Rev. 03 NOP-OP-1001-07, Manual Clearance Coversheet, filled out NOP-OP-1001-10, Clearance Preparation and Review Checklist, Rev 10 Valve Location Book Operations Schematic, OS-005 (Containment Spray System)

General

References:

Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Time Critical Task: No Validation Time: 40 minutes 1 of 6

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet Admin JPM 3 (RO)

EXAMINER COPY INITIAL CONDITIONS:

The plant is currently operating at 100%.

eSOMS is currently out of service and will not be restored for another four hours.

Containment Spray Pump #1 has a leak on the pumps seal that requires replacement.

Clearance No. is DB-060-05-XXX The Manual Clearance Coversheet has been filled out.

INITIATION CUE:

The Shift Manager directs you to determine the tagging points, tag type, placement configuration, and hang order for Containment Spray Pump #1 for seal replacement. A cover sheet has been completed. Another operator will complete restoration review.

(Hand Candidate a copy of NOBP-OP-1001, and NOP-OP-1001-07, Cover Sheet, form filled out) 2 of 6

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet Admin JPM 3 (RO)

CANDIDATE COPY INITIAL CONDITIONS:

The plant is currently operating at 100%.

eSOMS is currently out of service and will not be restored for another four hours.

Containment Spray Pump #1 has a leak on the pumps seal that requires replacement.

Clearance No. is DB-060-05-XXX The Manual Clearance Coversheet has been filled out.

INITIATION CUE:

The Shift Manager directs you to determine the tagging points, tag type, placement configuration, and hang order for Containment Spray Pump #1 for seal replacement. A cover sheet has been completed. Another operator will complete restoration review.

3 of 6

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet Admin JPM 3 (RO)

PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT required unless denoted in the "Comments".

START TIME: _______

1. PERFORMANCE STEP: :Reviews NOBP-OP-1001, Manual Clearance Generation and Cover Sheet STANDARD: Determines Section 4.0 is the correct section CUE: NONE SAT UNSAT
2. PERFORMANCE STEP: Determine Tagging Boundaries C

STANDARD Use system drawing OS-005 to determine tagging points COMMENTS Refer to Manual Clearance Tag List (NOP-OP-1001-09) key CUE: NONE SAT UNSAT

3. PERFORMANCE STEP: Determine Tag Type, Placement Configuration, Hand Order C

STANDARD: Tag electrical, high pressure, low pressure, and vents and drains COMMENTS: Refer to Manual Clearance Tag List (NOP-OP-1001-09) key CUE: NONE SAT UNSAT TERMINATING CUES: This JPM is complete (Terminated by the examiner)

END TIME 4 of 6

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet Admin JPM 3 (RO)

Verification of Completion Job Performance Measure No. A-3 Examinees Name:

Examiners Name:

Date Performed:

Facility Evaluator:

Number of Attempts:

Time to Complete:

Question Documentation:

Question:_____________________________________________________________

Response:_____________________________________________________________

Result: Satisfactory/Unsatisfactory Examiners signature and date: ______________________________________

5 of 6

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM 3 (SRO)

Facility: Davis-Besse Task No: 331-007-03-300 Task

Title:

Determine Compensatory Measures For Removing Fire Suppression For Startup Transformer 01 K/A

Reference:

KA 2.2.37 Job Performance Measure No: NEW Examinee:

NRC Examiner: Date:

Method of testing:

Simulated Performance ___ Actual Performance _X_

Classroom _X_ Simulator _ _ Plant ___

Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.

When you complete the task successfully, the objective for this job performance measure will be satisfied.

Initial Conditions:

The plant conditions are specified in the Initial Conditions and Initiating Cues Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues Task Standard:

Determine Fire Suppression Compensatory Measures Required Materials:

DB-FP-0009, Fire Protection Impairment and Fire Watch Form DB-100 FHAR 8.2.2 and Table 8.4 Drawings - OS-47A Sheet 4, and OS-47B Sheet 4 General

References:

Time Critical Task: No Validation Time: 35 minutes 1 of 7

Appendix C Job Performance Measure Form ES-C-1 Worksheet Admin JPM 3 (SRO)

EXAMINER COPY INITIAL CONDITIONS:

The plant is currently operating at 100%

Maintenance needs to replace a sprinkler head on Startup Transformer 01 Work Order number is 200XXXXXX The work will take approximately 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> FP 126 will be closed to support the maintenance No Fire Detection instrumentation is out of service INITIATION CUE:

The Shift Manager directs you to determine the Fire Protection compensatory measure required.

(Hand Candidate a copy of DB-FP-00009) 2 of 7

Appendix C Job Performance Measure Form ES-C-1 Worksheet Admin JPM 3 (SRO)

CANDIDATE COPY INITIAL CONDITIONS:

The plant is currently operating at 100%

Maintenance needs to replace a sprinkler head on Startup Transformer 01 Work Order number is 200XXXXXX The work will take approximately 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> FP 126 will be closed to support the maintenance No Fire Detection instrumentation is out of service INITIATION CUE:

The Shift Manager directs you to determine the Fire Protection compensatory measure required.

3 of 7

Appendix C Job Performance Measure Form ES-C-1 Worksheet Admin JPM 3 (SRO)

PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT required unless denoted in the "Comments".

START TIME: _______

1. PERFORMANCE STEP: Locate the correct procedure STANDARD: Identifies Section 6.0 is the correct procedure section CUE: NONE SAT UNSAT
2. PERFORMANCE STEP: Completes Sections 1 of Form DB-100 C

STANDARD Fills in Name, Date and Extension COMMENTS See Form DB 100 key Any phone extension is acceptable NOTE: Attachment 4. Fire Suppression System Impairment Decision Tree may be used CUE: (If asked) Use extension 7269 SAT UNSAT

3. PERFORMANCE STEP: Completes Section 2A of Form DB-100 C

STANDARD: Checks Fire Suppression System Sprinklers, fills in fire system id number, Work Order Number, and reason for impairment COMMENTS: See Form DB 100 key CUE: NONE SAT UNSAT 4 of 7

Appendix C Job Performance Measure Form ES-C-1 Worksheet Admin JPM 3 (SRO)

4. PERFORMANCE STEP: Determine impairment features and completes Section 2B of Form C DB-100 (page 2)

STANDARD: Using Attachment 14, determines Zone FSA-Startup 01 Trans is affected Zone is a Appendix A fire suppression system, and with FP 126 closed, the fire suppression system is inoperable COMMENTS: See Form DB 100 key CUE: NONE SAT UNSAT

5. PERFORMANCE STEP: Determines Compensatory measures and completes Section 2C of C Form DB-100 STANDARD: Reviews Attachment 4 and determines FHAR 8.2.2 and Table 8-4 applies COMMENTS: See Form DB 100 key CUE: NONE SAT UNSAT
6. PERFORMANCE STEP: Determine Compensatory measure from FHAR 8.2.2 and completes C Section 2C of Form DB-100 STANDARD: Determines there is an Operable fire detection instrument in the affected area(s) and no further actions are required COMMENTS: See Form DB 100 key CUE: NONE SAT UNSAT 5 of 7

Appendix C Job Performance Measure Form ES-C-1 Worksheet Admin JPM 3 (SRO)

7. PERFORMANCE STEP: Completes Section 3 C*

STANDARD: *Checks 8.2.2 under Suppression column Recognizes NEIL notification is not required (not Critical)

COMMENTS: See Form DB 100 key CUE: NONE SAT UNSAT TERMINATING CUES: This JPM is complete (Terminated by the examiner)

END TIME 6 of 7

Appendix C Job Performance Measure Form ES-C-1 Worksheet Admin JPM 3 (SRO)

Verification of Completion Job Performance Measure No. A-3 Examinees Name:

Examiners Name:

Date Performed:

Facility Evaluator:

Number of Attempts:

Time to Complete:

Question Documentation:

Question:_____________________________________________________________

Response:_____________________________________________________________

Result: Satisfactory/Unsatisfactory Examiners signature and date: ______________________________________

7 of 7

Sheet CLEARANCE No.

Manual Clearance Tag List NOP-OP-1001-09 Rev. 02 1 Of 1 DB-060-05-XXX st nd st nd Equipment Equipment Equipment Tag # Tag Placement Hang 1 2 Restoration Clear 1 2 Notes ID Description Location Type Configuration order Verify Verify Configuration Order Remove Remove BE 111 P56-1 Supply 1 R Racked Out 1 Breaker CS 14 P56-1 2 R Closed 2 Discharge Valve CS 2 P56-1 Suction 3 R Closed 2 Valve CS 40 P56-1 Over 4 R Closed 2 Pressure Protection Valve CS 21 P56-1Vent 5 NT Open 3 CS 6 P56-1Drain 6 NT Open 3 CS 8 P56-1Drain 7 NT Open 3 NOTE CS44 may be substituted for CS 40 NOTE Vents and Drains may be tagged

MANUAL CLEARANCE COVERSHEET NOP-OP-1001-07 Rev. 02 Manual Clearance Date Time DB -060-05 -XXX / /

Equipment ID / Asset Number :

P56-1 /

Description / Reason Replace CTMT Spray Pump 1 seal Placement Notes Align pump drains to the nearest floor drain Cautions None Completion Notes Vent the pump and associated piping prior to placing the pump in service Order Number FLOC Description 200XXXXXX P56-1 CTMT SPRAY PUMP 1 Clearance Acceptance Work Group Acceptance

/ /

Print/Sign Date Print/Sign Date Clearance Release Work Group Release

/ /

Print/Sign Date Print/Sign Date Status Name (Print / Sign) Date / Time Prepared By / /

Reviewed By / /

Approved by / /

Issued for Work by / /

Removal Authorized by / /

Clearance Closed by / /

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 4 Administrative JPM NA - 4 REACTOR OPERATOR SRO - I SRO - U 1 of 9

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 4 Facility: Davis-Besse Task No: 072-011-01-0100 Task

Title:

Check out a Radiation Detector in the RRA K/A

Reference:

2.3.5 Job Performance Measure No: JPM 149 Examinee:

NRC Examiner: Date:

Method of testing:

Simulated Performance ___ Actual Performance _X_

Classroom ___ Simulator __ Plant __X_

Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.

When you complete the task successfully, the objective for this job performance measure will be satisfied.

Initial Conditions:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Task Standard:

Check out a FLUKE 451B Required Materials:

Operator Aid for Use of FLUKE 451B FLUKE 451B Radiation Meter Radiation Sources General

References:

Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Time Critical Task No Validation Time: 10 minutes 2 of 9

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 4 EXAMINER COPY INITIAL CONDITIONS:

A large break Loss of Coolant Accident has occurred.

RE 8421 is reading 50 mRem/hr for #4 Mechanical Penetration Room general area dose rates.

The water curtain between Mechanical Penetration Room 4 and the Heater Bay has actuated inadvertently and flooding of Emergency Core Cooling System Room 2 is imminent.

INITIATING CUES:

The Shift Manager has directed you to isolate the water curtain supply from the Auxiliary Building by closing FP 266 #4 Mechanical Penetration Room 314 Water Curtain Isolation, located in the southeast corner of #4 Mechanical Penetration Room.

Radiation Protection coverage is not available and you are required to obtain a portable radiation detector prior to entering the Auxiliary Building.

The On-Site Emergency Response Facilities are not yet manned.

The Shift Manager directs you to check out a Fluke 451B radiation detector.

3 of 9

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 4 CANDIDATE COPY INITIAL CONDITIONS:

A large break Loss of Coolant Accident has occurred.

RE 8421 is reading 50 mRem/hr for #4 Mechanical Penetration Room general area dose rates.

The water curtain between Mechanical Penetration Room 4 and the Heater Bay has actuated inadvertently and flooding of Emergency Core Cooling System Room 2 is imminent.

INITIATING CUES:

The Shift Manager has directed you to isolate the water curtain supply from the Auxiliary Building by closing FP 266 #4 Mechanical Penetration Room 314 Water Curtain Isolation, located in the southeast corner of #4 Mechanical Penetration Room.

Radiation Protection coverage is not available and you are required to obtain a portable radiation detector prior to entering the Auxiliary Building.

The On-Site Emergency Response Facilities are not yet manned.

The Shift Manager directs you to check out a Fluke 451B radiation detector.

4 of 9

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 4 PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT assumed unless denoted in the "Comments".

START TIME:

1. PERFORMANCE STEP: Refer to Posted Operator Aid For Emergency Checkout of Fluke 451B STANDARD: Refer to Posted Operator Aid For Emergency Checkout of Fluke 451B.

CUE: None SAT UNSAT

2. PERFORMANCE STEP: Obtain a Portable Radiation Detector.

C STANDARD: Obtain a Fluke 451B CUE: None SAT UNSAT

3. PERFORMANCE STEP: Ensure instrument is not past its calibration due date.

STANDARD: Check the date on the Calibration sticker has not been exceeded.

CUE: None SAT UNSAT

4. PERFORMANCE STEP: Ensure the daily instrument check is current.

STANDARD: Check the daily instrument check has been completed for the current day and month.

CUE: None SAT UNSAT 5 of 9

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 4

5. PERFORMANCE STEP: Inspect meter for physical damage.

STANDARD: Physically inspect the instrument for any damage including mylar window.

CUE: None SAT UNSAT

6. PERFORMANCE STEP: Turn the meter on C

STANDARD: Press the Power button CUE: None SAT UNSAT

7. PERFORMANCE STEP: Wait for meter to complete start up sequence C

STANDARD: The meter should stabilize less than 0.5 mr/hr within 30 - 40 seconds CUE: None COMMENT:

SAT UNSAT

8. PERFORMANCE STEP: Slide open the meter beta shield.

C STANDARD: Utilize beta shield release button to enable opening of beta shield COMMENT: If not completed, meter response will be low when exposed to the source.

CUE: None SAT UNSAT

9. PERFORMANCE STEP: Remove the shield plug from source 1.1.117.

C STANDARD: Ensure slide attenuator is fully inserted and remove shield plug and set in a safe position on the cabinet.

CUE: None SAT UNSAT 6 of 9

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 4

10. PERFORMANCE STEP: Align meter over source 1.1.117 as indicated in picture.

C STANDARD: Ensure meter is aligned as indicated in picture on Operator Aid, dimples indicating meter effective center should be aligned over the source.

CUE: None SAT UNSAT

11. PERFORMANCE STEP: Slide source attenuator out to the #1 position. (line on attenuator C even with edge of cabinet upper lip).

STANDARD: Slide source attenuator out to the #1 position. (line on attenuator even with edge of cabinet upper lip)

CUE: None SAT UNSAT

12. PERFORMANCE STEP: Ensure meter responds to between 4.4 - 6.6 mR/hr. Adjust meter C and attenuator slide alignment if necessary.

STANDARD: Meter should respond to between 4.4 - 6.6 mR/hr, adjustments to meter and attenuator slide may be necessary to show proper response.

COMMENT: If examinee slides attenuator out too far, meter may respond off scale high and will take several seconds after adjustment to respond on scale.

If examinee failed to open beta shield, meter will indicate below desired scale.

CUE: None SAT UNSAT

13. PERFORMANCE STEP: Push source attenuator slide in fully.

STANDARD: Source attenuator slide should be pushed into the cabinet as far as it will go.

CUE: None SAT UNSAT

14. PERFORMANCE STEP: Remove the meter.

STANDARD: Remove the meter.

COMMENT: Examinee should be careful with meter at this point as beta window is exposed.

CUE: None SAT UNSAT 7 of 9

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 4

15. PERFORMANCE STEP: Close the meter beta shield.

C STANDARD: Close the meter beta shield.

CUE: None SAT UNSAT

16. PERFORMANCE STEP: Place the shield plug over source 1.1.117.

C STANDARD: Place the shield plug over source 1.1.117.

CUE: None SAT UNSAT

17. PERFORMANCE STEP: Adjust scale as necessary based on radiation fields encountered.

Consideration should also be given to using audible feature of meter.

STANDARD: Examinee should select a low scale based on current radiation field and may choose to turn the audible response on.

CUE: None SAT UNSAT TERMINATING CUES This JPM is complete. (Terminated by the evaluator)

END TIME 8 of 9

Appendix C, Rev. 9 Job Performance Measure Form ES-C-1 Worksheet ADMIN JPM - 4 Verification of Completion Job Performance Measure No. A-4 Examinees Name:

Examiners Name:

Date Performed:

Facility Evaluator:

Number of Attempts:

Time to Complete:

Question Documentation:

Question:_____________________________________________________________

Response:_____________________________________________________________

Result: Satisfactory/Unsatisfactory Examiners signature and date: _______________________________________