MONTHYEARML11363A0742011-12-16016 December 2011 10 CFR 50.55a Request ISI-05: Proposed Alternative Bottom Mounted Instrument Examinations Project stage: Request ML1201104002012-01-11011 January 2012 Acceptance Review for Ginna TAC No. ME7731 Project stage: Acceptance Review ML12179A3222012-06-29029 June 2012 Relief Request for Authorization of a Proposed Alternative for Certain Requirements of Inservice Inspection Program for Examination of Bottom Mounted Instrumentation Nozzles Project stage: Other 2012-01-11
[Table View] |
Similar Documents at Ginna |
---|
Category:E-Mail
MONTHYEARML23311A1692023-11-0707 November 2023 NRR E-mail Capture - Constellation - Fleet Request - Acceptance of Proposed Alternative for Examinations of Exam Categories B-B, B-D, and C-A SG Pressure Retaining Welds and Full Penetration Welded Nozzles (L-2023-LLR-0055 and L-2023-LLR-00 ML23312A1302023-11-0707 November 2023 Final Rci/Rai - Constellation R. E. Ginna Nuclear Power Plant - Exemption from Security Rule (EPID L-2023-LLE-0029) (Email) ML23311A1682023-11-0707 November 2023 NRR E-mail Capture - Constellation - Fleet Request - Acceptance of Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections (L-2023-LLR-0053 and L-2023-LLR-005 ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI ML22325A0052022-11-18018 November 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-273-A, Revision 2 ML22339A0032022-09-28028 September 2022 R. E. Ginna Nuclear Power Plant - Ginna: Acceptance Review: to Revise Technical Specifications (TS) TS 5.6.5, Core Operating Limits Report ML22269A4522022-09-22022 September 2022 R. E. Ginna Nuclear Power Plant - Acceptance Review: to Revise Technical Specifications (TS) TS 5.6.5, Core Operating Limits Report (COLR) ML22255A0132022-09-0909 September 2022 NRR E-mail Capture - NRC Acceptance Review of Braidwood, Byron, Calvert Cliffs, Ginna - License Amendment Request to Adopt TSTF-577 ML22200A0782022-07-19019 July 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request to Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22138A1672022-05-16016 May 2022 R. E. Ginna Nuclear Power Plant - Acceptance Review TS to Revise Technical Specifications (TS) for the Spent Fuel Pool Charcoal System and Two (2) TS Administrative Changes (EPID-L-2022-LLA-0057) ML22129A0132022-05-0606 May 2022 NRR E-mail Capture - Draft RAIs for Requests for Alternatives I4R-17, I4R-23, ISI-05-018, I6R-10 ML22271A0772022-05-0606 May 2022 NRR E-mail Capture - Final RAIs 9.1.2021 Constellation Relief Request ML22116A0242022-04-25025 April 2022 NRR E-mail Capture - NRC Acceptance Review of Braidwood, Byron, and Ginna Request to Adopt TSTF-246 ML22088A1562022-03-0202 March 2022 NRR E-mail Capture - Byron, Braidwood, Calvert Cliffs, and Ginna - Non-acceptance of Application to Revise Technical Specifications 5.6.5.b, the Core Operating Limits Report (COLR) ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML21308A5592021-11-0404 November 2021 NRR E-mail Capture - NRC Request for Additional Information for Ginna Biennial EP Exercise Exemption Request ML21301A0672021-10-28028 October 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-541 ML21293A1332021-10-19019 October 2021 R. E. Ginna Nuclear Power Plant - Acceptance of Request for Exemption from the Biennial Emergency Preparedness Exercise Requirements in 10 CFR 50, Appendix E, Section IV.F.2.C ML21293A2342021-10-19019 October 2021 R. E. Ginna Nuclear Power Plant - Acceptance of Request for Exemption from the Biennial Emergency Preparedness Exercise Requirements in 10 CFR 50, Appendix E, Section IV.F.2.C ML21279A1122021-10-0606 October 2021 R. E. Ginna Nuclear Power Plant - Request for Exemption from the Biennial Emergency Preparedness Exercise Requirements in 10 CFR 50, Appendix E, Section IV.F.2.c ML21273A1092021-09-30030 September 2021 R. E. Ginna Nuclear Power Plant - Acceptance Review - Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections (EPID L-2021-LLR-0074 ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21215A3502021-08-0303 August 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-554 ML21189A1602021-07-0808 July 2021 NRR E-mail Capture - Request for Additional Information - Braidwood, Byron, and Ginna - Amendment to Address the Issues in Westinghouse NSALs ML21172A2702021-06-22022 June 2021 E-Mail Acceptance of Application - Risk Informed Completion Times in Accordance with TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, ML21172A2692021-06-22022 June 2021 E Mail Acceptance of Application to Adopt 10 CFR 50.69, _Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors (Epid_ L-2021-LLA-0092) ML21154A0132021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0142021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0112021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21123A2442021-05-0303 May 2021 NRR E-mail Capture - NRC Acceptance Review of Braidwood/Byron/Ginna - Application to Address the Issues Identified in Westinghouse Documents NSAL-09-5 and NSAL-15-1 (L-2021-LLA-0066) ML21117A0442021-04-26026 April 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21084A2532021-03-24024 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Transfer Application ML21076A5152021-03-17017 March 2021 R. E. Ginna Nuclear Power Plant - RAI Steam Generator LAR to Revise Technical Specifications for Steam Generator Tube Inspection Frequency (EPID L-2020-LLA-0207) (e-mail) ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21033A8552021-02-0202 February 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request to Expand the Use ASME Codes Cases N-878 and N-880 ML21029A3302021-01-29029 January 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative Request to Use ASME Code Case N-885 ML20357A2232020-12-17017 December 2020 Update on Ginna POV - 3504A and 4562 (Email Request for Inspection Information) ML20350B5582020-12-14014 December 2020 NRR E-mail Capture - Exelon Generation Company, LLC -Alternative Request for Documentation of Replacement of Pressure Retaining Bolting ML20335A5692020-11-30030 November 2020 R. E. Ginna Nuclear Power Plant - Acceptance Review: Alternative to ASME Code, Section XI ML20325A1002020-11-20020 November 2020 Acceptance Review: Force-on-Force Temporary Exemption Request ML20294A4942020-10-20020 October 2020 R. E. Ginna Nuclear Power Plant - Acceptance Review: to Revise Technical Specifications for Steam Generator Tube Inspection Frequency ML20276A1032020-10-0202 October 2020 R. E. Ginna Nuclear Power Plant - Acceptance Review - Exemptions from 10 CFR 2.109(b), Effect of Timely Renewal Application ML20266G3032020-09-22022 September 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Request to Use Paragraph IWA-5120 of the 2017 Edition of the ASME B&PV Code, Section XI ML20218A6422020-08-0505 August 2020 R. E. Ginna Nuclear Power Plant - Request for Additional Information (RAI) for LAR to Implement WCAP, TSTF-411, and TSTF-418 ML20191A0182020-07-0101 July 2020 NRR E-mail Capture - Exelon Fleet RR for SPI for Appendix J Valves ML20153A7042020-06-0101 June 2020 NRR E-mail Capture - Preliminary RAI for Fleet Request to Use Alternative OMN-26 ML20149K4302020-05-22022 May 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Request for an Alternative to Use ASME Code Case N-885 ML20106F2482020-04-15015 April 2020 Acceptance Review: R. E. Ginna Nuclear Power Plant to Implement WCAP, TSTF-411, and TSTF-418 2023-11-07
[Table view] |
Text
From: Pickett, Douglas Sent: Wednesday, January 11, 2012 3:28 PM To: 'Harding Jr, Thomas' Cc: Widrevitz, Dan; Lingam, Siva; Boyle, Patrick; Salgado, Nancy; Gonzalez, Hipolito
Subject:
Acceptance Review for Ginna TAC No. ME7731 Mr. Harding:
By letter dated December 16, 2011 (TAC No. ME7731), R.E. Ginna Nuclear Power Plant, LLC submitted relief request ISI-05 for the R.E. Ginna Nuclear Power Plant. The relief request proposes an alternative to the requirements of 10 CFR 50.55a with respect to examinations of the bottom mounted reactor vessel instrument penetrations.
The purpose of this e-mail is to provide the results of the Nuclear Regulatory Commission (NRC) staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it provides technical information in sufficient detail to enable the staff to complete its detailed technical review and make an independent assessment regarding its acceptability in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
Please contact me if you have any questions. A copy of this email will be made publicly available in ADAMS.
Douglas V. Pickett, Senior Project Manager Calvert Cliffs, R.E. Ginna U.S. Nuclear Regulatory Commission 301-415-1364 Email: douglas.pickett@nrc.gov