From:
Hughey, John Sent:
Friday, July 08, 2011 8:10 AM To:
'thomas.loomis@exeloncorp.com'
Subject:
Acceptance Review for Peach Bottom Reactor Anomalies License Amendment Request (TAC No. ME6356/ME6357)
ADAMSAccessionNumber:
ML111890030 By letter dated June 2, 2011, Exelon Generation Company, LLC submitted a license amendment request (LAR) for Peach Bottom Atomic Power Station (PBAPS), Units 2 and 3, proposing to amend the PBAPS, Units 2 and 3, Technical Specifications (TS) to modify TS Section 3.1.2, Reactor Anomalies. The proposed amendment concerns a change to the method of calculating core reactivity for the purpose performing the reactivity anomaly surveillance at PBAPS, Units 2 and 3.
The purpose of this email is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed license amendment in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the NRC staff to complete its technical review, you will be advised by separate correspondence.
John Hughey Peach Bottom Project Manager NRR / Division of Operating Reactor Licensing Phone: 301-415-3204 e-mail: John.Hughey@nrc.gov