ML11257A158
| ML11257A158 | |
| Person / Time | |
|---|---|
| Site: | Watts Bar |
| Issue date: | 09/09/2011 |
| From: | - No Known Affiliation |
| To: | Division of Operating Reactor Licensing |
| References | |
| Download: ML11257A158 (5) | |
Text
1 WBN2Public Resource From:
Boyd, Desiree L [dlboyd@tva.gov]
Sent:
Friday, September 09, 2011 10:35 AM To:
Poole, Justin; Milano, Patrick; Campbell, Stephen; Epperson, Dan Cc:
Arent, Gordon; Smith, James D; Bryan, Robert H Jr; Smith, James D; Crouch, William D
Subject:
NRC PM Open Items List 9-12-11.docx Attachments:
NRC PM Open Items List 9-12-11.docx For next phone call.
Thank You,
~*~*~*~*~*~*~*~*~*~*~*~
Désireé L. Boyd WBN 2 Licensing Support Sun Technical Services dlboyd@tva.gov 423-365-8764
Hearing Identifier:
Watts_Bar_2_Operating_LA_Public Email Number:
493 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF22D164B6)
Subject:
NRC PM Open Items List 9-12-11.docx Sent Date:
9/9/2011 10:35:22 AM Received Date:
9/9/2011 10:35:26 AM From:
Boyd, Desiree L Created By:
dlboyd@tva.gov Recipients:
"Arent, Gordon" <garent@tva.gov>
Tracking Status: None "Smith, James D" <jdsmith@tva.gov>
Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov>
Tracking Status: None "Smith, James D" <smith1jd@westinghouse.com>
Tracking Status: None "Crouch, William D" <wdcrouch@tva.gov>
Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>
Tracking Status: None "Milano, Patrick" <Patrick.Milano@nrc.gov>
Tracking Status: None "Campbell, Stephen" <Stephen.Campbell@nrc.gov>
Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov>
Tracking Status: None Post Office:
TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 249 9/9/2011 10:35:26 AM NRC PM Open Items List 9-12-11.docx 31424 Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received:
Page 1 of 3 NRC PM Open Items List 9/12/11 (423) 751-7777 ID 4233652004#
No.
Description Status Additional Comments Resp Org/Person
- 1.
Cyber Security Plan/Controls and Implementation NRC TI issued TBD NRC Table Top/Pilot Oct 2011 Procedures complete 9/30/11 Pre-inspection TBD Inspection Dec 2011 NRC Inspection in 2011 To be discussed at the next ACRS meeting (October 5th - closed portion).
Set up follow-up meeting 9/20 or 9/21 Heinrich/Snyder (Bryan)
- 2.
Instrumentation RAI List (Knuettel)
- 1. Item 3 for GA-ESI RM-1000 RAD Monitors.
- 2. GA proprietary, non-proprietary and affidavits for withholding submittals
(~12 documents.)
- 3. NRC comments on procedures to GA-ESI
- 4. RM1000 EMI/RFI questions
- 5. Submit non-prop/affidavits
- 1. 9/23/11
- 2. Various -
see status
- 3. 9/26/11
- 4. 10/1/11
- 5. 11/30/11 RAI Responses
- Item 1 GA/ESI is preparing a report to document the conformance of their CGD program to NRC requirements based on NRC telecom on 8/30/11.
Item 2 - 04038903-1SP - Prop due 9/30/11 04038903-2SP - Prop due 10/6/11 04038903-4SP - Prop due 10/21/11 04038903-QSR - Prop due 9/30/11 Item 3 OP-7.3-240 - Prop due 9/26/11
- Item 4 Create new bridge document 04038800-1SP - Prop due 10/1/11 Eng/Hilmes (Smith)
- 3.
Verify MACCs values for SAMA Cost Benefit Evaluation
- 1. 9/8/11A
- 2. 9/13/11
- 3. 9/20/11
- 1. Non-conservatisms in some values identified.
Discuss updated results with NRC
- 2. Submitted revised tables
- 3. Submit revised RAI responses ENG/Koontz
Page 2 of 3 No.
Description Status Additional Comments Resp Org/Person
- 4.
Exemption to 10CFR50.49 for some Category II cables 9/23/11 Hilmes (Stockton)
- 5.
Complete Implementation (Hemmer)
Pump Relocation 5/30/12 Bldg Plan 9/23/11 Inspection -
June 2012 Phase I commitments 10/1/11 Additional clarification to Phase I actions will be needed. Fleet wide issue.
Substantial building to complete and equipment in May.
Provide document of mitigating equipment and location for unit 2.
Hemmer (Smith)
- 6.
Chapter 15.5 RAIs 9/21/11 Includes FHA calc. X/Q discussion for each accident, corrections to previously submitted dose calcs, and a complete 15.5 markup. Potential meeting following submittal. Look at splitting submittal up.
Wastrack (Bryan)
- 7.
Fire Protection Report Questions regarding OMA
- 1. 10/24-28/11 2.9/30/11 3.10/1/11
- 4. 11/4/11
- 5. 11/30/11
- 1. Audit
- 2. Group 7 RAI response
- 3. Receive Group 8 RAIs
- 4. Response to Group 8
- 5. Submit As-designed U1/U2 FPR ENG/Hilmes (Crouch)
- 8.
Tech Spec Revisions from latest T/S markup and NRC Review comments
- 1. Oct, 2011
- 2. Sept, 2011
- 3. Oct, 2011
- 4. TBD
- 1. CSST A & B - discretionary
- 2. I-131 DEI
- 3. Diesel Generator Frequency
- 9.
ACRS Topics 10/5/11 Cyber, Chapter 15 except dose, Chapter 4 (Fuels),
WINCISE, Hydrology, process for FSAR drawing documentation update, Gordon
- 10.
SSER 22/23/24 Open Items Response 9/16/11 9/16 is the target date for the next SSER update. The expanded HH list and status is covered periodically.
Licensing
- 11.
Transient Analysis issues Boron dilution RAI response 9/16/11 Question on RG revision and modes 3, 4, & 5. TVA to provide write up explaining NRC acceptance (CLB) of unit1 for modes 3, 4, & 5.
ENG/Koontz WEC/Morgan
Page 3 of 3 No.
Description Status Additional Comments Resp Org/Person
- 12.
FSAR A106 9/16/11 Target date. Correction - change note 17 of Table 7.1.1 to Reg Guide 1.152 R 3 instead of R 2 Lic/Stockton
- 13.
Develop list of planned License Conditions, Exemptions and Relief Requests (Crouch)
- 1. 11/1/11
- 2. TBD
- 1. Review Unit 1 SER for exemptions. Sand baskets, cyber security, physical security, PAD 4.0
- 2. NRR to review current exemptions NRR/TVA (Bryan)
- 14.
Verify Tech Spec Setpoints match calcs TS certification
- 1. 10/4/11
- 2. TBD
- 1. 6 SSDs remaining to be issued.
- 2. TS certification Eng/Hilmes (Bryan)
- 15.
Issue two Unit Offsite Dose Calculation Manual (Beach) Review TS Chapter 5 programs also 3/1/12 Determine actual need date Chemistry/
Woods (Bryan)
- 16.
Issue Unit 2 Completion Letter (Crouch) 8/1/12 Licensing
- 17.
Submit final as-constructed FSAR figures 7/1/12 Licensing/
Stockton
- 18.
TMI action items 7/1/12 TVA to provide letter when TMI actions are field complete.
Licensing (Gordon)
- 19.
ASME N-801 & N-802 code cases March 2012`
NRC response to relief request submitted 9/1/11.
- 0.
Discretionary Actions
- 1.
Letter to terminate Part 30/40 License after receipt of Part 50 License 4/1/12 Licensing (Crouch)
- 2.
Combined U1/U2 FSAR (Stockton) 3/1/13 Licensing
- 3.
Status of GSI 199 Eastern Seismicity (Crouch)
Fall 2011 No action pending upcoming Generic Letter Related information on GSI 194 may need input TVA/NRR
- 4.
Letter to notify NRC when Vital Area Boundary returned to original location 12/1/11 Security Plan Update - Boundary to be restored by 9/30/11 Lic/Crouch
- 5.
IEB 88-02 SG Tube Cracking TBD Tubes are assumed locked in the WEC analysis.
Waiting for NRC concurrence.
Corp SG/
Webber ISI/Tinley