Letter Sequence Meeting |
---|
|
Administration
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
Results
Other: ML111640211, ML111861529, ML111890408, ML111890413, ML112130165, ML112350873, ML112350883, ML112630673, ML112630676, ML112770237, ML112770246, ML112770251, ML113050623, ML113060606, ML113060615, ML113060623, ML113210411, ML113330116
|
MONTHYEARML1104105052011-02-10010 February 2011 2/22/11 Notice of Forthcoming Public Meeting with STP Nuclear Operating Co., Units 1 & 2, to Discuss Risk-informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor Sump Performance, Resolution Option Approach Project stage: Meeting ML1107700052011-04-0505 April 2011 Summary of Meeting with STP Nuclear Operating Company to Discuss a Risk-informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Option Approach for South Texas, Units 1 and 2 Project stage: Meeting ML1113302442011-05-16016 May 2011 Notice of Meeting with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 and 2 Project stage: Meeting ML1114706522011-05-16016 May 2011 Correction 06/02/2011 Notice of Meeting with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 Project stage: Meeting ML11157A0102011-06-0202 June 2011 STP Nuclear Operating Company, Licensee Handouts, 6/2/2011 Meeting Risk-Informed GSI-191 Closure Plan for GSI-191 Resolution Project stage: Meeting ML1116401602011-06-21021 June 2011 Summary of Meeting with STP Nuclear Operating Company Regarding Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance; Resolution Approach for South Texas, Units 1 and 2 (TAC ME5358-ME5 Project stage: Meeting ML1116402112011-06-24024 June 2011 Notice of Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 & 2 Project stage: Other ML1118903912011-07-0606 July 2011 Email Additional Materials for Teleconference on 7/7/11 with STP to Discuss Risk Informed GSI-191 Project stage: Meeting ML1118904082011-07-0606 July 2011 Licensee Handout Loca Frequencie Approach and Example Application Project stage: Other ML1118904132011-07-0606 July 2011 Licensee Slide Regarding Questions on LOCA Frequency Analysis and Responses to Comments Project stage: Other ML1118904202011-07-0606 July 2011 Licensee Slide from 7/7/11 Meeting with STP Nuclear Project stage: Meeting ML1118903762011-07-0707 July 2011 Email Licensee Slides for 7/7/11 Teleconference with STP to Discuss Risk Informed GSI-191 Project stage: Meeting ML1118903802011-07-0707 July 2011 Licensee Slides, LOCA Initiating Event Frequencies and Uncertainties(Draft) Project stage: Draft Other ML1118615292011-07-12012 July 2011 Notice of Conference Call with STP Nuclear Operating Company to Discuss Risk-informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 and 2 Project stage: Other ML1120707292011-07-26026 July 2011 Meeting Notice with South Texas Project, Units 1 and 2 - Licensee Slides Computational Fluid Dynamics Validation Plan Project stage: Meeting ML1120707072011-07-26026 July 2011 Meeting Notice with South Texas Project, Units 1 and 2 - Licensee Slide Models and Methods Used for Casa Grande Project stage: Meeting ML1121301822011-08-0202 August 2011 Meeting Notice with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 and 2 (TAC ME5358-ME5359 Project stage: Meeting ML1119500942011-08-0404 August 2011 Summary of Meeting with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 and 2 Project stage: Meeting ML1121301652011-08-19019 August 2011 7/26/11 - Summary of Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 an Project stage: Other ML1123508732011-08-22022 August 2011 Models and Methods Used for Casa Grande Project stage: Other ML1123508832011-08-22022 August 2011 LOCA Initiating Event Frequencies and Uncertainties Status Report Project stage: Other ML1125101482011-09-15015 September 2011 Notice of Meeting by Conference Call with STP Nuclear Operating Co. to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 and 2 Project stage: Meeting ML1126306732011-09-20020 September 2011 Email, NRC Staff Questions, Loss-of-Coolant Accident Frequency Analysis, Resolution Approach for Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance. Project stage: Other ML1126306762011-09-20020 September 2011 NRC Staff Questions, Loss-of-Coolant Accident Frequency Analysis, Resolution Approach for Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance. Project stage: Other ML1127702372011-09-30030 September 2011 LOCA Frequencies for STP GSI-191( Final) Project stage: Other ML1127701702011-10-0303 October 2011 E-mail Licensee Handouts for 10/3/11 Public Meeting Project stage: Meeting ML1127701762011-10-0303 October 2011 Licensee Handouts from 10/3/11 Meeting STP LOCA Frequency Project stage: Meeting ML1127702032011-10-0303 October 2011 Licensee Slides from 10/3/11 Meeting LOCA Frequencies, Final Results Project stage: Meeting ML1127702302011-10-0303 October 2011 E-mail Documents for 10/3/11 Teleconference Project stage: Meeting ML1127702462011-10-0303 October 2011 E-mail Questions Associated with LOCA Frequency Analysis Project stage: Other ML1127702512011-10-0303 October 2011 STP Responses to Questions Associated with LOCA Frequency Analysis Project stage: Other ML1124114192011-10-0404 October 2011 8/22/11 Summary of Meeting with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 and 2 (TAC M Project stage: Meeting ML1127901512011-10-11011 October 2011 Notice of Meeting by Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 & Project stage: Meeting ML1127900992011-10-11011 October 2011 Notice of Meeting by Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 an Project stage: Meeting ML1130606232011-10-20020 October 2011 Technical Review of STP LOCA Frequency Estimation Methodology Project stage: Other ML1130506322011-10-26026 October 2011 Licensee Handouts from November 1, 2011 Meeting with STP Nuclear Operating Company on GSI-191 Project stage: Meeting ML1130506232011-10-26026 October 2011 Alion- Expected Impact of Chemical Effects on GSI-191 Risk Informed Evaluation for South Texas Project Project stage: Other ML1130606152011-10-31031 October 2011 LOCA Frequencies for STP Nuclear Operating Company GSI-191 Project stage: Other ML1128401142011-10-31031 October 2011 10/3/11 Summary of Meeting Via Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas Project stage: Meeting ML1129701092011-11-0101 November 2011 Notice of Meeting Via Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor Sump Performance, Resolution Approach for South Texas, Units 1 & 2 Project stage: Meeting ML1132104112011-11-0101 November 2011 Revised Notice of by Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Project stage: Other ML1130606062011-11-0202 November 2011 Questions Associated with Loss-of-Coolant Accident (LOCA) Frequency Analysis Project stage: Other ML1133301162011-11-29029 November 2011 Email, 11/1/2011 Pre-Licensing Conference Call to Discuss the Topic of Expected Impact of Chemical Effects on GSI-191 Risk-Informed Evaluation, Phenomena Identification and Ranking Table Items (TAC ME5358-ME5359) Project stage: Other ML1131201292011-11-29029 November 2011 Summary of 11/1/11 Meeting by Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance,Resolution Approach for South Texas, Un Project stage: Meeting ML1133505632011-12-0101 December 2011 Licensee Presentation from 12/1/11 Meeting Via Conference Call to Discuss Risk-Informed GSI-191,Assessment of Debris Accumulation on Pressurized Water Reactor Sump Performance Project stage: Meeting ML1131801962011-12-0505 December 2011 Summary of Meeting with STP Nuclear Operating Company Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas Units 1 and 2 Project stage: Meeting ML1134300872011-12-23023 December 2011 Summary of 12/1/11 Meeting by Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas Un Project stage: Meeting 2011-05-16
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML22252A0432022-09-12012 September 2022 Summary of August 31, 2022, Webinar with STP Nuclear Operating Company to Discuss a Proposed LAR to Revise the Dose Consequence Analysis for Main Steam Line Break and Locked Rotor Analysis Events for STP, Units 1 & 2 ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML21236A3082021-09-10010 September 2021 Regulatory Audit Summary Regarding License Amendment Request to Revise Moderator Temperature Coefficient Surveillance Requirements ML21222A1192021-08-12012 August 2021 Summary of Meeting with STP Nuclear Operating Company Regarding the License Amendment Request to Revise the Moderator Temperature Coefficient Surveillance Requirements for South Texas Project, Units 1 and 2 ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML20279A8152020-10-20020 October 2020 Summary of September 14, 2020, Presubmittal Teleconference with STP Nuclear Operating Company Regarding the Proposed LAR to Revise the Moderator Temperature Coefficient Surveillance Requirement for South Texas Project, Units 1 and 2 (EPID L ML20189A2832020-07-0707 July 2020 Summary of Region IV Annual Assessment Public Meeting ML20163A5522020-06-12012 June 2020 Summary of April 21, 2020, Teleconference with STP Nuclear Operating Company to Discuss the License Amendment Request to Revise the Emergency Plan for South Texas Project, Units 1 and 2 ML20140A2612020-05-27027 May 2020 May 5, 2020, Summary of Teleconference with STP Nuclear Operating Company to Discuss a Proposed Exigent License Amendment Request to Revise the Pressure of the Safety Injection Accumulators for South Texas Project, Unit 1 ML20107J5482020-04-15015 April 2020 Teleconference Regarding NRC Observations on the March 30, 2020, License Amendment Request to Revise the Emergency Plan STP Nuclear Operation Company South Texas Project, Units 1 and 2, Dockets 50-498 and 50-499 ML20049A0572020-02-26026 February 2020 Summary of February 6, 2020, Meeting with STP Nuclear Operating Company to Discuss a Proposed License Amendment Request to Revise the Emergency Plan for South Texas Project, Units 1 and 2 (EPID L- 2020-LRM-0004) ML19350C5902019-12-17017 December 2019 12/3/19, Summary of Teleconference with STP Nuclear Operating Company to Discuss a Proposed License Amendment Request to Revise the Emergency Plan for South Texas Project, Units 1 and 2, ML19102A0162019-04-16016 April 2019 4/10/2019 Summary of Public Teleconference Regarding Potential Submission of a Relief Request to Allow Use of Carbon Fiber Reinforced Polymer for Selected Piping Repairs at South Texas, Units 1 and 2 ML17005A1002017-01-18018 January 2017 January 4, 2017, Summary of Meeting to Discussion Stp'S Response to Request for Additional Information the Revised Aluminum Bronze Selective Leaching Aging Management Program for All Potentially Susceptible Welds Throughout the Facility ML16279A3312016-10-27027 October 2016 Summary of Public Meeting with STP Nuclear Operating Company Regarding Open Items, Risk-Informed Generic Safety Issue (GSI) 191 Application and Supplements for South Texas Project, Units 1 and 2 (CAC Nos. MF2400-MF2409) ML16272A4362016-10-14014 October 2016 Summary of Public Preapplication Meeting with STP Nuclear Operating Company to Discuss Possible License Amendment Request to Modify Emergency Response Organization for South Texas Project, Units 1 and 2 ML16246A0222016-10-0505 October 2016 Summary of Public Meeting with STP Nuclear Operating Company Regarding Open Items Related to Risk-Informed Generic Safety Issue (GSI) 191 Application and Supplements for South Texas Project, Units 1 and 2 (CAC Nos. MF2400 - MF2409) ML16238A5272016-09-0101 September 2016 Summary of 7/28/16, Public Meeting with STP Nuclear Operating Company to Discuss the License Amendment and Exemption Requests to Use a Risk-Informed Approach to the Resolution of GSI-191 (CAC Nos. MF2400 - MF2409) ML16218A3672016-08-30030 August 2016 07/21/2016 Summary of Public Teleconference Meeting with STP Nuclear Operating Company Discussing Revisions to License Renewal Application Aluminum Bronze Selective Leaching Aging Management Program and Background Document ML16236A0322016-08-23023 August 2016 08/18/2016 Summary of Conference Call With STP Nuclear Operating Company Concerning the Aluminum Bronze Selective Leaching Aging Management Program in the South Texas Project, License Renewal Application ML16236A3042016-08-23023 August 2016 08/11/2016 Summary of Conference Call Between NRC and STP Nuclear Operating Company Concerning the 2016 Annual Update to the South Texas Project License Renewal Application ML16180A0142016-07-25025 July 2016 Summary of Meeting Discussion Between South Texas Project, Units 1 and 2, and NRC Staff Regarding the Revised Aluminum Bronze Selective Leaching Aging Management Program for All Potentially Susceptible Welds Throughout the Facility ML16190A0082016-07-13013 July 2016 Summary of 6/22/2016 Public Meeting with STP Nuclear Operating Company Regarding Open Items, Risk-Informed Generic Safety Issue (GSI) 191 Application and Supplements for South Texas Project, Units 1 and 2 (CAC Nos. MF2400-MF2409) ML16188A0072016-07-0707 July 2016 Summary of Telecon Held on July 5, 2016 With STP Nuclear Operating Company, Concerning Additional Information Pertaining to the STP, License Renewal Application (TAC. Nos. ME4936, ME4937) ML16188A0112016-07-0707 July 2016 Summary of Telecon Held on July 5, 2016 With STP Nuclear Operating Company, Concerning Additional Information Pertaining to the STP, License Renewal Application (TAC Nos. ME4936, ME4937) ML16188A0092016-07-0707 July 2016 Summary of Telecon Held on July 5, 2016 with STP Nuclear Operating Company, Concerning Additional Information Pertaining to the STP, License Renewal Application (Tac. Nos. ME4936, ME4937) - Enclosure 1 ML16175A1082016-06-24024 June 2016 Summary of 4/21/2016 Public Meeting with STP Nuclear Operating Company Regarding Open Items, Risk-Informed Generic Safety Issue (GSI) 191 Application and Supplements for South Texas Project, Units 1 and 2 ML16166A0272016-06-14014 June 2016 Summary of Telephone Conference Call Held on 06/08/2016, Between the USNRC and STP Nuclear Operating Company Response to Request for Additional Information B2.1.18-6 Pertaining to the South Texas Project License Renewal Application ML16092A0852016-04-13013 April 2016 3/17/2016 Summary of Public Meeting with STP Nuclear Operating Company Regarding Open Items, Risk-Informed Generic Safety Issue (GSI) 191 Application and Supplements for South Texas Project, Units 1 and 2 (CAC Nos. MF2401-MF2409) ML16092A0442016-04-11011 April 2016 Summary of 3/3/2016 Public Meeting with STP Nuclear Operating Company Regarding Open Items, Risk-Informed Generic Safety Issue (GSI) 191 Application and Supplements for South Texas Project, Units 1 and 2 (CAC Nos. MF2400-MF2409) ML16088A2432016-04-0101 April 2016 2/18/2016, Summary of Public Meeting with STP Nuclear Operating Company Regarding Open Items, Risk-Informed Generic Safety Issue (GSI) 191 Application and Supplements for South Texas Project, Units 1 and 2 (CAC Nos. MF2400-MF2409) ML16081A2052016-03-24024 March 2016 Summary of Meeting with STP Nuclear Operating Company to Discuss Potential License Amendment Request for South Texas Project, Unit 1 Regarding Permanent Operation with 56 Control Rods ML16074A0412016-03-14014 March 2016 Summary of a Call Held on March 10, 2016, between USNRC and STPNOC, Concerning the Staff's Upcoming Audit Regarding the Amp for the Loss Of Material Due to Selective of Al-Br Welds in the ECW System for the STP LRA (TAC Nos. ME4936 And ME4937) ML16060A1272016-03-0707 March 2016 February 23, 2016, Summary of Conference Calls Held between NRC and STP Concerning Staff's Review of Submerged Closure Bolting Portion of 2014 Annual Update for STP License Renewal Application (TAC ME4936 And ME4937) ML16028A1522016-02-18018 February 2016 1/14/2016 Summary of Public Meeting with STP Nuclear Operating Company Regarding Modifications to the Licensee'S Risk-Informed Generic Safety Issue (GSI) 191 Application and Supplements for South Texas Project, Units 1 and 2 ML16035A4802016-02-12012 February 2016 Jsc Meeting Summary Attachment ML16011A0612016-02-0202 February 2016 Summary of 10/1/15 Meeting with STP Nuclear Operating Company to Discuss Revised Pilot Submittal and Request for Exemptions for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 at South Texas Project, Units 1 and 2 (CAC MF ML16011A0702016-01-28028 January 2016 Summary of Preapplication Meeting with STP Nuclear Operating Company to Discuss Exigent License Amendment Request to Operate Following Removal of a D6 Control Rod at South Texas Project, Unit 1 ML16033A0072016-01-19019 January 2016 January 19, 2016, Summary of Public Meeting with STP to Discuss the Plant-Specific Aging Management Program, Selective Leaching of Aluminum Bronze, Associated with STP's License Renewal Application ML16013A0662016-01-14014 January 2016 Summary of 11/9 and 12/30/15 Conference Calls with STP Nuclear Operating Company to Discuss the Fall 2015 Steam Generator Tube Inspection Activities (CAC No. A11018) ML15308A0112015-11-30030 November 2015 Record of Conference Call on STP Request for Additional Information Set 34 ML15201A0032015-07-30030 July 2015 7/2/15 Summary of Meeting with STP Nuclear Operating Company to Discuss Revised Pilot Submittal and Request for Exemptions for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 at South Texas, Units 1 and 2 ML15177A1042015-07-21021 July 2015 4/22/2015 Summary of Meeting with STP Nuclear Operating Company to Discuss Revised Pilot Submittal and Request for Exemptions for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 at South Texas, Units 1 and 2 (TAC MF2400 t ML15177A2742015-07-21021 July 2015 5/6/2015 Summary of Meeting with STP Nuclear Operating Company to Discuss Revised Pilot Submittal and Request for Exemptions for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 at South Texas, Units 1 and 2 (TAC Nos. MF24 ML15180A2732015-07-15015 July 2015 6/3/2015 Summary of Meeting with STP Nuclear Operating Company to Discuss Revised Pilot Submittal and Request for Exemptions for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 at South Texas, Units 1 and 2 (TAC MF2400 to ML15139A3442015-06-11011 June 2015 Summary of Telephone Conference Call Held on May 12, 2015 Between the U.S. Nuclear Regulatory Commission and STP Nuclear Operating Company, Concerning Request for Additional Information, Set 31, Pertaining to the South Texas Project, Licens ML15103A0022015-05-13013 May 2015 Summary of 4/8/15 Meeting with STP Nuclear Operating Company to Discuss Revised Pilot Submittal and Request for Exemptions for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 at South Texas, Units 1 and 2 ML15084A0032015-04-0606 April 2015 2/4/15 Summary of Meeting with STP Nuclear Operating Company to Discuss Revised Pilot Submittal and Request for Exemptions for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 at South Texas, Units 1 and 2 (TAC MF2400-MF24 ML15084A0042015-04-0101 April 2015 2/5/2015 Summary of Presubmittal Meeting with STP Nuclear Operating Company to Discuss Integrated Leak Rate Testing Program License Amendment Request for South Texas, Units 1 and 2 ML15020A1062015-02-19019 February 2015 12/1-3/2014 Summary of Meeting with STP Nuclear Operating Company to Discuss Revised Pilot Submittal and Request for Exemptions for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 at South Texas, Unit 1 and 2 (TAC MF2400- 2022-09-12
[Table view] Category:Memoranda
MONTHYEARML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22034A3932022-02-16016 February 2022 Calendar Year 2021 Security Baseline Completion Memo ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML19102A0162019-04-16016 April 2019 4/10/2019 Summary of Public Teleconference Regarding Potential Submission of a Relief Request to Allow Use of Carbon Fiber Reinforced Polymer for Selected Piping Repairs at South Texas, Units 1 and 2 ML18304A2902018-11-19019 November 2018 STP ISFSI PSP Rev 23 Review ML18289A5652018-10-16016 October 2018 Memorandum to D. White Technical Assistance Request - Review of Physical Security Plan for the South Texas Project Generating Station Independent Spent Fuel Storage Installation (CAC No.001027) ML18173A0082018-06-20020 June 2018 Cancelling Numerous Inspection Report Numbers ML17233A0082017-08-21021 August 2017 Notification of Administrative Correction to Renewed Facility Operating License ML17187A1782017-07-0606 July 2017 License Renewal Application ML17137A3252017-05-17017 May 2017 Safety Evaluation of LAR by South Texas Project Nuclear Operating Company to Adopt a Risk-Informed Resolution of Generic Safety Issue-191 ML15190A0422017-05-12012 May 2017 the NRC Staff Evaluation of the Final Rule for Continued Storage of Spent Nuclear Fuel for the License Renewal Environmental Review for South Texas Project, Units 1 and 2 ML16334A4002017-03-24024 March 2017 Climate Change Review Analysis for South Texas Project, Units 1 and 2 - License Renewal Application ML16302A0162016-10-12012 October 2016 Corrected After Action Report/ Improvement Plan for Plume Phase Exercise Conducted on 07/13/2016 ML16013A0662016-01-14014 January 2016 Summary of 11/9 and 12/30/15 Conference Calls with STP Nuclear Operating Company to Discuss the Fall 2015 Steam Generator Tube Inspection Activities (CAC No. A11018) ML13330B2222013-12-0505 December 2013 Notice of Meeting with STP Nuclear Operating Company to Discuss Revised Pilot Submittal and Request for Exemptions for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 at South Texas Project, Units 1 and 2 (TAC MF2400-MF24 ML13324A4942013-11-19019 November 2013 Deferral of Baseline Inspection Activities ML13303A9742013-10-31031 October 2013 PubMtgNotice-Nov13-2013-update ML13119A0802013-04-30030 April 2013 Notice Meeting Via Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed Approach to Resolve Generic Safety Issue 191 for South Texas, Units 1 and 2 ML13101A3142013-04-12012 April 2013 Notice of Meeting Via Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed Approach to Resolve Generic Safety Issue 191 for South Texas, Units 1 and 2 ML13023A3342013-02-25025 February 2013 1/15/2013 Summary of Public Meetings Conducted to Discuss Draft Supplemental Environmental Impact Statement Related to Review of South Texas Project, Units 1 & 2, License Renewal Application ML13046A0652013-02-22022 February 2013 3/5/13 Notice of Preapplication Meeting Via Conference Call with STP Nuclear Operating Company to Discuss License Amendment Request for Fire Protection Program to Credit Additional Operator Actions for South Texas, Units 1 and 2 ML12342A3972013-01-0303 January 2013 Forthcoming Meeting to Discuss the Draft Supplemental Environmental Impact Statement for the License Renewal of South Texas Project, Units 1 and 2 ML12340A1352012-11-27027 November 2012 Meeting Notice by Conference Call with STP Nuclear Operating Company; Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution South Texas Project, Units 1 and 2 ML12331A2922012-11-27027 November 2012 Notice of Meeting by Conference Call with STP Nuclear Operating Company; Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 and ML12321A1222012-11-20020 November 2012 12/3/12 Notice of Meeting by Conference Call with STP Nuclear Operating Company; Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Unit ML12312A2342012-11-13013 November 2012 Memo to File Summary Verbal Authorization Provided on 11/6/12 for Relief Request RR-ENG-3-10, RPV Head Flange O-Ring Leakoff Lines NDE, Third 10-Year Inservice Inspection Interval ML12243A4042012-09-25025 September 2012 Notice of Prelicensing Meeting with STP Nuclear Operating Company to Discuss Proposed Amendment for Approval of Revised Fire Protection Program Related to Alternate Shutdown Capability for South Texas, Units 1 and 2 ML12261A3012012-09-21021 September 2012 Notice of Forthcoming Public Meeting Via Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach ML12227A5602012-09-12012 September 2012 Summary of Telephone Conference Call Held on August 9, 2012, Between NRC and STPNOC, Concerning Clarification of One Part of Response to RAI 4.3-13. Pertaining to the STP, Units 1 and 2, LRA ML12227A5902012-08-23023 August 2012 9/6/2012 Notice of Meeting by Conference Call with STP Nuclear Operating Company; Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Uni ML12226A4552012-08-15015 August 2012 Forthcoming Meeting with STP Nuclear Operating Company Regarding License Renewal for the South Texas Project, Units 1 and 2 ML12206A3032012-08-0707 August 2012 Summary of Telephone Conference Call Held on 7/3/12, Between the U.S. NRC and STP Nuclear Operating Company, Concerning Debris from Coating Failures - Followup, Pertaining to the South Texas Project, Units 1 and 2, LRA, TAC Nos. ME4936 and ML12146A0202012-05-31031 May 2012 Notice of 6/11/12 Meeting by Conference Call with STP Nuclear Operating Company; Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Unit ML12080A0352012-04-19019 April 2012 Summary of Telephone Conference Call Held on February 22, 2012 Between the U.S. Nuclear Regulatory Commission and STP Nuclear Operating Company, Regarding Requests for Additional Information STP - Record of Conference Call-02222012 on RAIs- ML12080A0552012-04-11011 April 2012 STP - Record of Conference Call-03082012 on RAIs-SGTI-RxHeadStudClosures ML12080A0492012-04-11011 April 2012 STP - Record of Conference Call-03012012 on RAIs-RV Beltline ML12080A0442012-04-11011 April 2012 STP - Record of Conference Call-02092012 on RAIs-TLAAs ML12080A0402012-04-11011 April 2012 STP - Record of Conference Call-020162012 on RAIs-RVIs-31180-etc ML1207400312012-03-15015 March 2012 3/29/12 Notice of Meeting Viaconference Call with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for Units 1 and 2 ML1203400432012-02-0303 February 2012 Notice of Forthcoming Meeting Via Conference Call with STP Nuclear Operating Company ML1203003642012-02-0202 February 2012 3/8/12 Forthcoming Meeting by Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, U ML1200901012012-01-10010 January 2012 Notice of Forthcoming Public Meeting Via Conference Call with South Texas Project Nuclear Operating Company ML11348A0392012-01-0404 January 2012 and 12/1/11, Summary of Telephone Conference Calls Between the U.S. Nuclear Regulatory Commission and STP Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the South Texas Project LRA - Set 9 ML11320A1162011-12-0505 December 2011 November 9, 2011, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and STP Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the South Texas Project Units 1 and 2 ML1129701092011-11-0101 November 2011 Notice of Meeting Via Conference Call with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor Sump Performance, Resolution Approach for South Texas, Units 1 & 2 ML1124114192011-10-0404 October 2011 8/22/11 Summary of Meeting with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 and 2 (TAC M ML1125101482011-09-15015 September 2011 Notice of Meeting by Conference Call with STP Nuclear Operating Co. to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 and 2 ML11216A2632011-08-23023 August 2011 Summary of Telephone Conference Call Held on July 28, 2011, Between the U.S. NRC and STP Nuclear Operating Company, Concerning RAI Pertaining to the South Texas Project, LRA ML1121301822011-08-0202 August 2011 Meeting Notice with STP Nuclear Operating Company to Discuss Risk-Informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 and 2 (TAC ME5358-ME5359 ML1118615292011-07-12012 July 2011 Notice of Conference Call with STP Nuclear Operating Company to Discuss Risk-informed GSI-191, Assessment of Debris Accumulation on Pressurized-Water Reactor (PWR) Sump Performance, Resolution Approach for South Texas, Units 1 and 2 2022-06-06
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 4, 2011 LICENSEE: STP Nuclear Operating Company FACILITY: South Texas Project, Units 1 and 2
SUBJECT:
SUMMARY
OF AUGUST 22, 2011, PRE-LICENSING PUBLIC MEETING WITH STP NUCLEAR OPERATING COMPANY TO DISCUSS THE PROPOSED RISK-INFORMED APPROACH TO THE RESOLUTION OF GSI-191, "ASSESSMENT OF DEBRIS ACCUMULATION ON PWR SUMP PERFORMANCE" (TAC NOS. ME5358 AND ME5359)
On August 22,2011, a public meeting was held between the U.S. Nuclear Regulatory Commission (NRC), and representatives of STP Nuclear Operating Company (STPNOC, the licensee), at NRC Headquarters, Rockville, MD. The meeting notice and agenda, dated August 2, 2011, is located in the Agencywide Documents Access and Management System (ADAMS) under Accession No. ML112130182. The purpose of the meeting was to discuss the proposed risk-informed approach to the resolution of Generic Safety Issue (GSI)-191, "Assessment of Debris Accumulation on PWR [Pressurized-Water Reactor1 Sump Performance." South Texas Project (STP) is the lead plant and STPNOC plans to submit a license amendment request (LAR) in mid-2012. The licensee previously provided an overview of its proposed approach during the public meetings held on June 2, July 6, and July 26, 20111.
The purpose of this conference call was to provide an overview of the Containment Accident Sequence Stochastic Analysis (CASA) Grande method for calculating the effects of debris generated from a spectrum of postulated accidents on emergency core cooling system pump performance and the topic of jet formation as a result of a break.
The licensee's presentation slides and additional materials provided for the meeting are located at ADAMS Accession No. ML112350857. A list of meeting attendees is provided in the Enclosure to this meeting summary.
Meeting Summary The licensee provided copies of the following presentations prior to the meeting:
- 1. Models and Methods Used for CASA Grande
- a. Required Inputs to CASA Grande
- b. Topical Approach and Implementation Plan
- c. Interface with Probabilistic Risk Assessment (PRA)
- d. Example Calculations to Illustrate Physics Models 1 Summaries of the meetings held on June 2, July 7, and July 26, 2011, are available in ADAMS Accession Nos ML111640160, ML111950094, and ML112130165, respectively.
-2
- 2. Loss-of-Coolant Accident (LOCA) Initiating Event Frequencies and Uncertainties Status Report
- a. Current Status
- b. Refinements of Approach for Conditional Rupture Probabilities
- c. Preliminary Results
- d. Independent Review by Ali Mosleh
- e. Issues to Complete Item 2 above was not included in the agenda published in the Federal Register, and, therefore, could not be discussed during the meeting. The NRC staff advised STPNOC that this topic could be scheduled for discussion at a future meeting.
The topic of jet formation announced in the Notice for this meeting was not discussed.
STPNOC representatives indicated that they were unable to complete the analysis in time and were not ready for discussion. The topic of jet formation will also be discussed in a future public meeting.
The licensee presented an overview of the Models and Methods used for CASA Grande for subtopics 1.a, 1.b, 1.c, and 1d. The presentation covered the following in more detail:
Required Inputs to CASA Grande and Topical Approach and Implementation Plan
- Debris generation covering containment geometry, pipe break (LOCA) frequencies, zone of influence (lOI) size/shape for plant materials, debris characteristics for plant materials, qualified coating quantity for LOCA categories, unqualified coating category, latent debris quantity, and miscellaneous debris quantity.
- Chemical product generation (not required at STP) for initial quantification.
CASA Grande will have the capability to automatically calculate chemical debris quantities generated based on type of debris, buffer type in the pool, time dependent temperature in the pool, and the spray duration.
- Debris transport covering blowdown, washdown, pool fill, and recirculation transport fractions for LOCA categories, and fiberglass erosion fractions for non transporting pieces of debris, including upstream blockage.
- Air intrusion including vortexing and gas desorption, along with corresponding void fractions.
- Debris bypass based on the test data and flow conditions.
- 3 Interface to PRA STPNOC indicated that separate results will be compiled for each standard LOCA size (small, medium, and large). Initially, conditional break size probabilities (i.e. given a break, what is the probability that it is of a given size) will be used so that break frequencies can be addressed separately. Plant operating states and sump failure modes will be modeled in detail so that operator mitigating actions can be identified and modeled.
Example Calculations to Illustrate Physics Model STPNOC presented an example calculation to illustrate the physical model to be used for the risk-informed approach and reflected the use of the following:
- Break frequencies for the break considered (cold-leg weld break)
- ZOI for Nukon and Microtherm insulation material
- Microtherm debris generation
- Coating debris generation
- Latent and miscellaneous debris generation
- Blowdown, washdown, and pool fill transport
- Erosion of large pieces of Nukon
- Time dependent recirculation transport
- Nukon and microtherm debris transport (fine and large)
- Qualified, unqualified, and latent debris transport
- Strainer head-loss calculation and impact of gas desorption on head-loss calculation
- Debris bypass calculation to address the downstream effects The NRC staff asked several clarification questions during the presentation. The licensee's responses are summarized below:
- 1. Air intrusion calculation analysis will be performed by the use of pressurel temperature history with pressurized and non-pressurized containment conditions. Best-estimate model assumptions will be documented in the LAR.
- 2. The licensee stated initially that break sizes only from 2 inches to double-ended guillotine break (DEGB) will be considered for debris-generation calculations.
However, NRC staff expressed concern with this assumption and asked the licensee to provide justification. The licensee agreed to consider all breaks from Yz-inch to DEGB.
- 4
- 3. The licensee indicated that for STP chemical effects on debris generation are likely to be negligible and STP may not need to consider the chemical effects.
The NRC staff questioned the lack of a methodology to consider chemical effects on debris generation. The licensee agreed to discuss chemical effects testing, bypass, and in-vessel effects in a separate public meeting. The licensee asserted that if chemical effects are demonstrated to be a non-issue for STP, additional information will be provided regarding how chemical effects could be addressed under the risk-informed approach for those plants that may be impacted.
- 4. The licensee plans to provide more detail on the sampling method to be used to propagate the results and associated uncertainties through the PRA model to ensure that highly unlikely cases (Le., at the tails of the probabilistic distributions) are appropriately sampled and included in the analysis. The licensee expects to demonstrate that the sampling strategy is sufficiently robust to ensure that the results are valid and adequately estimate the risk associated with all break sizes.
- 5. The model discussed during the meeting covers only the weld breaks. The licensee clarified that potential non-weld breaks will be addressed in the final evaluation to be completed in 2012.
- 6. The licensee indicated that, during the recirculation mode, all possible combinations of three ECCS trains with CS system on and off will be analyzed for debris transport.
- 7. The NRC staff questioned the basis for the assumption that the unqualified coatings will reach the containment pool at 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The NRC staff believed that there should be some time-dependent distribution curve. The licensee agreed to make the impact of unqualified coating time dependent.
- 8. The NRC staff expressed concern that the sample calculation does not reflect the impact of the void fraction on the NPSH margin. The licensee agreed to address the impact of head loss due to gas desorption and resulting void fraction on the NPSH margin calculated based on the debris loading on the strainer.
- 9. The licensee expressed objection to the suggestion that STP will be significantly impacted by debris generation due to the use of Microtherm [thermal insulation material]. Because STP is the lead plant, the license agreed to include the methodology to address the impact of materials with adverse properties for debris generation (e.g. Microtherm) for the benefit of other licensees.
- 10. The licensee agreed to provide a plan for modifying the STP's PRA model detailing how sump blockage and downstream effects will be addressed for large, medium, and small breaks.
- 5 Action Items The NRC staff agreed to arrange another telephone conference call public meeting to discuss the topic of LOCA Initiating Event Frequencies and Uncertainties. The NRC and STPNOC representatives also agreed to hold the next face-to-face public meeting in October 2011.
No Public Meeting Feedback Forms were received for this meeting.
Please direct any inquiries to me at (301) 415-3016, or balwant.singal@nrc.gov.
Sincerely,
~~\~~~'\A-~
Balwant K. Singal, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-498 and 50-499
Enclosure:
List of Attendees cc w/encl: Distribution via Listserv
LIST OF ATTENDEES FOR MEETING WITH STP NUCLEAR OPERATING COMPANY REGARDING RISK-INFORMED APPROACH TO RESOLUTION OF GSI-191 ISSUE SOUTH TEXAS PROJECT. UNITS 1 AND 2 AUGUST 22, 2011 NAME TITLE ORGANIZATION Paul Jamie Licensing STPNOC Steve Blossom Project Manager STPNOC Rick Grantom Manager, Risk Projects STPNOC Ernie Kee Supervisor, Risk Management STPNOC Wes Schulz DeSign Engineer STPNOC
- Tim Sande Principal Engineer Alion Science and Technology I Craig D. Sellers Program Manager Alion Science and Technology Andre Drake Principal Engineer Constellation Energy John Koelbel* Fleet PRA Services Constellation Energy Brian Brogan* PRA Engineer Entergy (Palisades)
Jeff Voskuil* PRA Engineer Entergy (Palisades)
Keith Smith* Project Manager Entergy (Palisades)
Bill Beckius* Technical Consultant Entergy (Palisades)
Jeff Weyhmiller* Design Engineer Entergy (Palisades)
Karl Fleming Consultant KNF Consulting Bruce Letellier - Los Alamos National Laboratory Yassin Hassan Professor Texas A&M University Alex Galenko Research Associate University of Texas, Austin
- Erich Schneider Assistant Professor University of Texas, Austin i Ervin Geiger Reactor System Engineer NRC Ralph Architzel 1Senior Reactor Engineer NRC Balwant K. Singal Senior Project Manager NRC Steve Smith Reactor Systems Engineer NRC Stephen Dinsmore Senior Reliability and Risk Engineer NRC Stewart Bailey Branch Chief NRC Donnie Harrison Branch Chief NRC
- Participated via phone Entergy - Entergy Nuclear Operations NRC - U.S. Nuclear Regulatory Commission STPNOC - STP Nuclear Operating Company Enclosure
-5 Action Items The NRC staff agreed to arrange another telephone conference call public meeting to discuss the topic of LOCA Initiating Event Frequencies and Uncertainties. The NRC and STPNOC representatives also agreed to hold the next face-to-face public meeting in October 2011.
No Public Meeting Feedback Forms were received for this meeting.
Please direct any inquiries to me at (301) 415-3016, or balwantsingal@nrc.gov.
Sincerely, IRAI Balwant K Singal, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-498 and 50-499
Enclosure:
List of Attendees cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC CSteger, NRR LPLIV r/f JMcHale, EDO RIV RidsAcrsAcnw_MailCTR Resource SDinsmore, NRRIDRA/APLA RidsNrrDorlLpl4 Resource BPurnell, NRRIDPR/PGCB RidsNrrDprPgcb Resource DHarrison, NRR/DRA/APLA RidsNrrDraApla Resource SSmith, NRRIDSS/SSIB RidsNrrDssSsib Resource EGeiger, NRR/DSS/SSIB RidsNrrLAJBurkhardt Resource SBailey, NRR/DSS/SSIB RidsNrrPMSouthTexas Resource SLaur, NRRIDRA/APLA RidsOgcRp Resource RArchitzel, NRR/DSS/SSIB RidsRgn4MailCenter Resource DHarrison, NRR/DRA/APLA ADAMS Accession No. ML112411419 NRR/LPL4/PM NRR/LPL4/LA NRRlDSS/SSIB/BC NRRIDRA/APLAlBC NRR/LPL4/BC NRR/LPL4/PM BSingal J y DHarrison MMarkley BSingal 9/15/11 9/14/11 11 9/26/11 10/4/11 10/4/11 OFFICIAL RECORD COpy