1 WBN2Public Resource From:
Boyd, Desiree L [dlboyd@tva.gov]
Sent:
Thursday, September 01, 2011 2:27 PM To:
Poole, Justin; Milano, Patrick; Campbell, Stephen; Epperson, Dan Cc:
Arent, Gordon; Smith, James D; Bryan, Robert H Jr; Smith, James D; Crouch, William D
Subject:
NRC PM Open Items List 9-6-11.docx Attachments:
NRC PM Open Items List 9-6-11.docx For next phone call, Tuesday September 6th.
Thank You,
~*~*~*~*~*~*~*~*~*~*~*~
Désireé L. Boyd WBN 2 Licensing Support Sun Technical Services dlboyd@tva.gov 423-365-8764
Hearing Identifier:
Watts_Bar_2_Operating_LA_Public Email Number:
511 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF2299492A)
Subject:
NRC PM Open Items List 9-6-11.docx Sent Date:
9/1/2011 2:26:30 PM Received Date:
9/1/2011 2:26:32 PM From:
Boyd, Desiree L Created By:
dlboyd@tva.gov Recipients:
"Arent, Gordon" <garent@tva.gov>
Tracking Status: None "Smith, James D" <jdsmith@tva.gov>
Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov>
Tracking Status: None "Smith, James D" <smith1jd@westinghouse.com>
Tracking Status: None "Crouch, William D" <wdcrouch@tva.gov>
Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>
Tracking Status: None "Milano, Patrick" <Patrick.Milano@nrc.gov>
Tracking Status: None "Campbell, Stephen" <Stephen.Campbell@nrc.gov>
Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov>
Tracking Status: None Post Office:
TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 289 9/1/2011 2:26:32 PM NRC PM Open Items List 9-6-11.docx 30416 Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received:
Page 1 of 4 NRC PM Open Items List 9/6/11 (423) 751-7777 ID 4233652004#
No.
Description Status Additional Comments Resp Org/Person
- 1.
Cyber Security Plan/Controls and Implementation NRC TI issued TBD NRC Table Top/Pilot Oct 2011 Procedures complete 9/30/11 Pre-inspection TBD Inspection Dec 2011 NRC Inspection in 2011 To be discussed at the next ACRS meeting (October 5th - closed portion).
Heinrich/Snyder (Bryan)
Page 2 of 4 No.
Description Status Additional Comments Resp Org/Person
- 2.
Instrumentation RAI List (Knuettel)
- 1. Item 3 for GA-ESI RM-1000 RAD Monitors.
- 2. GA proprietary, non-proprietary and affidavits for withholding submittals
(~12 documents.)
- 3. NRC comments on procedures to GA-ESI
- 4. RM1000 EMI/RFI questions
- 1. 9/1/11
- 2. 9/9/11
- 3. 9/16/11
- Item 1 GA/ESI is revising their CGI program but needs time to be able to provide objective evidence of the program changes. We will order parts to facilitate GA developing objective evidence that their program is in compliance with NRC regulations.
Item 2 - 3 additional document requests from NRC Civil via email on 7/6/11. PROP versions from the original request are ready for GA to send to TVA Item 3 revise GA-ESI procedures for CGI dedication Item 4 deals with EMI/RFI questions from NRC.
The referenced document from GA where for earlier vintage RM1000. GA to determine response schedule.
Eng/Hilmes (Smith)
- 3.
Complete Implementation (Hemmer)
Pump Relocation 3/20/12 Bldg Plan 9/9/11 Inspection -
April 2012 Phase I commitments 10/1/11 Additional clarification to Phase I actions will be needed. Fleet wide issue.
Substantial building to complete Feb and equipment in March Hemmer (Smith)
- 4.
Document Control Issues for two letters 9/1/11A TVA/Bechtel to provide non-proprietary version of documents that can be released to the public (10/5, 10/21, & 10/29). TVA to provide revised letter that says non-prop once prop documents removed Licensing/Boyd
Page 3 of 4 No.
Description Status Additional Comments Resp Org/Person
- 5.
Chapter 15.5 RAIs 9/9/11 Includes FHA calc. X/Q discussion for each accident, corrections to previously submitted dose calcs, and a complete 15.5 markup. Potential meeting following submittal.
Wastrack (Bryan)
- 6.
Chapter 11 - X/Q TBD Comments resolved Bryan
- 7.
TMI action items 9/1/11A TVA has verified all applicable TMI items are tracked in our issues tracking database.
Licensing (Gordon)
- 8.
Fire Protection Report Questions regarding OMA Week of 10/24
- tentative Audit ENG/Hilmes (Crouch)
- 9.
Tech Spec Revisions from latest T/S markup and NRC Review comments Sept, 2011 Aug, 2011 Aug, 2011 CSST A & B - discretionary I-131 DEI Diesel Generator Frequency Licensing/Elton (Bryan)
- 10.
ASME III to XI transition TBD NRC response to relief request submitted 9/1/11.
Eng/Helms (Crouch)
- 11.
ACRS Topics 10/5/11 Cyber Security, process for documentation update,
- 12.
SSER 22/23 Open Items Response 9/16/11 9/16 is the target date for the next SSER update. The expanded HH list and its status is covered periodically.
- 13.
Transient Analysis issues Boron dilution RAI response 9/16/11 Question on RG revision and modes 3, 4, & 5. TVA to provide write up explaining NRC acceptance (CLB) of unit1 for modes 3, 4, & 5.
ENG/Koontz WEC/Morgan
- 14.
FSAR A106 9/16/11 Target date Lic/Stockton
- 15.
Develop list of planned License Conditions, Exemptions and Relief Requests (Crouch)
- 1. 9/1/11
- 2. TBD
- 1. Review Unit 1 SER for exemptions. Sand baskets, cyber security, physical security, PAD 4.0
- 2. NRR to review current exemptions NRR/TVA (Bryan)
- 16.
Verify Tech Spec Setpoints match calcs TS certification 9/1/11 TBD 2 SSDs remaining to be issued.
Eng/Hilmes (Bryan)
- 17.
Issue two Unit Offsite Dose Calculation Manual (Beach) Review TS Chapter 5 programs also 3/1/12 Determine actual need date Chemistry/
Woods (Bryan)
- 18.
Issue Unit 2 Completion Letter (Crouch) 8/1/12 Licensing
Page 4 of 4 No.
Description Status Additional Comments Resp Org/Person
- 19.
Submit final as-constructed FSAR figures 7/1/12 Licensing/
Stockton
- 0.
Discretionary Actions
- 1.
Letter to terminate Part 30/40 License after receipt of Part 50 License 4/1/12 Licensing (Crouch)
- 2.
Combined U1/U2 FSAR (Stockton) 3/1/13 Licensing
- 3.
Status of GSI 199 Eastern Seismicity (Crouch)
Fall 2011 No action pending upcoming Generic Letter Related information on GSI 194 may need input TVA/NRR
- 4.
Letter to notify NRC when Vital Area Boundary returned to original location 11/1/11 Security Plan Update - Boundary to be restored by 9/30/11 Lic/Crouch
- 5.
IEB 88-02 SG Tube Cracking TBD Tubes are assumed locked in the WEC analysis.
Waiting for NRC concurrence.
Corp SG/
Webber ISI/Tinley