Category:E-Mail
MONTHYEARML24260A0322024-09-10010 September 2024 NRR E-mail Capture - Request for Additional Information Regarding the Watts Bar Unit 2 Steam Generator Tube Inspection Report for U2R5 ML24215A3152024-07-24024 July 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Adopt TSTF-276-A, Revision 2 TS 3.8.1, AC Sources ML24177A1412024-06-11011 June 2024 NRR E-mail Capture - Audit Plan Related to Review of the Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, LAR to Revise Technical Specification Table 3.3.2-1 Function 5 ML24157A3152024-06-0303 June 2024 2024 Sequoyah Commercial Grade Dedication Inspection Information Request ML24155A1372024-05-29029 May 2024 Email from K. Green to S. Hughes Request for Additional Information Related to License Amendment Request to Revise Residual Heat Removal Flow Rate ML24156A0062024-05-22022 May 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Recapture Low-Power Testing Time ML24130A0132024-05-0707 May 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.7.11 for MCR Chiller Completion Time ML24123A0882024-05-0202 May 2024 NRR E-mail Capture - Correction Acceptance Review Results for the Browns Ferry, Sequoyah, and Watts Bar License Amendment Request to Revise TS 5.4.1 or 5.7.1 (L-2024-LLA-0039) ML24122B4872024-04-30030 April 2024 NRR E-mail Capture - Acceptance Review Results for the Browns Ferry, Sequoyah, and Watts Bar License Amendment Request to Revise TS 5.4.1 or 5.7.1 (L-2024-LLA-0039) ML24082A0662024-04-17017 April 2024 Email to Stuart Rymer on Exemption Decision for Watts Bar ML24116A2012024-04-17017 April 2024 Nrctva ISFSI CBS (RFI) ML24082A0682024-04-10010 April 2024 Email to Stuart Rymer Re_ Availability of EA-FONSI for Watts Bar ML24100A8392024-04-0909 April 2024 Response from State of Tn Regarding Review of Environmental Assessment for Watts Bar Exemption Request ML24100A8402024-04-0808 April 2024 Email to State of Tn Requesting Review of Environmental Assessment for Watts Bar Exemption Request ML24071A0982024-03-0707 March 2024 NRR E-mail Capture - Audit Plan Related to Review of the Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce RHR Flow Rate ML24058A0962024-02-26026 February 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant License Amendment Request to Revise UFSAR for Hydrologic Analysis ML24047A2792024-02-15015 February 2024 RAI Related to the Exemption Request for 10 CFR 37.11 ML24045A0312024-02-14014 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML24033A0562024-02-0101 February 2024 NRR E-mail Capture - Correction Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Adopt TSTF-427-A, Revision 2 Regarding Degraded Barriers ML24036A0132024-01-23023 January 2024 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar Nuclear Plants, License Amendment Request to Revise TS Table 3.3.2-1, Function 5, Turbine Trip and Feedwater Isolation ML24022A2592024-01-22022 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Revise TS LCO 3.8.2 to Remove Note C-S Diesel Generator ML24016A0762024-01-16016 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2 - License Amendment Request to Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications ML23347A0642023-12-13013 December 2023 12-13-23 Email from Kimberly Green to Wells, Russell, Subject: Results of NRC SUNSI Review of Watts Bar Nuclear Plant Dual-Unit UFSAR, Amendment 5 ML23334A0932023-11-28028 November 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise TS Surveillance Requirement 3.9.5.1 to Reduce RHR Flow Rate During Mode 6 ML23319A1662023-11-0202 November 2023 NRR E-mail Capture - Acceptance Review Results for Browns Ferry Nuclear Plant, Sequoyah Nuclear Plant, and Watts Bar Nuclear Plant, Exemption Request Related to 10 CFR 37.11(c)(2) ML23254A2872023-09-11011 September 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise TS Table 1.1-1 Re Number of Required Rvh Closure Bolts ML23236A2562023-08-24024 August 2023 NRR E-mail Capture - Acceptance Review Results for the Sequoyah and Watts Bar License Amendment Request to Adopt TSTF-567 (L-2023-LLA-0106) ML23191A8672023-07-10010 July 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML23166A1142023-06-15015 June 2023 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2023-03 ML23150A2472023-05-25025 May 2023 NRR E-mail Capture - Audit Plan Related to Review of the Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Increase the Number of Tritium Producing Burnable Absorber Rods ML23116A1492023-04-21021 April 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Increase the Number of Tritium Producing Burnable Absorber Rods ML23075A0032023-03-13013 March 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1, 2, and 3, License Amendment Request to Revise TS 3.7.11, Required Actions A.1 and E.1 Footnotes Re Date for the Modification ML23072A0722023-03-10010 March 2023 NRR E-mail Capture - (External_Sender) State Consultation - Sequoyah Nuclear Plant, Units 1 and 2; and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML23067A2372023-03-0808 March 2023 WB_2023-02_RP_inspection_doc_request ML23013A0382023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML23013A0362023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML22356A2982022-12-22022 December 2022 Email Response to Letter, Dated November 22, 2022 Regarding Watts Bar Integrated Inspection Report ML22353A0812022-12-15015 December 2022 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Unit 2, Alternative Request WBN-2-ISI-01 Regarding Examination of Upper Head Injection Nozzle Dissimilar Metal Piping Butt Welds ML22348A0972022-12-14014 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML22348A0442022-12-13013 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22227A0712022-08-15015 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 (EPID L-2022-LLA-0103) - Corrected ML22227A0262022-08-12012 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22215A2752022-08-0303 August 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-554 ML22194A8762022-07-13013 July 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-529 ML22166A4292022-06-0606 June 2022 NRR E-mail Capture - LAR to Adopt TSTF-577 ML22146A3342022-05-25025 May 2022 NRR E-mail Capture - Acceptance Review Results for Browns Ferry Nuclear Plant, Units 1, 2, and 3, Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Relief Requests (EPID L-2022-LLR-0045 - 0047) ML22136A0182022-05-16016 May 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah Nuclear Plant, Units 1 and 2, Alternative Request RP-11 and Watts Bar Nuclear Plant, Units 1 and 2, Alternative Request IST-RR-9 ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to Tva'S Request to Revised the TVA Plants' Radiological Emergency Plans 2024-09-10
[Table view] |
Text
WBN2Public Resource From: Poole, Justin Sent: Monday, July 11, 2011 10:10 AM To: Epperson, Dan Cc: WBN2HearingFile Resource
Subject:
FW: NRC PM Open Items List 7-13-11.docx Attachments: NRC PM Open Items List 7-13-11.docx Justin C. Poole Project Manager NRR/DORL/LPWB U.S. Nuclear Regulatory Commission (301)415-2048 email: Justin.Poole@nrc.gov From: Boyd, Desiree L [1]
Sent: Monday, July 11, 2011 10:01 AM To: Poole, Justin; Milano, Patrick; Campbell, Stephen Cc: Arent, Gordon; Smith, James D; Bryan, Robert H Jr; Smith, James D; Crouch, William D
Subject:
NRC PM Open Items List 7-13-11.docx For next phone call, 7/13/11.
Thank You,
~*~*~*~*~*~*~*~*~*~*~*~
Désireé L. Boyd WBN 2 Licensing Support Sun Technical Services dlboyd@tva.gov 423-365-8764 1
Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 447 Mail Envelope Properties (19D990B45D535548840D1118C451C74D8CB287E5A3)
Subject:
FW: NRC PM Open Items List 7-13-11.docx Sent Date: 7/11/2011 10:10:10 AM Received Date: 7/11/2011 10:10:14 AM From: Poole, Justin Created By: Justin.Poole@nrc.gov Recipients:
"WBN2HearingFile Resource" <WBN2HearingFile.Resource@nrc.gov>
Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov>
Tracking Status: None Post Office: HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 719 7/11/2011 10:10:14 AM NRC PM Open Items List 7-13-11.docx 32097 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
Page 1 of 6 NRC PM Open Items List 7/13/11 (423) 751-6338 ID 657601 No. Description Status Additional Comments Resp Org/Person
- 1. Cyber Security Plan/Controls and NRC TI issued NRC Inspection in 2011 Heinrich/Snyder Implementation TBD (Bryan)
Provide detail for systems (unit specific and common)
NRC Table which will be complete and which will not be complete Top/Pilot for Unit 2 fuel load.
Oct 2011 NRC requested a clarification in a telecom the week of 7/4/11. Need details on exemptions.
Procedures complete 9/30/11 Clarification -
TBD Inspection Dec 2011
Page 2 of 6 No. Description Status Additional Comments Resp Org/Person
- 2. Instrumentation RAI List (Knuettel) 1. 12/24/11 RAI Responses Eng/Hilmes
- 1. Documentation of V&V 2. 8/1/11
- Item 1 consists of 11 individual questions divided (Smith)
- 2. Item 3 for GA-ESI RM-1000 RAD 3. 7/22/11 between Bechtel TVA/GA and WEC. GA date is Monitors. 4. 9/9/11 6 months from contract award.
- 3. Table 7.1-1 first submittal
- Item 2 GA/ESI is revising their CGI program but
- 4. GA proprietary, non-proprietary and needs time to be able to provide objective affidavits for withholding submittals evidence of the program changes. We will order
(~12 documents.) parts to facilitate GA developing objective evidence that their program is in compliance with NRC regulations.
- Item 3 Due to the 12/24 date for GA to complete their review, we will submit the Common Q PAMS Table 7.1-1 update first and follow up with the RM-1000 update later.
- Item 4 - Potential for 3 additional document requests from NRC Civil. Do not anticipate any significant impact to the completion date.
- 3. Resolve Licensing Basis Preservation 6/17/11A TVA to provide QA audit results. Audit is complete. Eng/Freeman Self Assessment PERs (Crouch) Will docket the audit. (Smith)
- 4. Status of GSI 199 Eastern Seismicity Fall 2011 No action pending upcoming Generic Letter TVA/NRR (Crouch)
Page 3 of 6 No. Description Status Additional Comments Resp Org/Person
- 5. Complete Implementation (Hemmer) Diesel Diesel is onsite, need support equipment Hemmer 8/1/11 (Smith)
Pump Additional clarification to Phase I actions will be Relocation needed. Fleet wide issue.
11/1/11 Procedures Issued 6/30/11 -
complete Inspection -
November 2011 Phase I commitments 8/1/11
- 6. Provide feedback on the status of NRC SSER 23 NRC to provide status of review in SSER 23 NRR review of Integrated Safeguards Test complete submittal
- 7. Document Control Issues for two letters 7/15/11 7/15, 10/5, 10/21 and 10/29 letters. NRC to reprint Licensing/Boyd 7/15 letter and provide to NRC Document control.
TVA/Bechtel to provide non-proprietary version of documents that can be released to the public. TVA to provide revised letter that says non-prop once prop documents removed. NRC action to contact Kenny Nguyen, NRC Document Control regarding A102.
Additional copy of A102 provided to NRC on 6/7/11.
Page 4 of 6 No. Description Status Additional Comments Resp Org/Person
- 8. Chapter 15.5 RAIs 8/1/11 Additional question regarding meteorology data from Wastrack 2008-2009. Calc revisions required. TVA formulating (Bryan) plan/schedule. Small increases in doses expected except control room which will decrease. NRC is targeting SSER 24 (early August) to contain this updated information. NRC to perform confirmatory runs in parallel. Will provide data by 6/27/11.
- 9. Fire Protection Report Questions 7/1/11A OMA justifications. ENG/Hilmes regarding OMA (Crouch)
TBD Clarification to OMA justifications 8/15/11 FPR revision 6/30/11A Clarification to 5/26/11 ltr Qs VII-2, VIII-13,14 and 6/7/11 ltr Qs II-43, VIII-17 7/12/11 Technical Meeting 7/29/11 Group 6 rough draft RAIs received via email 6/21/11.
- 10. IST Tech Spec Change 7/31/11 Schedule by 6/17/11. TVA Corporate Pre-submittal meeting week of 7/11/11. Licensing (Shea)
- 11. Tech Spec Revisions from latest T/S 6/20/11A Submittal to address NRC review comments Licensing/Elton markup and NRC Review comments (Bryan)
TBD CSST A & B July, 2011 I-131 DEI July, 2011 Diesel Generator Frequency
- 12. ASME III to XI transition Need NRC When does ISI program begin with partial plant N-3? Eng/Helms Letter Are repairs/mods after N-5 controlled under Section III (Crouch) or Section XI? The timing for the NIS-2 in the letter does not comply with the ASME Code . The NIS-2 must be before commercial operation.
Review Code Cases 801/802 vs TVA letter for conflicts. Review complete - no impact.
Page 5 of 6 No. Description Status Additional Comments Resp Org/Person
- 13. Chapter 11/FSEIS RAIs 6/23/11A NRC Computer Code Input Request Chem/Woods (Bryan) 7/29/11 Cost Benefit Analyses - need to improve date complete NRC to provide additional RAIs
- 14. Letter to notify NRC when Vital Area 11/1/11 Security Plan Update - Boundary to be restored by Lic/Crouch Boundary returned to original location 9/30/11
- 15. Part 70 License EA - 6/13/11A NRC to issue Part 70 license. Fuel receipt is 6/20/11. Milano FL - 6/15/11
- 16. ACRS Topics 7/12/11 Improvements, Inspection status, Refurb status, Construction Status, Japan, IST Re-Presentation, Cyber Security, Ch 7 digital upgrades. Agenda has been finalized.
- 17. SAMDA RAIs 6/24/11A Need a clarifying response.
- 18. SSER 22/23 Open Items Response 7/22/11 7/15 is the target date for the next SSER update. The expanded HH list and its status is covered periodically.
- 19. Chapter 12 RAI on Instrument Channel 6/27/11 Clarification for RMs 50.68(b)(6) ENG/Hilmes Operability Tests 7/15/11 Need to clean up calculation.
- 20. Transient Analysis issues 6/28-30/11 & TVA/WEC confirming availability of personnel. Final ENG/Koontz 7/1/11 until audit plan to come. WEC/Morgan Additional Follow up Audit noon, if necessary 6/21/11A NRC to provide final audit questions. TVA would prefer to have a more specific plan to draw closure.
6/24/11A TVA to provide additional RAI responses/clarification Follow-up items from 6/28 audit 7/29/11 Audit follow-up - send non-SLB items separately
- 21. FSAR A105 7/29/11 Lic/Stockton
Page 6 of 6 No. Description Status Additional Comments Resp Org/Person
- 22. IEB 88-02 SG Tube Cracking NRC to setup What are the SG inspection plans in light of the Corp SG/
telecon experience with a French reactor exhibiting SG tube Webber cracking early? Is TVA planning to change the ISI/Tinley inspection plan due to this operating experience?
- 23. Develop list of planned License 9/1/11 Review Unit 1 SER for exemptions. NRR/TVA Conditions, Exemptions and Relief (Bryan)
Requests (Crouch)
- 24. Submit final REP prior to fuel load 10/1/11 Submit Final REP and EPIPs 180 days prior to OL. EP/
(Spink) Detchemendy (Bryan)
- 25. Issue two Unit Offsite Dose Calculation 9/1/11 Chemistry/
Manual (Beach) Review TS Chapter 5 Woods programs also (Bryan)
- 26. Copy of Site Plan for NSIR TBD No action until inspection scheduled. Fire Ops/Sterchi NRC to determine level of detail is needed.
- 27. Issue Unit 2 Completion Letter (Crouch) 3/1/12 Licensing
- 28. Combined U1/U2 FSAR (Stockton) 3/1/12 Licensing
- 29. Submit final as-constructed FSAR 10/1/11 Licensing/
figures Stockton
- 30. Verify Tech Spec Setpoints match calcs 8/1/11 Eng/Hilmes (Bryan)
- 31. Letter to terminate Part 30/40 License 4/1/12 Licensing after receipt of Part 50 License (Crouch)
- 32. B 2011-01 60 day response Licensing (Gordon)
- 33. TMI action items Review list - include pre-0737 items? Licensing (Gordon)