'eDF Energy" P.O. Box 63 Lycoming, NY 13093 NINE MILE POINT NUCLEAR STATION U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 November 14, 2011 ATTENTION:

SUBJECT:

Document Control Desk Nine Mile Point Nuclear Station Unit Nos. 1 and 2; Docket Nos. 50-220 and 50-410 2011 Summary of Regulatory Commitment Changes There are no regulatory commitment changes requiring NRC notification in accordance with the guidance contained in NEI 99-04, "Guidelines for Managing NRC Commitment Changes," Revision 0, for the period of October 1, 2010 to September 30, 2011.

Should you have any questions regarding the information in this submittal, please contact me at (315) 349-5219.

Very truly yours, John J Dosa Director Licensing JJD/GNS cc:

NRC Regional Administrator, Region I NRC Resident Inspector NRC Project Manager AcGO