ML111741385

From kanterella
Jump to navigation Jump to search
IR 05000458-11-006, on April 25 Through May 12, 2011, River Bend Station, Biennial Baseline Inspection of the Identification and Resolution of Problems, Identification and Resolution
ML111741385
Person / Time
Site: River Bend Entergy icon.png
Issue date: 06/23/2011
From: Hay M
Division of Reactor Safety IV
To: Olson E
Entergy Operations
References
IR-11-006
Download: ML111741385 (27)


See also: IR 05000458/2011006

Text

Mr. Eric W. Olson

Site Vice President

Entergy Operations, Inc.

River Bend Station

5485 US Highway 61

St Francisville, LA 70775

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REG!ON IV

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

June 23, 2011

SUBJECT:

RiVER BEND STATION - NRC PROBLEM IDENTiFICATION AND

RESOLUTION INSPECTION REPORT 05000458/2011006

Dear Mr. Olson,

On May 12, 2011, the U. S. Nuclear Regulatory Commission (NRC) completed a team

inspection at your River Bend Station. The enclosed report documents the inspection findings,

as discussed on May 12, 2011, with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to identification

and resolution of problems, safety and compliance with the Commission's rules and regulations

and with the conditions of your operating license. The team reviewed selected procedures and

records, observed activities, and interviewed personnel. The team also interviewed a

representative sample of personnel regarding the condition of your safety conscious work

environment.

This report documents one self-revealing violation of very low safety significance (Green). This

finding was determined to involve a violation of NRC requirements. Additionally, one licensee-

identified violation, which was determined to be of very low safety significance, is listed in this

report. However, because of the very low safety significance of the violation and because it was

entered into your corrective action program, the NRC is treating this violation as a noncited

violation consistent with Section VI. A. 1 of the NRC Enforcement Policy. If you contest this

noncited violation, you should provide a response within 30 days of the date of this inspection

report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document

Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, U.S.

Nuclear Regulatory Commission, Region IV, 612 E. Lamar Blvd., Suite 400, Arlington,

Texas, 76011-4125; the Director, Office of Enforcement, United States Nuclear Regulatory

Commission, Washington DC 20555-0001; and the NRC Resident Inspector at River Bend

Station. In additionf jf you disagree 'va,/jth the chaiacterization of any finding in this report, you

should provide a response within 30 days of the date of this inspection report, with the basis for

your disagreement, to the Regional Administrator, Region IV, and the NRC Resident Inspector

at River Bend Station. The information you provide will be considered in accordance with

Inspection Manual Chapter 0305.

Mr. Eric W. Olson

Site Vice President

Entergy Operations, Inc.

River Bend Station

5485 US Highway 61

St Francisville, LA 70775

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REG!ON IV

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

June 23, 2011

SUBJECT:

RiVER BEND STATION - NRC PROBLEM IDENTiFICATION AND

RESOLUTION INSPECTION REPORT 05000458/2011006

Dear Mr. Olson,

On May 12, 2011, the U. S. Nuclear Regulatory Commission (NRC) completed a team

inspection at your River Bend Station. The enclosed report documents the inspection findings,

as discussed on May 12, 2011, with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to identification

and resolution of problems, safety and compliance with the Commission's rules and regulations

and with the conditions of your operating license. The team reviewed selected procedures and

records, observed activities, and interviewed personnel. The team also interviewed a

representative sample of personnel regarding the condition of your safety conscious work

environment.

This report documents one self-revealing violation of very low safety significance (Green). This

finding was determined to involve a violation of NRC requirements. Additionally, one licensee-

identified violation, which was determined to be of very low safety significance, is listed in this

report. However, because of the very low safety significance of the violation and because it was

entered into your corrective action program, the NRC is treating this violation as a noncited

violation consistent with Section VI. A. 1 of the NRC Enforcement Policy. If you contest this

noncited violation, you should provide a response within 30 days of the date of this inspection

report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document

Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, U.S.

Nuclear Regulatory Commission, Region IV, 612 E. Lamar Blvd., Suite 400, Arlington,

Texas, 76011-4125; the Director, Office of Enforcement, United States Nuclear Regulatory

Commission, Washington DC 20555-0001; and the NRC Resident Inspector at River Bend

Station. In additionf jf you disagree 'va,/jth the chaiacterization of any finding in this report, you

should provide a response within 30 days of the date of this inspection report, with the basis for

your disagreement, to the Regional Administrator, Region IV, and the NRC Resident Inspector

at River Bend Station. The information you provide will be considered in accordance with

Inspection Manual Chapter 0305.

Entergy Operations, Inc.

- 2 -

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records component of NRC's

document system (ADAMS). ADAMS is accessible from the NRC Web-site at

www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room).

Docket: 50-458

License: NPF-47

Sincerely,

Michael Hay, Chief

Technical Support Branch

Division of Reactor Safety

Enclosure: Inspection Report 05000458/20110006

w/Attachments:

Attachment A, Supplemental Information

Attachment 8, Information Request - February 16, 2011

cc: w/Enclosure:

Distribution via Ustserv

Entergy Operations, Inc.

- 2 -

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records component of NRC's

document system (ADAMS). ADAMS is accessible from the NRC Web-site at

www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room).

Docket: 50-458

License: NPF-47

Sincerely,

Michael Hay, Chief

Technical Support Branch

Division of Reactor Safety

Enclosure: Inspection Report 05000458/20110006

w/Attachments:

Attachment A, Supplemental Information

Attachment 8, Information Request - February 16, 2011

cc: w/Enclosure:

Distribution via Ustserv

Docket:

License:

Report:

Licensee:

Facility:

Location:

Dates:

Team Leader:

Inspectors:

Approved By:

u.s. NUCLEAR REGULATORY COMMISSION

REGION IV

05000458

NPF-47

05000458/2011006

Entergy Operations, Inc.

River Bend Station

24 miles NNW of Baton Rouge, Louisiana

April 25 through May 12, 2011

Robert C. Hagar, Senior Project Engineer

Jeremy Groom, Resident Inspector

Andy J. Barrett, Resident Inspector

Gabriel W. Apger, Operations Examiner

Michael Hay, Chief

Technical Support Branch

Division of Reactor Safety

- 1 -

Enclosure

Docket:

License:

Report:

Licensee:

Facility:

Location:

Dates:

Team Leader:

Inspectors:

Approved By:

u.s. NUCLEAR REGULATORY COMMISSION

REGION IV

05000458

NPF-47

05000458/2011006

Entergy Operations, Inc.

River Bend Station

24 miles NNW of Baton Rouge, Louisiana

April 25 through May 12, 2011

Robert C. Hagar, Senior Project Engineer

Jeremy Groom, Resident Inspector

Andy J. Barrett, Resident Inspector

Gabriel W. Apger, Operations Examiner

Michael Hay, Chief

Technical Support Branch

Division of Reactor Safety

- 1 -

Enclosure

SUMMARY OF FINDINGS

IR 05000458/2011006; April 25 through May 12, 2011; River Bend Station, Biennial Baseline

Inspection of the Identification and Resolution of Problems, Problem Identification and

Resolution

The inspection was performed by a regional senior project engineer, a regional operator

examiner, and two resident inspectors. One noncited violation of very !o\\N significance was

identified during this inspection. Additionally, one licensee-identified finding of very low safety

significance is documented in this report. The significance of most findings is indicated by their

color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609, "Significance

Determination Process." The cross-cutting aspect is determined using Inspection Manual

Chapter 0310, "Components Within the Cross Cutting Areas." Findings for which the

significance determination process does not apply may be Green or be assigned a severity level

after NRC management review. The NRC's program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process,"

Revision 4, dated December 2006.

Identification and Resolution of Problems

The team reviewed approximately 500 condition reports, work orders, engineering evaluations,

root and apparent cause evaluations, and other supporting documentation to determine if

problems were being properly identified, characterized, and entered into the corrective action

program for evaluation and resolution. The team reviewed a sample of system health reports,

self-assessments, trending reports and metrics, and various other documents related to the

corrective action program. Overall, the team determined that the licensee's program for

identifying, prioritizing, and correcting conditions adverse to quality was effective. With few

exceptions, the licensee identified conditions adverse to quality at a low threshold, properly

classified and evaluated those conditions, and developed appropriate corrective actions.

The licensee appropriately evaluated industry operating experience for relevance to the facility

and had entered applicable items in the corrective action program. The licensee used industry

operating experience when performing root cause and apparent cause evaluations. In addition,

the licensee performed effective quality assurance audits and self-assessments, as

demonstrated by self-identification of poor corrective action program performance and

identification of ineffective corrective actions.

A.

NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

Green. The inspectors reviewed a self-revealing green noncited violation of

10 CFR 50, Appendix B, Criterion XVI, "Corrective Actions," for the licensee's

failure to take corrective action to address service-induced failures of Gould

J-series relays. In response, the licensee initiated condition report

CR-RBS-20 10-06032 to ensure that appropriate levels of preventive

maintenance are performed on high-critical components.

- 2-

Enclosure

SUMMARY OF FINDINGS

IR 05000458/2011006; April 25 through May 12, 2011; River Bend Station, Biennial Baseline

Inspection of the Identification and Resolution of Problems, Problem Identification and

Resolution

The inspection was performed by a regional senior project engineer, a regional operator

examiner, and two resident inspectors. One noncited violation of very !o\\N significance was

identified during this inspection. Additionally, one licensee-identified finding of very low safety

significance is documented in this report. The significance of most findings is indicated by their

color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609, "Significance

Determination Process." The cross-cutting aspect is determined using Inspection Manual

Chapter 0310, "Components Within the Cross Cutting Areas." Findings for which the

significance determination process does not apply may be Green or be assigned a severity level

after NRC management review. The NRC's program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process,"

Revision 4, dated December 2006.

Identification and Resolution of Problems

The team reviewed approximately 500 condition reports, work orders, engineering evaluations,

root and apparent cause evaluations, and other supporting documentation to determine if

problems were being properly identified, characterized, and entered into the corrective action

program for evaluation and resolution. The team reviewed a sample of system health reports,

self-assessments, trending reports and metrics, and various other documents related to the

corrective action program. Overall, the team determined that the licensee's program for

identifying, prioritizing, and correcting conditions adverse to quality was effective. With few

exceptions, the licensee identified conditions adverse to quality at a low threshold, properly

classified and evaluated those conditions, and developed appropriate corrective actions.

The licensee appropriately evaluated industry operating experience for relevance to the facility

and had entered applicable items in the corrective action program. The licensee used industry

operating experience when performing root cause and apparent cause evaluations. In addition,

the licensee performed effective quality assurance audits and self-assessments, as

demonstrated by self-identification of poor corrective action program performance and

identification of ineffective corrective actions.

A.

NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

Green. The inspectors reviewed a self-revealing green noncited violation of

10 CFR 50, Appendix B, Criterion XVI, "Corrective Actions," for the licensee's

failure to take corrective action to address service-induced failures of Gould

J-series relays. In response, the licensee initiated condition report

CR-RBS-20 10-06032 to ensure that appropriate levels of preventive

maintenance are performed on high-critical components.

- 2-

Enclosure

The performance deficiency was the licensee's failure to take adequate

corrective actions to address service-induced failures of the high-critical, high-

duty-cycle Gould J-series relay designated as EHS-MCC16B6D-33X1. This

performance deficiency was determined to be more than minor and was

therefore a finding because it impacted the Mitigating Systems Cornerstone

attribute of equipment performance and affected the cornerstone objective to

ensure the availability, reliability, and capability of systems that respond to

initiating events to prevent undesirable consequences. This finding had very iow

safety significance because the finding was not a design or qualification

deficiency confirmed not to result in a loss of operability, did not represent a loss

of system safety function, did not represent a loss of safety function for a single

train for greater than its technical specification allowed outage time, and did not

screen as potentially risk significant due to a seismic, flooding or severe weather

initiating event. Because the apparent cause of this finding was the licensee's

misclassification of the failed relay within the preventive maintenance

optimization program in 2008, and because the licensee's performance in that

program was not reflective of current licensee performance, no cross-cutting

aspect was assigned to this finding (Section 40A2.5).

B.

Licensee-Identified Violations

One violation of very low safety significance, which was identified by the licensee, has

been reviewed by the inspectors. Corrective actions taken or planned by the licensee

have been entered into the licensee's corrective action program. This violation and

corrective action tracking number (condition report number) are listed in Section 40A7.

- 3 -

Enclosure

The performance deficiency was the licensee's failure to take adequate

corrective actions to address service-induced failures of the high-critical, high-

duty-cycle Gould J-series relay designated as EHS-MCC16B6D-33X1. This

performance deficiency was determined to be more than minor and was

therefore a finding because it impacted the Mitigating Systems Cornerstone

attribute of equipment performance and affected the cornerstone objective to

ensure the availability, reliability, and capability of systems that respond to

initiating events to prevent undesirable consequences. This finding had very iow

safety significance because the finding was not a design or qualification

deficiency confirmed not to result in a loss of operability, did not represent a loss

of system safety function, did not represent a loss of safety function for a single

train for greater than its technical specification allowed outage time, and did not

screen as potentially risk significant due to a seismic, flooding or severe weather

initiating event. Because the apparent cause of this finding was the licensee's

misclassification of the failed relay within the preventive maintenance

optimization program in 2008, and because the licensee's performance in that

program was not reflective of current licensee performance, no cross-cutting

aspect was assigned to this finding (Section 40A2.5).

B.

Licensee-Identified Violations

One violation of very low safety significance, which was identified by the licensee, has

been reviewed by the inspectors. Corrective actions taken or planned by the licensee

have been entered into the licensee's corrective action program. This violation and

corrective action tracking number (condition report number) are listed in Section 40A7.

- 3 -

Enclosure

REPORT DETAilS

4.

OTHER ACTIVITIES (OA)

40A2 Problem Identification and Resolution (71152)

The team based the following conclusions on the sample of corrective action documents

that were initiated in the assessment period, which ranged from July 10, 2009, to the end

of the on-site portion of this inspection on May 12, 2011 .

. 1

Assessment of the Corrective Action Program Effectiveness

a.

Inspection Scope

The team reviewed approximately 500 root and apparent cause evaluations, work

orders, engineering evaluations, and other supporting documentation, from

approximately 15,000 that had been issued between July 10, 2009, to May 12, 2011, to

determine if problems were being properly identified, characterized, and entered into the

corrective action program for evaluation and resolution. The team also reviewed a

sample of system health reports, operability determinations, self-assessments, trending

reports and metrics, and various other documents related to the corrective action

program. The team evaluated the licensee's efforts in establishing the scope of

problems by reviewing selected logs, work requests, self-assessment reports, audit

reports, system health reports, action plans, and results from surveillance tests and

preventive maintenance tasks. A team member reviewed work requests and attended

the licensee's periodic Condition Review Group and the management review committee

meetings to assess the reporting threshold, prioritization efforts, and significance

determination process, as well as observing the interfaces with the operability

assessment and work control processes when applicable. The team's review included

verifying the licensee considered the full extent of cause and extent of condition for

problems, as well as how the licensee assessed generic implications and previous

occurrences. The team assessed the timeliness and effectiveness of corrective actions,

completed or planned, and looked for additional examples of similar problems. The team

conducted interviews with plant personnel to identify other processes that may exist

where problems may be identified and addressed outside the corrective action program.

The team also reviewed corrective action documents that addressed past NRC-identified

violations to verify that the corrective action addressed the issues as described in the

inspection reports. The inspectors reviewed a sample of corrective actions closed to

other corrective action documents to verify that corrective actions were still appropriate

and timely.

The team considered risk insights from both the NRC's and River Bend Station's risk

assessments to focus the sample selection and plant tours on risk significant systems

and components. The team selected their samples from issues that involved the

following risk-significant systems:

-4-

Enclosure

REPORT DETAilS

4.

OTHER ACTIVITIES (OA)

40A2 Problem Identification and Resolution (71152)

The team based the following conclusions on the sample of corrective action documents

that were initiated in the assessment period, which ranged from July 10, 2009, to the end

of the on-site portion of this inspection on May 12, 2011 .

. 1

Assessment of the Corrective Action Program Effectiveness

a.

Inspection Scope

The team reviewed approximately 500 root and apparent cause evaluations, work

orders, engineering evaluations, and other supporting documentation, from

approximately 15,000 that had been issued between July 10, 2009, to May 12, 2011, to

determine if problems were being properly identified, characterized, and entered into the

corrective action program for evaluation and resolution. The team also reviewed a

sample of system health reports, operability determinations, self-assessments, trending

reports and metrics, and various other documents related to the corrective action

program. The team evaluated the licensee's efforts in establishing the scope of

problems by reviewing selected logs, work requests, self-assessment reports, audit

reports, system health reports, action plans, and results from surveillance tests and

preventive maintenance tasks. A team member reviewed work requests and attended

the licensee's periodic Condition Review Group and the management review committee

meetings to assess the reporting threshold, prioritization efforts, and significance

determination process, as well as observing the interfaces with the operability

assessment and work control processes when applicable. The team's review included

verifying the licensee considered the full extent of cause and extent of condition for

problems, as well as how the licensee assessed generic implications and previous

occurrences. The team assessed the timeliness and effectiveness of corrective actions,

completed or planned, and looked for additional examples of similar problems. The team

conducted interviews with plant personnel to identify other processes that may exist

where problems may be identified and addressed outside the corrective action program.

The team also reviewed corrective action documents that addressed past NRC-identified

violations to verify that the corrective action addressed the issues as described in the

inspection reports. The inspectors reviewed a sample of corrective actions closed to

other corrective action documents to verify that corrective actions were still appropriate

and timely.

The team considered risk insights from both the NRC's and River Bend Station's risk

assessments to focus the sample selection and plant tours on risk significant systems

and components. The team selected their samples from issues that involved the

following risk-significant systems:

-4-

Enclosure

Reactor Protection System

Standby Service Water

Emergency 480 Volts AC

Normal Service Water

Division 1 and Division 2 Diesel Generators

125 Volts DC

High Pressure Core Spray

Turbine Plant Component Cooling

Reactor Core Isolation Cooling

Normal 128 kVolts AC

120 VAC

Instrument Air

Diesel Room Ventilation

Division 3 Diesel

Division 1 and Division 2 4160 Volts AC

Safety Relief Valves

Auxiliary Building Ventilation

Service Water Cooling

Residual Heat Removal

Fire Protection Water

230 KV Power

Division 3 4160 Volts AC

Reactor Pressure Vessel Level Instrumentation

Feedwater

To assess whether selected problems had been effectively addressed, the team also

expanded their review to include five years of evaluations involving Gould J1 0 electrical

relays and recirculation pump seal leakage.

To assess whether problems had been identified and entered into the corrective action

program, the team conducted a walkdown of Station Service Water and Emergency

Diesel Generator systems.

b.

Assessments

1.

Assessment - Effectiveness of Problem Identification

The team concluded that, generally, the licensee had correctly identified deficiencies that

were conditions adverse to quality and had entered those conditions into their corrective

action program in accordance with the licensee's corrective action program guidance

and NRC requirements. The team determined that the licensee had identified problems

at a low threshold. Also, the team found no indication of processes where problems may

be identified and addressed outside the corrective action program. However, the team

made the following observations about the effectiveness of licensee problem

identification:

II

For the existence of water inside vaults associated with cables within the scope

of 10 CFR 50.65, the licensee had not initiated a condition report. This issue was

entered into the corrective action program as CR-HQN-2011-0491.

- 5 -

Enclosure

Reactor Protection System

Standby Service Water

Emergency 480 Volts AC

Normal Service Water

Division 1 and Division 2 Diesel Generators

125 Volts DC

High Pressure Core Spray

Turbine Plant Component Cooling

Reactor Core Isolation Cooling

Normal 128 kVolts AC

120 VAC

Instrument Air

Diesel Room Ventilation

Division 3 Diesel

Division 1 and Division 2 4160 Volts AC

Safety Relief Valves

Auxiliary Building Ventilation

Service Water Cooling

Residual Heat Removal

Fire Protection Water

230 KV Power

Division 3 4160 Volts AC

Reactor Pressure Vessel Level Instrumentation

Feedwater

To assess whether selected problems had been effectively addressed, the team also

expanded their review to include five years of evaluations involving Gould J1 0 electrical

relays and recirculation pump seal leakage.

To assess whether problems had been identified and entered into the corrective action

program, the team conducted a walkdown of Station Service Water and Emergency

Diesel Generator systems.

b.

Assessments

1.

Assessment - Effectiveness of Problem Identification

The team concluded that, generally, the licensee had correctly identified deficiencies that

were conditions adverse to quality and had entered those conditions into their corrective

action program in accordance with the licensee's corrective action program guidance

and NRC requirements. The team determined that the licensee had identified problems

at a low threshold. Also, the team found no indication of processes where problems may

be identified and addressed outside the corrective action program. However, the team

made the following observations about the effectiveness of licensee problem

identification:

II

For the existence of water inside vaults associated with cables within the scope

of 10 CFR 50.65, the licensee had not initiated a condition report. This issue was

entered into the corrective action program as CR-HQN-2011-0491.

- 5 -

Enclosure

When the licensee conducts "tabletop" training sessions before they conduct

emergency drills, and then addresses performance-related weaknesses or issues

through coaching and mentoring without initiating corresponding condition

reports, they miss opportunities to use their corrective action program to identify

possible trends in those weaknesses and issues, and to develop possible

improvements in associated training programs to address those trends. This

issue was entered into the corrective action program as CR-RBS-2011-040S1.

e

In the same sample of ten measuring and test equipment nonconformance

reports, the inspectors found five reports for which the licensee had not

completed an independent review, even though those reports involved

circumstances that, according to licensee procedures, warranted an independent

review. This issue was entered into the corrective action program as

CR-RBS-2011-4055.

"

Prior to this inspection, the licensee had not identified that instructions in

Procedure ADM-0029, "Control of Measuring and Test Equipment (M&TE) and

the Tool Room Process," Step 10.2.1, for dispositioning measuring and test

equipment nonconformance reports were not consistent with similar instructions

in Step 5.7.4 [4] of fleet Procedure EN-MA-105, "Control of Measuring and Test

Equipment (M&TE)." This issue was entered into the corrective action program

as CR-RBS-2011-4055.

"

For six status items in the radiation protection logs that warranted initiation of a

condition report according to licensee procedures, the licensee had not initiated

corresponding condition reports. This issue was entered into the corrective

action program as CR-RBS-2011-03961.

2.

Assessment - Effectiveness of Prioritization and Evaluation of Issues

The licensee generally had performed adequate assessments of conditions adverse to

quality during this assessment period. The team noted that the immediate and prompt

operability assessments reviewed had been completed in a timely manner, except as

noted below. For this assessment, the team made the following related observations:

"

Although the condition described in CR-RBS-201 0-04526 warranted

classification as a Category A condition for which a root cause evaluation would

be performed, the licensee classified that condition in Category B and completed

an apparent-cause evaluation. This condition report did not include the

licensee's basis for claSSifying that condition in Category B rather than

Category A. This issue was entered into the corrective action program as

CR-RBS-2011-04132.

"

For the condition described in CR-RBS-201 0-05224, the leak rate determined by

the licensee's apparent cause evaluation (a "pencil-sized stream") vilas not

consistent with the leak rate that had been used in the jicensee's reportability

evaluation (30 drops/minute). According to the licensee's procedures, the

licensee should have initiated a new condition report to document that new

- 6 -

Enclosure

When the licensee conducts "tabletop" training sessions before they conduct

emergency drills, and then addresses performance-related weaknesses or issues

through coaching and mentoring without initiating corresponding condition

reports, they miss opportunities to use their corrective action program to identify

possible trends in those weaknesses and issues, and to develop possible

improvements in associated training programs to address those trends. This

issue was entered into the corrective action program as CR-RBS-2011-040S1.

e

In the same sample of ten measuring and test equipment nonconformance

reports, the inspectors found five reports for which the licensee had not

completed an independent review, even though those reports involved

circumstances that, according to licensee procedures, warranted an independent

review. This issue was entered into the corrective action program as

CR-RBS-2011-4055.

"

Prior to this inspection, the licensee had not identified that instructions in

Procedure ADM-0029, "Control of Measuring and Test Equipment (M&TE) and

the Tool Room Process," Step 10.2.1, for dispositioning measuring and test

equipment nonconformance reports were not consistent with similar instructions

in Step 5.7.4 [4] of fleet Procedure EN-MA-105, "Control of Measuring and Test

Equipment (M&TE)." This issue was entered into the corrective action program

as CR-RBS-2011-4055.

"

For six status items in the radiation protection logs that warranted initiation of a

condition report according to licensee procedures, the licensee had not initiated

corresponding condition reports. This issue was entered into the corrective

action program as CR-RBS-2011-03961.

2.

Assessment - Effectiveness of Prioritization and Evaluation of Issues

The licensee generally had performed adequate assessments of conditions adverse to

quality during this assessment period. The team noted that the immediate and prompt

operability assessments reviewed had been completed in a timely manner, except as

noted below. For this assessment, the team made the following related observations:

"

Although the condition described in CR-RBS-201 0-04526 warranted

classification as a Category A condition for which a root cause evaluation would

be performed, the licensee classified that condition in Category B and completed

an apparent-cause evaluation. This condition report did not include the

licensee's basis for claSSifying that condition in Category B rather than

Category A. This issue was entered into the corrective action program as

CR-RBS-2011-04132.

"

For the condition described in CR-RBS-201 0-05224, the leak rate determined by

the licensee's apparent cause evaluation (a "pencil-sized stream") vilas not

consistent with the leak rate that had been used in the jicensee's reportability

evaluation (30 drops/minute). According to the licensee's procedures, the

licensee should have initiated a new condition report to document that new

- 6 -

Enclosure

information had made the reportability evaluation questionable. However, the

licensee did not initiate that condition report. This issue was entered into the

corrective action program as CR-RBS-2011-03834.

..

For the condition described in CR-RBS-201 0-05088 (a heater in a ventilation

system not delivering an adequate amount of power), the licensee's reportability

evaluation was incomplete, in that the evaluation had concluded that oscillations

in heater power were normal, but had failed to consider the low-power condition

of the heater. Subsequent analysis demonstrated that the low-power condition

had not been reportable. This issue was entered into the licensee's corrective

action program as CR-RBS-2011-03786.

..

The operability evaluation in CR-RBS-201 0-01717 was incomplete, in that the

licensee had addressed a small oil leak in the reactor core isolation cooling pump

by determining that the leak rate with the pump not running was low enough that

pump operability would not have been affected, but had not evaluated the leak

rate with the pump operating. A subsequent evaluation determined that the leak

rate with the pump operating did not affect operability of the pump. This issue

was entered into the licensee's corrective action program as

CR-RBS-20 11-3854.

..

According to licensee procedures, the condition in CR-RBS-2009-03080

(repetitive maintenance items and adverse trends in nuisance alarms from the

fire protection computer) warranted classification as a Category C condition,

which would have required action to correct the condition. However, the licensee

classified the condition as Category 0, which required only trending the condition

with no action to correct it. This condition report did not include the licensee's

basis for classifying that condition in Category 0 rather than Category C. This

issue was entered into the corrective action program as CR-RBS-201104131.

For the condition described in CR-RBS-2008-04711 (inadvertent distribution of

radioactive materials foilowing automatic initiation of the standby-gas treatment

system), the licensee's evaluation had been incomplete, in that the licensee had

failed to consider a previous evaluation that had determined that installing sock

filters on certain drain lines would not be acceptable during surveillance testing.

As a result, the corrective actions developed in CR-RBS-2008-04711 had

included installing sock filters on those drain lines to prevent further

contamination, and those sock filters had remained on the drain lines during two

recent surveillance tests. The licensee's subsequent evaluation determined that

installation of the sock filters had not invalidated the surveillance test results.

This issue was entered into the corrective action program as

CR-RBS-2011-03818.

3.

Assessment -- Effectiveness of Corrective Action Program

Overall. the team concluded that the licensee had generally deve!oped appropriate

corrective actions to address piOblems. However, the team identified the following two

examples of conditions adverse to quality where the licensee had failed to identify or

take appropriate corrective action:

- 7 -

Enclosure

information had made the reportability evaluation questionable. However, the

licensee did not initiate that condition report. This issue was entered into the

corrective action program as CR-RBS-2011-03834.

..

For the condition described in CR-RBS-201 0-05088 (a heater in a ventilation

system not delivering an adequate amount of power), the licensee's reportability

evaluation was incomplete, in that the evaluation had concluded that oscillations

in heater power were normal, but had failed to consider the low-power condition

of the heater. Subsequent analysis demonstrated that the low-power condition

had not been reportable. This issue was entered into the licensee's corrective

action program as CR-RBS-2011-03786.

..

The operability evaluation in CR-RBS-201 0-01717 was incomplete, in that the

licensee had addressed a small oil leak in the reactor core isolation cooling pump

by determining that the leak rate with the pump not running was low enough that

pump operability would not have been affected, but had not evaluated the leak

rate with the pump operating. A subsequent evaluation determined that the leak

rate with the pump operating did not affect operability of the pump. This issue

was entered into the licensee's corrective action program as

CR-RBS-20 11-3854.

..

According to licensee procedures, the condition in CR-RBS-2009-03080

(repetitive maintenance items and adverse trends in nuisance alarms from the

fire protection computer) warranted classification as a Category C condition,

which would have required action to correct the condition. However, the licensee

classified the condition as Category 0, which required only trending the condition

with no action to correct it. This condition report did not include the licensee's

basis for classifying that condition in Category 0 rather than Category C. This

issue was entered into the corrective action program as CR-RBS-201104131.

For the condition described in CR-RBS-2008-04711 (inadvertent distribution of

radioactive materials foilowing automatic initiation of the standby-gas treatment

system), the licensee's evaluation had been incomplete, in that the licensee had

failed to consider a previous evaluation that had determined that installing sock

filters on certain drain lines would not be acceptable during surveillance testing.

As a result, the corrective actions developed in CR-RBS-2008-04711 had

included installing sock filters on those drain lines to prevent further

contamination, and those sock filters had remained on the drain lines during two

recent surveillance tests. The licensee's subsequent evaluation determined that

installation of the sock filters had not invalidated the surveillance test results.

This issue was entered into the corrective action program as

CR-RBS-2011-03818.

3.

Assessment -- Effectiveness of Corrective Action Program

Overall. the team concluded that the licensee had generally deve!oped appropriate

corrective actions to address piOblems. However, the team identified the following two

examples of conditions adverse to quality where the licensee had failed to identify or

take appropriate corrective action:

- 7 -

Enclosure

Condition report CR-RBS-2010-02476 identified that corrective actions

associated with CR-RBS-201 0-01587 had been delayed because they had

incorrectly been closed to a global preventive maintenance task that was later

closed. This issue was entered into the licensee's corrective action program as

CR-RBS-2011-04097.

to

The licensee developed CR-RBS-2010-02362 corrective action #14 to implement

a vendor recommendation to install capacitors to reduce "chattering" of certain

relays in circuits associated with oil heaters of the control building chillers, and

thereby improve the reliability of those relays. However, the licensee

inappropriately closed that corrective action to a system health report, and, as a

result, did not implement that recommendation. This issue was entered into the

corrective action program as CR-RBS-2011-04208 .

. 2

Assessment of the Use of Operating Experience

a.

Inspection Scope

The team examined the licensee's program for reviewing industry operating experience,

including reviewing the governing procedure and self assessments. The team reviewed

a sample operating experience notifications that had been issued during the assessment

period to assess whether the licensee had appropriately evaluated the notifications for

relevance to the facility. The team then examined whether the licensee had entered

those items into their corrective action program and assigned actions to address the

issues. The team reviewed a sample of root cause evaluations and corrective action

documents to verify if the licensee had appropriately included industry-operating

experience.

b.

Assessment

Overall, the team determined that the iicensee was adequately evaluating industry

operating experience for relevance to the facility, based on reviewing a sample size of

17 industry operating experience notifications. The team concluded that the licensee

was evaluating industry operating experience when performing root cause and apparent

cause evaluations. Both internal and external operating experience were being

incorporated into lessons learned for training and pre-job briefs .

. 3

Assessment of Self-Assessments and Audits

a.

Inspection Scope

The team reviewed a sample size of 83 licensee self-assessments, surveillances, and

audits to assess whether the licensee was regularly identifying performance trends and

effectively addressing them. The team reviewed audit reports to assess the

effectiveness of assessments in specific areas. The team evaluated the use of self- and

third party assessments, the role of the quality assurance department, and the role of the

performance improvement group related to licensee performance. The specific self-

assessment documents reviewed are listed in the attachment.

- 8 -

Enclosure

Condition report CR-RBS-2010-02476 identified that corrective actions

associated with CR-RBS-201 0-01587 had been delayed because they had

incorrectly been closed to a global preventive maintenance task that was later

closed. This issue was entered into the licensee's corrective action program as

CR-RBS-2011-04097.

to

The licensee developed CR-RBS-2010-02362 corrective action #14 to implement

a vendor recommendation to install capacitors to reduce "chattering" of certain

relays in circuits associated with oil heaters of the control building chillers, and

thereby improve the reliability of those relays. However, the licensee

inappropriately closed that corrective action to a system health report, and, as a

result, did not implement that recommendation. This issue was entered into the

corrective action program as CR-RBS-2011-04208 .

. 2

Assessment of the Use of Operating Experience

a.

Inspection Scope

The team examined the licensee's program for reviewing industry operating experience,

including reviewing the governing procedure and self assessments. The team reviewed

a sample operating experience notifications that had been issued during the assessment

period to assess whether the licensee had appropriately evaluated the notifications for

relevance to the facility. The team then examined whether the licensee had entered

those items into their corrective action program and assigned actions to address the

issues. The team reviewed a sample of root cause evaluations and corrective action

documents to verify if the licensee had appropriately included industry-operating

experience.

b.

Assessment

Overall, the team determined that the iicensee was adequately evaluating industry

operating experience for relevance to the facility, based on reviewing a sample size of

17 industry operating experience notifications. The team concluded that the licensee

was evaluating industry operating experience when performing root cause and apparent

cause evaluations. Both internal and external operating experience were being

incorporated into lessons learned for training and pre-job briefs .

. 3

Assessment of Self-Assessments and Audits

a.

Inspection Scope

The team reviewed a sample size of 83 licensee self-assessments, surveillances, and

audits to assess whether the licensee was regularly identifying performance trends and

effectively addressing them. The team reviewed audit reports to assess the

effectiveness of assessments in specific areas. The team evaluated the use of self- and

third party assessments, the role of the quality assurance department, and the role of the

performance improvement group related to licensee performance. The specific self-

assessment documents reviewed are listed in the attachment.

- 8 -

Enclosure

b.

Assessment

The team concluded that the licensee had an adequate self-assessment process .

. 4

Assessment of Safety~Conscious Work Environment

a.

Inspection Scope

The inspection team conducted informal individual interviews with 23 individuals. The

interviewees represented various functional organizations and ranged across contractor,

staff, and supervisor levels. The team conducted these interviews to assess whether

conditions existed that would challenge the establishment of a safety conscious work

environment at the River Bend Station.

b.

Assessment

Because the team encountered no indication of an issue related to the safety conscious

work environment during their interviews with site personnel, the team concluded that

the licensee had maintained a safety conscious work environment.

.5

Specific Issues identified During this Inspection

Failure to Take Corrective Action for Service-Induced Failures of Gould J-series Relays

Introduction. The inspectors reviewed a self-revealing green noncited violation of

10 CFR Part 50, Appendix B, Criterion XVI, "Corrective Actions," for the licensee's failure

to take corrective action to address service-induced failures of Gould J-series relays.

Description. On October 9,2008, River Bend Station personnel initiated

CR-RBS-2008-05915 to document that valve SWP-MOV4B, standby service water to

drywell unit coolers, had failed in the open position. That valve supplies service water to

the drywell unit coolers and has a safety function to close during a loss-of-coolant

accident. A lower-tier apparent-cause evaluation performed by the licensee had

determined that the valve had failed due to a coil failure for relay EHS-MCC2B-5A-33X.

The licensee had also determined that the relay had failed because it had been in

service beyond its expected lifetime. The River Bend preventive maintenance template

for Gould J10 control relays had established a replacement interval based on not

exceeding the expect service life for the given service conditions. (For relays the

licensee had classified as high-critical, high-duty-cycle, they had established a 21-year

replacement period.) To address extent-of-condition concerns, the licensee had

implemented a replacement project for Gould relays deSignated as high-duty-cycle, high-

critical. Corrective Action 7 to CR-RBS-2008-05915 had established work orders for

127 relays classified as high-duty-cycle, high-critical. Based on work orders that had

been generated, the licensee closed CR-RBS-2008-05915 on November 26, 2008. By

July 2009, the licensee had completed work to replace the relays they had classified as

high-duty-cyc1e, high-cf!t!caL

- 9 -

Enclosure

b.

Assessment

The team concluded that the licensee had an adequate self-assessment process .

. 4

Assessment of Safety~Conscious Work Environment

a.

Inspection Scope

The inspection team conducted informal individual interviews with 23 individuals. The

interviewees represented various functional organizations and ranged across contractor,

staff, and supervisor levels. The team conducted these interviews to assess whether

conditions existed that would challenge the establishment of a safety conscious work

environment at the River Bend Station.

b.

Assessment

Because the team encountered no indication of an issue related to the safety conscious

work environment during their interviews with site personnel, the team concluded that

the licensee had maintained a safety conscious work environment.

.5

Specific Issues identified During this Inspection

Failure to Take Corrective Action for Service-Induced Failures of Gould J-series Relays

Introduction. The inspectors reviewed a self-revealing green noncited violation of

10 CFR Part 50, Appendix B, Criterion XVI, "Corrective Actions," for the licensee's failure

to take corrective action to address service-induced failures of Gould J-series relays.

Description. On October 9,2008, River Bend Station personnel initiated

CR-RBS-2008-05915 to document that valve SWP-MOV4B, standby service water to

drywell unit coolers, had failed in the open position. That valve supplies service water to

the drywell unit coolers and has a safety function to close during a loss-of-coolant

accident. A lower-tier apparent-cause evaluation performed by the licensee had

determined that the valve had failed due to a coil failure for relay EHS-MCC2B-5A-33X.

The licensee had also determined that the relay had failed because it had been in

service beyond its expected lifetime. The River Bend preventive maintenance template

for Gould J10 control relays had established a replacement interval based on not

exceeding the expect service life for the given service conditions. (For relays the

licensee had classified as high-critical, high-duty-cycle, they had established a 21-year

replacement period.) To address extent-of-condition concerns, the licensee had

implemented a replacement project for Gould relays deSignated as high-duty-cycle, high-

critical. Corrective Action 7 to CR-RBS-2008-05915 had established work orders for

127 relays classified as high-duty-cycle, high-critical. Based on work orders that had

been generated, the licensee closed CR-RBS-2008-05915 on November 26, 2008. By

July 2009, the licensee had completed work to replace the relays they had classified as

high-duty-cyc1e, high-cf!t!caL

- 9 -

Enclosure

On January 16, 2011, valve SWP-MOV55B failed closed. That valve is the Division 2

standby service water return valve to the cooling tower inlet The licensee initiated

CR-RBS-2011-00393 to document this issue, During troubleshooting, the licensee

found that the valve's control power fuses had failed because the Gould J10 control

relay identified as EHS-MCC16B6D-33X1 had shorted out. During an equipment

performance evaluation, the licensee discovered that during a preventive maintenance

optimization program in 2008, SWP-MOV55B had been misclassified as a non-critical

component instead of a high-critical component. (According to licensee

Procedure EN-DC 153, "Preventive Maintenance Component Classification," the relay

should have been classified as high-critical and high-duty-cycie,) Consequently.

because the relay had been classified as non-critical, the licensee had not established a

recurring preventive maintenance task to periodically replace the relay, The inspectors

discovered that the subject relay had been in service for 26 years, well beyond its

expected lifetime of 21 years, The inspectors also determined that because this relay

had been misclassified, it had not been identified in the scope of the corrective actions

identified in CR-RBS-2008-05915. Consequently, no corrective actions had been

implemented to address service beyond its expected life, and the component had been

allowed to run to failure.

As corrective action to address the misclassification of components within the preventive

maintenance optimization system, the licensee initiated condition

report CR-RBS-201 0-06032 to ensure that appropriate levels of preventive maintenance

are performed on high-critical components.

Analysis, The performance deficiency was the licensee's failure to take adequate

corrective actions to address service-induced failures of the high-critical, high-duty-cycle

Gould J-series relay designated as EHS-MCC2B-5A-33X. This performance deficiency

was determined to be more than minor and was therefore a finding because it impacted

the Mitigating Systems Cornerstone attribute of equipment performance and affected the

cornerstone objective to ensure the availability, reliability, and capability of systems that

respond to initiating events to prevent undesirable consequences, in that this

performance deficiency allowed a coil failure that rendered valve SWP-MOV4B

inoperable. The inspectors used Manual Chapter 0609,04, "Phase 1 -Initial Screening

and Characterization of Findings," to determine that this finding has very-low safety

significance because the finding was not a design or qualification deficiency confirmed

not to result in a loss of operability. does not represent a loss of system safety function,

does not represent a loss of safety function for a single train for greater than its technical

specification allowed outage time, and does not screen as potentially risk significant due

to a seismic, flooding or severe weather initiating event The inspectors determined that

the apparent cause of this finding was the licensee's misclassification of the failed relay

within the preventive maintenance optimization program in 2008. The inspectors

considered that the licensee's performance in that program was not reflective of current

licensee performance. so no cross-cutting aspect was assigned to this finding.

Enforcement. Title 10 CFR Part 50, Appendix B, Criterion XVI, "Corrective Actions,"

requires, in part, that measures shall be established to assure that conditions adverse to

quality are promptly identified and corrected. Contrary to the above, on November 26,

2008, the licensee failed to correct a condition adverse to quality, in that the plant

configuration that allowed relay EHS-MCC2B-5A-33X to run to failure was a condition

- 10 -

Enclosure

On January 16, 2011, valve SWP-MOV55B failed closed. That valve is the Division 2

standby service water return valve to the cooling tower inlet The licensee initiated

CR-RBS-2011-00393 to document this issue, During troubleshooting, the licensee

found that the valve's control power fuses had failed because the Gould J10 control

relay identified as EHS-MCC16B6D-33X1 had shorted out. During an equipment

performance evaluation, the licensee discovered that during a preventive maintenance

optimization program in 2008, SWP-MOV55B had been misclassified as a non-critical

component instead of a high-critical component. (According to licensee

Procedure EN-DC 153, "Preventive Maintenance Component Classification," the relay

should have been classified as high-critical and high-duty-cycie,) Consequently.

because the relay had been classified as non-critical, the licensee had not established a

recurring preventive maintenance task to periodically replace the relay, The inspectors

discovered that the subject relay had been in service for 26 years, well beyond its

expected lifetime of 21 years, The inspectors also determined that because this relay

had been misclassified, it had not been identified in the scope of the corrective actions

identified in CR-RBS-2008-05915. Consequently, no corrective actions had been

implemented to address service beyond its expected life, and the component had been

allowed to run to failure.

As corrective action to address the misclassification of components within the preventive

maintenance optimization system, the licensee initiated condition

report CR-RBS-201 0-06032 to ensure that appropriate levels of preventive maintenance

are performed on high-critical components.

Analysis, The performance deficiency was the licensee's failure to take adequate

corrective actions to address service-induced failures of the high-critical, high-duty-cycle

Gould J-series relay designated as EHS-MCC2B-5A-33X. This performance deficiency

was determined to be more than minor and was therefore a finding because it impacted

the Mitigating Systems Cornerstone attribute of equipment performance and affected the

cornerstone objective to ensure the availability, reliability, and capability of systems that

respond to initiating events to prevent undesirable consequences, in that this

performance deficiency allowed a coil failure that rendered valve SWP-MOV4B

inoperable. The inspectors used Manual Chapter 0609,04, "Phase 1 -Initial Screening

and Characterization of Findings," to determine that this finding has very-low safety

significance because the finding was not a design or qualification deficiency confirmed

not to result in a loss of operability. does not represent a loss of system safety function,

does not represent a loss of safety function for a single train for greater than its technical

specification allowed outage time, and does not screen as potentially risk significant due

to a seismic, flooding or severe weather initiating event The inspectors determined that

the apparent cause of this finding was the licensee's misclassification of the failed relay

within the preventive maintenance optimization program in 2008. The inspectors

considered that the licensee's performance in that program was not reflective of current

licensee performance. so no cross-cutting aspect was assigned to this finding.

Enforcement. Title 10 CFR Part 50, Appendix B, Criterion XVI, "Corrective Actions,"

requires, in part, that measures shall be established to assure that conditions adverse to

quality are promptly identified and corrected. Contrary to the above, on November 26,

2008, the licensee failed to correct a condition adverse to quality, in that the plant

configuration that allowed relay EHS-MCC2B-5A-33X to run to failure was a condition

- 10 -

Enclosure

adverse to quality, and the licensee failed to identify and correct that condition.

Consequently, on January 16, 2011, the subject relay failed in service and rendered

valve SWP-MOV4B inoperable. Because this finding had very low safety significance,

and because the licensee entered this issue into their corrective action program as

CR-RBS-2011-04064, this finding is being treated as a noncited violation in accordance

with Section 2.3.2 of the Enforcement Policy: NCV 05000458/2011006-01, "Failure to

Take Corrective Action for Service-Induced Failures of Gould J-series Relays."

40A6 Meetings

Exit Meeting Summary

On May 12, 2011, the team presented the inspection results to Mr. Eric Olson (the site Vice

President) and other members of the licensee staff. The licensee acknowledged the issues

presented. The inspectors asked the licensee whether any materials examined during the

inspection should be considered proprietary. No proprietary information was identified.

40A7 Licensee-Identified Violations

The following violation of very low safety significance (Green) was identified by the licensee and

is a violation of NRC requirements which meets the criteria of Section 2.3.2 of the NRC

Enforcement Policy for being dispositioned as a noncited violation.

Failure to Incorporate Key Assumptions into an Abnormal Operating Procedure

The licensee identified a non cited violation of Technical Specification 5.4.1,

"Procedures," for their failure to incorporate into Procedure AOP-50, "Station Blackout,"

instructions to open Division I and II equipment room doors within 30 minutes of a station

blackout event. The corresponding assumption is used in calculations that determine

the licensee's coping during a station blackout. This violation has Green risk

significance because the finding was not a design or qualification deficiency confirmed

not to result in a loss of operability, does not represent a loss of system safety function,

does not represent a loss of safety function for a single train for greater than its technical

specification allowed outage time, and does not screen as potentially risk-significant due

to a seismic, flooding or severe weather initiating event. In CR-2009-05598 the licensee

documented the change in AOP-50 that requires the doors to be opened within

30 minutes.

- 11 -

Enclosure

adverse to quality, and the licensee failed to identify and correct that condition.

Consequently, on January 16, 2011, the subject relay failed in service and rendered

valve SWP-MOV4B inoperable. Because this finding had very low safety significance,

and because the licensee entered this issue into their corrective action program as

CR-RBS-2011-04064, this finding is being treated as a noncited violation in accordance

with Section 2.3.2 of the Enforcement Policy: NCV 05000458/2011006-01, "Failure to

Take Corrective Action for Service-Induced Failures of Gould J-series Relays."

40A6 Meetings

Exit Meeting Summary

On May 12, 2011, the team presented the inspection results to Mr. Eric Olson (the site Vice

President) and other members of the licensee staff. The licensee acknowledged the issues

presented. The inspectors asked the licensee whether any materials examined during the

inspection should be considered proprietary. No proprietary information was identified.

40A7 Licensee-Identified Violations

The following violation of very low safety significance (Green) was identified by the licensee and

is a violation of NRC requirements which meets the criteria of Section 2.3.2 of the NRC

Enforcement Policy for being dispositioned as a noncited violation.

Failure to Incorporate Key Assumptions into an Abnormal Operating Procedure

The licensee identified a non cited violation of Technical Specification 5.4.1,

"Procedures," for their failure to incorporate into Procedure AOP-50, "Station Blackout,"

instructions to open Division I and II equipment room doors within 30 minutes of a station

blackout event. The corresponding assumption is used in calculations that determine

the licensee's coping during a station blackout. This violation has Green risk

significance because the finding was not a design or qualification deficiency confirmed

not to result in a loss of operability, does not represent a loss of system safety function,

does not represent a loss of safety function for a single train for greater than its technical

specification allowed outage time, and does not screen as potentially risk-significant due

to a seismic, flooding or severe weather initiating event. In CR-2009-05598 the licensee

documented the change in AOP-50 that requires the doors to be opened within

30 minutes.

- 11 -

Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

T Bordelon, Specialist, Corrective Actions & Assessments

F. Hurst, Emergency Plan Instructor

K. Huffstatler, Senior Licensing Specialist

M. Jurey, Quality Assurance Auditor

D. Lorfing, Manager, Licensing

M. Mitchell, Engineer

S. Phillips, Specialist, Corrective Actions & Assessments

J. Roberts, Director, Nuclear Safety & Assurance

J. Schlesinger, Engineer

D. Vines, Manager, Corrective Actions & Assessments

D. Wells, Employee Concerns Program Coordinator

NRC Personnel

P. Elkmann, Senior Emergency Planning Inspector

V. Gaddy, Branch Chief

G. Larkin, Senior Resident Inspector

H. Walker, Senior Reactor Systems Engineer

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed 05000458/2011006-01 NCV

Failure to Take Corrective Action for Service-Induced Failures of

Gould J-series Relays (Section 40A2.5)

LIST OF DOCUMENTS REVIEWED

Section 40A2: Identification and Resolution of Problems

CALCULATIONS

NUMBER

E-143

E-144

TITLE

Standby Battery "ENB-SAT01A" Duty Cycle, Current

Profile and Size Verification

1=t-.11:l I:l A T('\\11:l n ** t" ("", ... 1", (" ** ~~~~+ Cl~",,"';J~ ~~,.J C':_~

....... .. '-'-.....,.1 "t \\J t...., L...o"Yf.Y

......, , ..... 1\\,;;) ,"",ut J ~lll ,

I Ville; Cit fU ufLC

Verification

- 1 -

REVISION

10

'"

u

Attachment A

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

T Bordelon, Specialist, Corrective Actions & Assessments

F. Hurst, Emergency Plan Instructor

K. Huffstatler, Senior Licensing Specialist

M. Jurey, Quality Assurance Auditor

D. Lorfing, Manager, Licensing

M. Mitchell, Engineer

S. Phillips, Specialist, Corrective Actions & Assessments

J. Roberts, Director, Nuclear Safety & Assurance

J. Schlesinger, Engineer

D. Vines, Manager, Corrective Actions & Assessments

D. Wells, Employee Concerns Program Coordinator

NRC Personnel

P. Elkmann, Senior Emergency Planning Inspector

V. Gaddy, Branch Chief

G. Larkin, Senior Resident Inspector

H. Walker, Senior Reactor Systems Engineer

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed 05000458/2011006-01 NCV

Failure to Take Corrective Action for Service-Induced Failures of

Gould J-series Relays (Section 40A2.5)

LIST OF DOCUMENTS REVIEWED

Section 40A2: Identification and Resolution of Problems

CALCULATIONS

NUMBER

E-143

E-144

TITLE

Standby Battery "ENB-SAT01A" Duty Cycle, Current

Profile and Size Verification

1=t-.11:l I:l A T('\\11:l n ** t" ("", ... 1", (" ** ~~~~+ Cl~",,"';J~ ~~,.J C':_~

....... .. '-'-.....,.1 "t \\J t...., L...o"Yf.Y

......, , ..... 1\\,;;) ,"",ut J ~lll ,

I Ville; Cit fU ufLC

Verification

- 1 -

REVISION

10

'"

u

Attachment A

G13.18.3.6*009

Division III 125 VDC Battery Sizing, Load

Circuit

3

Voltage Drop, Short Circuit, Charger Verification and

Cable Verification

G13.18.3.6*021

DC System Analysis, Methodology & Scenario

1

Development

PROCEDURES

NUMBER

TITLE

REVISIONS

ADM-0099

Performance Improvement Using Fundamentals

5

EN-DC-132

Control of Engineering Documents

5

EN-DC-153

preventive maintenance component classification

5

EN-DC-346

Cable Reliability Program

1

EN-FAP-U-003

Corrective Action Review Board (CARB) Process

2

EN-FAP-OP-OO6

Operator Aggregate Impact lndex Performance

0

Indicator

EN-HR-138

Executive Review Board Process

2

EN-Ll-102

Corrective Action Process

1,2,&16

EN-Ll-108

Event Notification And Reporting

4

EN-U-118

Root Cause Analysis Process

13

EN-U-118-06

Common Cause Analysis (CCA)

1

EN-L1-119

Apparent Cause Evaluation (ACE) Process

11

EN-Ll-119-0 1

Equipment Failure Evaluation

0

EN-MA-126

Control of Supplemental Personnel

12

EN-MA-126-01

New to Nuclear Workforce Orientation

0&2

EN-OP-104

Operability Determination Process

5

EN-OP-115

Conduct of Operations

10

EN-QV-132

Site Executive Protocol Group

ENS-TQ-110

Emergency Preparedness Training Program

15

EN-TQ-114

Licensed Operator Requalification Training Program

5

no.~l"'ri,...+i,...n

'--'.,,:H..IlltJI.IVf t

-2-

Attachment A

G13.18.3.6*009

Division III 125 VDC Battery Sizing, Load

Circuit

3

Voltage Drop, Short Circuit, Charger Verification and

Cable Verification

G13.18.3.6*021

DC System Analysis, Methodology & Scenario

1

Development

PROCEDURES

NUMBER

TITLE

REVISIONS

ADM-0099

Performance Improvement Using Fundamentals

5

EN-DC-132

Control of Engineering Documents

5

EN-DC-153

preventive maintenance component classification

5

EN-DC-346

Cable Reliability Program

1

EN-FAP-U-003

Corrective Action Review Board (CARB) Process

2

EN-FAP-OP-OO6

Operator Aggregate Impact lndex Performance

0

Indicator

EN-HR-138

Executive Review Board Process

2

EN-Ll-102

Corrective Action Process

1,2,&16

EN-Ll-108

Event Notification And Reporting

4

EN-U-118

Root Cause Analysis Process

13

EN-U-118-06

Common Cause Analysis (CCA)

1

EN-L1-119

Apparent Cause Evaluation (ACE) Process

11

EN-Ll-119-0 1

Equipment Failure Evaluation

0

EN-MA-126

Control of Supplemental Personnel

12

EN-MA-126-01

New to Nuclear Workforce Orientation

0&2

EN-OP-104

Operability Determination Process

5

EN-OP-115

Conduct of Operations

10

EN-QV-132

Site Executive Protocol Group

ENS-TQ-110

Emergency Preparedness Training Program

15

EN-TQ-114

Licensed Operator Requalification Training Program

5

no.~l"'ri,...+i,...n

'--'.,,:H..IlltJI.IVf t

-2-

Attachment A

EN-WM-107

Post Maintenance Testing

3

OSP-0029

Log Report - Auxiliary, Reactor and Fuel Buildings

46

RLEC-EP-115

Emergency Response Organization Tabletop Training

13

STP-309-0601

Division I ECCS Test

36

CONDITION REPORTS

CR-HON-2009-00738

CR-HON-2009-01184

CR-HON-2010-00013

CR-HON-2010-00067

CR-HON-2010-00386

CR-RBS-2001-01414

CR-RBS-2002-02028

CR-RBS-2004-01920

CR-RBS-2004-03160

CR-RBS-2005-0 1141

CR-RBS-2005-01448

CR-RBS-2005-03985

CR-RBS-2006-04478

CR-RBS-2007 -01706

CR-RBS-2007 -02102

CR-RBS-2007 -03092

CR-RBS-2007 -03243

CR-RBS-2007 -04505

CR-RBS-2007 -04669

CR-RBS-2007 -04698

CR-RBS-2007 -05548

CR-RBS-2008-02558

CR-RBS-2008-02844

CR-RBS-2008-03339

CR-RBS-2008-03449

CR-RBS-2008-03556

C R-RBS-2008-03634

CR-RBS-2008-03641

CR-RBS-2008-03854

CR-RBS-2008-03911

CR-RBS-2008-03911

CR-RBS-2008-04378

CR-RBS-2008-04379

CR-RBS-2008-04386

CR-RBS-2008-04711

CR-RBS-2008-05311

CR-RBS-2008-05915

CR-RBS-2008-07013

CR-RBS-2009-00043

CR-RBS-2009-00196

CR-RBS-2009-00352

CR-RBS-2009-01593

CR-RBS-2009-01626

CR-RBS-2009-01677

CR-RBS-2009-02588

CR-RBS-2009-02623

CR-RBS-2009-02681

CR-RBS-2009-02742

CR-RBS-2009-02764

CR-RBS-2009-02888

CR-RBS-2009-02894

CR-RBS-2009-03080

CR-RBS-2009-03094

CR-RBS-2009-03175

CR-RBS-2009-03176

CR-RBS-2009-03208

CR-RBS-2009-03212

CR-RBS-2009-03218

CR-RBS-2009-03222

CR-RBS-2009-03226

CR-RBS-2009-03231

CR -RBS-2009-03233

CR-RBS-2009-03233

CR-RBS-2009-03292

CR-RBS-2009-03341

CR-RBS-2009-03401

CR-RBS-2009-03460

CR-RBS-2009-03519

CR-RBS-2009-03520

CR-RBS-2009-03629

CR-RBS-2009-03743

CR-RBS-2009-03747

CR-RBS-2009-037 4 7

CR-RBS-2009-03752

CR-RBS-2009-03768

CR-RBS-2009-03771

CR-RBS-2009-03828

CR-RBS-2009-03901

CR-RBS-2009-03907

CR-RBS-2009-03963

C R -RBS-2009-04059

CR-RBS-2009-04096

CR-RBS-2009-04096

CR-RBS-2009-04102

- 3 -

Attachment A

EN-WM-107

Post Maintenance Testing

3

OSP-0029

Log Report - Auxiliary, Reactor and Fuel Buildings

46

RLEC-EP-115

Emergency Response Organization Tabletop Training

13

STP-309-0601

Division I ECCS Test

36

CONDITION REPORTS

CR-HON-2009-00738

CR-HON-2009-01184

CR-HON-2010-00013

CR-HON-2010-00067

CR-HON-2010-00386

CR-RBS-2001-01414

CR-RBS-2002-02028

CR-RBS-2004-01920

CR-RBS-2004-03160

CR-RBS-2005-0 1141

CR-RBS-2005-01448

CR-RBS-2005-03985

CR-RBS-2006-04478

CR-RBS-2007 -01706

CR-RBS-2007 -02102

CR-RBS-2007 -03092

CR-RBS-2007 -03243

CR-RBS-2007 -04505

CR-RBS-2007 -04669

CR-RBS-2007 -04698

CR-RBS-2007 -05548

CR-RBS-2008-02558

CR-RBS-2008-02844

CR-RBS-2008-03339

CR-RBS-2008-03449

CR-RBS-2008-03556

C R-RBS-2008-03634

CR-RBS-2008-03641

CR-RBS-2008-03854

CR-RBS-2008-03911

CR-RBS-2008-03911

CR-RBS-2008-04378

CR-RBS-2008-04379

CR-RBS-2008-04386

CR-RBS-2008-04711

CR-RBS-2008-05311

CR-RBS-2008-05915

CR-RBS-2008-07013

CR-RBS-2009-00043

CR-RBS-2009-00196

CR-RBS-2009-00352

CR-RBS-2009-01593

CR-RBS-2009-01626

CR-RBS-2009-01677

CR-RBS-2009-02588

CR-RBS-2009-02623

CR-RBS-2009-02681

CR-RBS-2009-02742

CR-RBS-2009-02764

CR-RBS-2009-02888

CR-RBS-2009-02894

CR-RBS-2009-03080

CR-RBS-2009-03094

CR-RBS-2009-03175

CR-RBS-2009-03176

CR-RBS-2009-03208

CR-RBS-2009-03212

CR-RBS-2009-03218

CR-RBS-2009-03222

CR-RBS-2009-03226

CR-RBS-2009-03231

CR -RBS-2009-03233

CR-RBS-2009-03233

CR-RBS-2009-03292

CR-RBS-2009-03341

CR-RBS-2009-03401

CR-RBS-2009-03460

CR-RBS-2009-03519

CR-RBS-2009-03520

CR-RBS-2009-03629

CR-RBS-2009-03743

CR-RBS-2009-03747

CR-RBS-2009-037 4 7

CR-RBS-2009-03752

CR-RBS-2009-03768

CR-RBS-2009-03771

CR-RBS-2009-03828

CR-RBS-2009-03901

CR-RBS-2009-03907

CR-RBS-2009-03963

C R -RBS-2009-04059

CR-RBS-2009-04096

CR-RBS-2009-04096

CR-RBS-2009-04102

- 3 -

Attachment A

CR-RBS-2009-04204

CR-RBS-2009-04254

CR-RBS-2009-04411

CR-RBS-2009-04417

CR-RBS-2009-04429

CR-RBS-2009-04440

CR-RBS-2009-04658

CR-RBS-2009-04658

CR-RBS-2009-04681

CR-RBS-2009-04681

CR-RBS-2009-04718

CR-RBS-2009-04722

CR-RBS-2009-04725

CR-RBS-2009-04733

CR-RBS-2009-04734

CR-RBS-2009-04894

CR-RBS-2009-05000

CR-RBS-2009-05298

CR-RBS-2009-05337

CR-RBS-2009-05340

CR-RBS-2009-05365

CR-RBS-2009-05374

CR-RBS-2009-05394

CR-RBS-2009-05501

CR-RBS-2009-05573

CR-RBS-2009-05573

CR-RBS-2009-05598

CR-RBS-2009-05621

CR-RBS-2009-05658

CR-RBS-2009-05682

CR-RBS-2009-05750

CR-RBS-2009-05751

CR-RBS-2009-05758

CR-RBS-2009-05768

CR-RBS-2009-05795

CR-RBS-2009-05797

CR-RBS-2009-05811

CR-RBS-2009-05837

CR-RBS-2009-05865

CR-RBS-2009-05883

CR-RBS-2009-05885

CR-RBS-2009-05948

CR-RBS-2009-06011

CR-RBS-2009-06013

CR-RBS-2009-06031

CR -RBS-2009-06031

CR-RBS-2009-06031

CR-RBS-2009-06057

CR-RBS-2009-06058

CR-RBS-2009-06069

CR-RBS-2009-06078

CR-RBS-2009-06078

CR-RBS-2009-06078

CR-RBS-2009-06097

CR-RBS-2009-06148

CR-RBS-2009-06148

CR-RBS-2009-06151

CR-RBS-2009-06235

CR-RBS-2009-06316

CR-RBS-2009-06325

CR-RBS-2009-06331

CR-RBS-2009-06393

CR-RBS-2009-06419

CR-RBS-2009-06425

CR-RBS-2009-06460

CR-RBS-2009-1667

CR-RBS-2009-1670

CR-RBS-2009-1675

CR-RBS-2009-1676

CR-RBS-2009-3747

CR-RBS-2009-3862

CR-RBS-2009-3963

CR-RBS-2009-4096

CR-RBS-2009-4296

CR-RBS-2009-4350

CR-RBS-2009-4658

CR-RBS-2010-00017

CR-RBS-2010-00069

CR-RBS-201 0-001 01

CR-RBS-2010-00196

CR-RBS-2010-00237

CR-RBS-2010-00280

CR-RBS-2010-00424

CR-RBS-2010-00465

CR-RBS-2010-00483

CR-RBS-2010-00538

CR-RBS-2010-00558

CR-RBS-2010-00575

CR-RBS-2010-00596

CR-RBS-2010-00660

CR-RBS-2010-00680

CR-RBS-2010-00731

CR-RBS-2010-00736

CR-RBS-2010-00739

CR-RBS-2010-00762

CR-RBS-2010-00778

CR-RBS-2010-00783

CR-RBS-2010-00802

CR-RBS-2010-00811

CR-RBS-2010-00819

CR-RBS-2010-00824

CR-RBS-2010-01140

CR-RBS-20i 0-0"1 i 48

CR-RBS-20iO-01193

CR-RBS-2010-01205

CR-RBS-2010-01428

CR-RBS-2010-01566

CR-RBS-2010-01587

- 4-

Attachment A

CR-RBS-2009-04204

CR-RBS-2009-04254

CR-RBS-2009-04411

CR-RBS-2009-04417

CR-RBS-2009-04429

CR-RBS-2009-04440

CR-RBS-2009-04658

CR-RBS-2009-04658

CR-RBS-2009-04681

CR-RBS-2009-04681

CR-RBS-2009-04718

CR-RBS-2009-04722

CR-RBS-2009-04725

CR-RBS-2009-04733

CR-RBS-2009-04734

CR-RBS-2009-04894

CR-RBS-2009-05000

CR-RBS-2009-05298

CR-RBS-2009-05337

CR-RBS-2009-05340

CR-RBS-2009-05365

CR-RBS-2009-05374

CR-RBS-2009-05394

CR-RBS-2009-05501

CR-RBS-2009-05573

CR-RBS-2009-05573

CR-RBS-2009-05598

CR-RBS-2009-05621

CR-RBS-2009-05658

CR-RBS-2009-05682

CR-RBS-2009-05750

CR-RBS-2009-05751

CR-RBS-2009-05758

CR-RBS-2009-05768

CR-RBS-2009-05795

CR-RBS-2009-05797

CR-RBS-2009-05811

CR-RBS-2009-05837

CR-RBS-2009-05865

CR-RBS-2009-05883

CR-RBS-2009-05885

CR-RBS-2009-05948

CR-RBS-2009-06011

CR-RBS-2009-06013

CR-RBS-2009-06031

CR -RBS-2009-06031

CR-RBS-2009-06031

CR-RBS-2009-06057

CR-RBS-2009-06058

CR-RBS-2009-06069

CR-RBS-2009-06078

CR-RBS-2009-06078

CR-RBS-2009-06078

CR-RBS-2009-06097

CR-RBS-2009-06148

CR-RBS-2009-06148

CR-RBS-2009-06151

CR-RBS-2009-06235

CR-RBS-2009-06316

CR-RBS-2009-06325

CR-RBS-2009-06331

CR-RBS-2009-06393

CR-RBS-2009-06419

CR-RBS-2009-06425

CR-RBS-2009-06460

CR-RBS-2009-1667

CR-RBS-2009-1670

CR-RBS-2009-1675

CR-RBS-2009-1676

CR-RBS-2009-3747

CR-RBS-2009-3862

CR-RBS-2009-3963

CR-RBS-2009-4096

CR-RBS-2009-4296

CR-RBS-2009-4350

CR-RBS-2009-4658

CR-RBS-2010-00017

CR-RBS-2010-00069

CR-RBS-201 0-001 01

CR-RBS-2010-00196

CR-RBS-2010-00237

CR-RBS-2010-00280

CR-RBS-2010-00424

CR-RBS-2010-00465

CR-RBS-2010-00483

CR-RBS-2010-00538

CR-RBS-2010-00558

CR-RBS-2010-00575

CR-RBS-2010-00596

CR-RBS-2010-00660

CR-RBS-2010-00680

CR-RBS-2010-00731

CR-RBS-2010-00736

CR-RBS-2010-00739

CR-RBS-2010-00762

CR-RBS-2010-00778

CR-RBS-2010-00783

CR-RBS-2010-00802

CR-RBS-2010-00811

CR-RBS-2010-00819

CR-RBS-2010-00824

CR-RBS-2010-01140

CR-RBS-20i 0-0"1 i 48

CR-RBS-20iO-01193

CR-RBS-2010-01205

CR-RBS-2010-01428

CR-RBS-2010-01566

CR-RBS-2010-01587

- 4-

Attachment A

CR-RBS-2010-01587

CR-RBS-2010-01592

CR-RBS-2010-01594

CR-RBS-2010-01667

CR-RBS-2010-01692

CR-RBS-2010-01717

CR-RBS-2010-01731

CR-RBS-2010-01763

CR-RBS-2010-01765

CR-RBS-2010-01775

CR-RBS-2010-01783

CR-RBS-2010-01808

CR-RBS-2010-01817

CR-RBS-2010-01821

CR-RBS-2010-01825

CR-RBS-2010-01831

CR-RBS-20i 0-01846

CR-RBS-2010-01849

CR-RBS-20 10-01850

CR-RBS-2010-01981

CR-RBS"2010-02048

CR-RBS-2010-02099

CR-RBS-2010-02177

CR-RBS-20 10-02362

CR-RBS-2010-02423

CR-RBS-2010-02468

CR-RBS-201 0-02475

CR-RBS-2010-02503

CR-RBS-2010-02527

CR-RBS-2010-02577

CR-RBS-2010-02732

CR-RBS-2010-02737

CR-RBS-201 0-02747

CR-RBS-2010-02771

CR-RBS-2010-02772

CR-RBS-2010-02775

CR-RBS-2010-02919

CR-RBS-2010-02920

CR-RBS-201 0-03104

CR-RBS-2010-03153

CR-RBS-2010-03170

CR-RBS-2010-03224

CR-RBS-2010-03584

CR-RBS-2010-03594

CR-RBS-2010-03629

CR-RBS-201 0-03744

CR-RBS-2010-03807

CR-RBS-2010-03826

CR-RBS-2010-03948

CR-RBS-2010-04013

CR-RBS-2010-04126

CR-RBS-201 0-04174

CR-RBS-2010-04186

CR-RBS-2010-04186

CR-RBS-201 0-04274

CR-RBS-2010-04318

CR-RBS-2010-04372

CR-RBS-2010-04491

CR-RBS-2010-04526

CR-RBS-2010-04959

CR-RBS-2010-04959

CR-RBS-201 0-04974

CR-RBS-201 0-051 05

CR-RBS-2010-05133

CR-RBS-2010-05224

CR-RBS-2010-05225

CR-RBS-2010-05244

CR-RBS-2010-05264

CR-RBS-2010-05270

CR-RBS-2010-05354

CR-RBS-2010-05371

CR-RBS-2010-05372

CR-RBS-2010-05391

CR-RBS-2010-05440

CR-RBS-2010-05540

CR-RBS-2010-05611

CR-RBS-2010-05627

CR-RBS-2010-05686

CR-RBS-2010-05766

CR-RBS-2010-05766

CR-RBS-20 1 0-05895

CR-RBS-2010-05912

CR-RBS-2010-06015

CR-RBS-2010-06053

CR-RBS-2010-06059

CR-RBS-2010-06099

CR-RBS-2010-06125

CR-RBS-2010-06168

CR-RBS-2010-06343

CR-RBS-2010-06498

CR-RBS-2010-06638

CR-RBS-2010-06658

CR-RBS-2010-06661

CR-RBS-2010-06683

CR-RBS-2010-06684

CR-RBS-2010-06689

CR-RBS-2010-06697

CR-RBS-2010-06754

CR-RBS-2010-06775

CR-RBS-2010-06823

CR-RBS-2010-6247

CR-RBS-2011-00053

CR-RBS-2011-00059

CR-RBS-20i 1-00147

CR-RBS-2011-00224

CR-RBS-2011-00393

CR-RBS-2011-00393

CR-RBS-2011-00575

- 5-

Attachment A

CR-RBS-2010-01587

CR-RBS-2010-01592

CR-RBS-2010-01594

CR-RBS-2010-01667

CR-RBS-2010-01692

CR-RBS-2010-01717

CR-RBS-2010-01731

CR-RBS-2010-01763

CR-RBS-2010-01765

CR-RBS-2010-01775

CR-RBS-2010-01783

CR-RBS-2010-01808

CR-RBS-2010-01817

CR-RBS-2010-01821

CR-RBS-2010-01825

CR-RBS-2010-01831

CR-RBS-20i 0-01846

CR-RBS-2010-01849

CR-RBS-20 10-01850

CR-RBS-2010-01981

CR-RBS"2010-02048

CR-RBS-2010-02099

CR-RBS-2010-02177

CR-RBS-20 10-02362

CR-RBS-2010-02423

CR-RBS-2010-02468

CR-RBS-201 0-02475

CR-RBS-2010-02503

CR-RBS-2010-02527

CR-RBS-2010-02577

CR-RBS-2010-02732

CR-RBS-2010-02737

CR-RBS-201 0-02747

CR-RBS-2010-02771

CR-RBS-2010-02772

CR-RBS-2010-02775

CR-RBS-2010-02919

CR-RBS-2010-02920

CR-RBS-201 0-03104

CR-RBS-2010-03153

CR-RBS-2010-03170

CR-RBS-2010-03224

CR-RBS-2010-03584

CR-RBS-2010-03594

CR-RBS-2010-03629

CR-RBS-201 0-03744

CR-RBS-2010-03807

CR-RBS-2010-03826

CR-RBS-2010-03948

CR-RBS-2010-04013

CR-RBS-2010-04126

CR-RBS-201 0-04174

CR-RBS-2010-04186

CR-RBS-2010-04186

CR-RBS-201 0-04274

CR-RBS-2010-04318

CR-RBS-2010-04372

CR-RBS-2010-04491

CR-RBS-2010-04526

CR-RBS-2010-04959

CR-RBS-2010-04959

CR-RBS-201 0-04974

CR-RBS-201 0-051 05

CR-RBS-2010-05133

CR-RBS-2010-05224

CR-RBS-2010-05225

CR-RBS-2010-05244

CR-RBS-2010-05264

CR-RBS-2010-05270

CR-RBS-2010-05354

CR-RBS-2010-05371

CR-RBS-2010-05372

CR-RBS-2010-05391

CR-RBS-2010-05440

CR-RBS-2010-05540

CR-RBS-2010-05611

CR-RBS-2010-05627

CR-RBS-2010-05686

CR-RBS-2010-05766

CR-RBS-2010-05766

CR-RBS-20 1 0-05895

CR-RBS-2010-05912

CR-RBS-2010-06015

CR-RBS-2010-06053

CR-RBS-2010-06059

CR-RBS-2010-06099

CR-RBS-2010-06125

CR-RBS-2010-06168

CR-RBS-2010-06343

CR-RBS-2010-06498

CR-RBS-2010-06638

CR-RBS-2010-06658

CR-RBS-2010-06661

CR-RBS-2010-06683

CR-RBS-2010-06684

CR-RBS-2010-06689

CR-RBS-2010-06697

CR-RBS-2010-06754

CR-RBS-2010-06775

CR-RBS-2010-06823

CR-RBS-2010-6247

CR-RBS-2011-00053

CR-RBS-2011-00059

CR-RBS-20i 1-00147

CR-RBS-2011-00224

CR-RBS-2011-00393

CR-RBS-2011-00393

CR-RBS-2011-00575

- 5-

Attachment A

CR-RBS-2011-00604

CR-RBS-2011-00658

CR-RBS-2011-00682

CR-RBS-2011-00811

CR-RBS-2011-00833

CR-RBS-2011-00897

CR-RBS-2011-00899

CR-RBS-2011-00899

CR-RBS-2011-01053

CR-RBS-2011-01107

CR-RBS-2011-01185

CR-RBS-2011-01313

CR-RBS-2011-01333

CR-RBS-2011-01430

CR-RBS-2011-01850

CR-RBS-2011-01967

CR-RBS-2011-02402

CR-RBS-2011-02460

CR-RBS-2011-02498

CR-RBS-2011-02S25

CR-RBS-2011-03196

CR-RBS-2011-03296

CR-RBS-2011-03751

CR-RBS-2011-03818

CR-RBS-2011-03856

CR-RBS-2011-03872

CR-RBS-2011-03961

CR-RBS-2011-04022

CR-RBS-2011-04046

CR-RBS-2011-04054

CR-RBS-2011-04055

ASSESSMENTS

LO-RLO-2008-00116

LO-RLO-2009-00041

LO-RLO-2009-00042

LO-RLO-2009-00060

LO-RLO-2009-00082

LO-RLO-2009-00102

LO-RLO-2009-00112

LO-RLO-2009-0 103

LO-RLO-2009-0124

LO-RLO-2009-0174

LO-RLO-2010-00020

LO-RLO-2010-00021

LO-RLO-2010-00035

LO-RLO-2010-0014

LO-RLO-2010-0016

LO-RLO-2010-0035

LO-RLO-2010-0041

LO-RLO-RBS-2009-139

LO-RLO-RBS-2009-140

LO-WTRBS-2011-00062

WORK ORDERS

071809

164528

164529

166223

179835

181114

192284

194016

198181

200986

201677

209393

209974

209975

211306

211412

213965

218725

221072

226485

223065

229594

229595

234052

234056

234057

234610

235805

235807

235808

238291

244247

249847

254023

258980

263705

266777

267260

267260

267262

267262

267341

268782

270028

271559

272015

- 6 -

Attachment A

CR-RBS-2011-00604

CR-RBS-2011-00658

CR-RBS-2011-00682

CR-RBS-2011-00811

CR-RBS-2011-00833

CR-RBS-2011-00897

CR-RBS-2011-00899

CR-RBS-2011-00899

CR-RBS-2011-01053

CR-RBS-2011-01107

CR-RBS-2011-01185

CR-RBS-2011-01313

CR-RBS-2011-01333

CR-RBS-2011-01430

CR-RBS-2011-01850

CR-RBS-2011-01967

CR-RBS-2011-02402

CR-RBS-2011-02460

CR-RBS-2011-02498

CR-RBS-2011-02S25

CR-RBS-2011-03196

CR-RBS-2011-03296

CR-RBS-2011-03751

CR-RBS-2011-03818

CR-RBS-2011-03856

CR-RBS-2011-03872

CR-RBS-2011-03961

CR-RBS-2011-04022

CR-RBS-2011-04046

CR-RBS-2011-04054

CR-RBS-2011-04055

ASSESSMENTS

LO-RLO-2008-00116

LO-RLO-2009-00041

LO-RLO-2009-00042

LO-RLO-2009-00060

LO-RLO-2009-00082

LO-RLO-2009-00102

LO-RLO-2009-00112

LO-RLO-2009-0 103

LO-RLO-2009-0124

LO-RLO-2009-0174

LO-RLO-2010-00020

LO-RLO-2010-00021

LO-RLO-2010-00035

LO-RLO-2010-0014

LO-RLO-2010-0016

LO-RLO-2010-0035

LO-RLO-2010-0041

LO-RLO-RBS-2009-139

LO-RLO-RBS-2009-140

LO-WTRBS-2011-00062

WORK ORDERS

071809

164528

164529

166223

179835

181114

192284

194016

198181

200986

201677

209393

209974

209975

211306

211412

213965

218725

221072

226485

223065

229594

229595

234052

234056

234057

234610

235805

235807

235808

238291

244247

249847

254023

258980

263705

266777

267260

267260

267262

267262

267341

268782

270028

271559

272015

- 6 -

Attachment A

WORK REQUESTS

019324

193739

225078

229253

243412

172738

193741

226399

230256

187156

223193

227375

232119

191107

225041

227381

232343

EFFECTIVENESS REVIEW PLANS

07-0493

07-1606

07-4922

08-0130QA

TRENDINGfTRACKING REPORTS

ON-SITE REVIEW COMMITTEE TRACKING DOCUMENTS

LO-WTRBS-2009-0047

AUDIT REPORTS

NUMBER

QA-19-2010-RBS-1

QA-01-2009-RBS-1

QA-01-2010-RBS-1

QA-1 0-201 O-RBS-1

QA-14/15-2009-RBS-1

QA-12/18-2009-RBS-1

QA-07-2010-RBS-1

QA-3-2009-RBS-1

QS-2009-RBS-018

LO-WTRBS-2010-0270

LO-WTRBS-2011-0067

TITLE

DATES

Training

March 31,2010

Fitness for Duty/Personnel Access Data

August 7,2009

System

Fitness for Duty/Access Authorization

August 20,2010

Maintenance

August 20,2010

Combined Radiation Protection and

December 17,2009

Radwaste

Combined Operations and Technical

August 3,2009

Specifications

Emergency Plan

April 12 - May 24,2010

Corrective Action Program

June 26,2009

Follow-Up Surveillance of the Yellow

August 18-21, 2009

Problem Identification and Resolution

(PI&R) Rating in the First Quarter 2009

Oversight Report

- 7 -

Attachment A

WORK REQUESTS

019324

193739

225078

229253

243412

172738

193741

226399

230256

187156

223193

227375

232119

191107

225041

227381

232343

EFFECTIVENESS REVIEW PLANS

07-0493

07-1606

07-4922

08-0130QA

TRENDINGfTRACKING REPORTS

ON-SITE REVIEW COMMITTEE TRACKING DOCUMENTS

LO-WTRBS-2009-0047

AUDIT REPORTS

NUMBER

QA-19-2010-RBS-1

QA-01-2009-RBS-1

QA-01-2010-RBS-1

QA-1 0-201 O-RBS-1

QA-14/15-2009-RBS-1

QA-12/18-2009-RBS-1

QA-07-2010-RBS-1

QA-3-2009-RBS-1

QS-2009-RBS-018

LO-WTRBS-2010-0270

LO-WTRBS-2011-0067

TITLE

DATES

Training

March 31,2010

Fitness for Duty/Personnel Access Data

August 7,2009

System

Fitness for Duty/Access Authorization

August 20,2010

Maintenance

August 20,2010

Combined Radiation Protection and

December 17,2009

Radwaste

Combined Operations and Technical

August 3,2009

Specifications

Emergency Plan

April 12 - May 24,2010

Corrective Action Program

June 26,2009

Follow-Up Surveillance of the Yellow

August 18-21, 2009

Problem Identification and Resolution

(PI&R) Rating in the First Quarter 2009

Oversight Report

- 7 -

Attachment A

QS-2009-RBS-022

Followup Surveillance of the 2009

Corrective Action Program Audit

October 21-29,2009

ENGINEERING CHANGES

EC 12578

EC 26327

EC-26030

EC-05628

NUMBER

SIMULATOR DISCREPANCY REPORTS

09-0011

09-0020

10-0094

SYSTEM HEALTH REPORTS

10-0114

Residual Heat Removal System, 4th Quarter 2010

Reactor Core Isolation Cooling, 4th Quarter 2010

Reactor Core Isolation Cooling, 1st Quarter 2011

High Pressure Core Spray, 151 Quarter 2011

Standby Liquid Control, 4th Quarter 2010

230KV Electrical Distribution, 4th Quarter 2010

Standby Service Water, 4th Quarter 2010

MISCELLANEOUS DOCUMENTS

TITLE

ER-RB-2005-0342-000, Functional Impairment of Auxiliary Building

Floor Drains

File No. RBF-07-0070, Response to Generic Letter 2007-01 River Bend

Station - Unit 1 Docket Number 50-458 License Number NPF-47

File No. G.1.495, G9.5, G9.33.4, River Bend Station - Unit 1 Docket

Number 50-458 License Number NPF-47 Updated Response to Generic

Letter 89-13, "Service Water System Problems Affecting Safety-Related

Equipment"

Preventative Maintenance Basis Temp!ate, EN-Relay - Control

- 8 -

REVISION

o

o

o

o

09-0013

REVISION/DATE

o

May 3,2007

October 21, 1998

3

Attachment A

QS-2009-RBS-022

Followup Surveillance of the 2009

Corrective Action Program Audit

October 21-29,2009

ENGINEERING CHANGES

EC 12578

EC 26327

EC-26030

EC-05628

NUMBER

SIMULATOR DISCREPANCY REPORTS

09-0011

09-0020

10-0094

SYSTEM HEALTH REPORTS

10-0114

Residual Heat Removal System, 4th Quarter 2010

Reactor Core Isolation Cooling, 4th Quarter 2010

Reactor Core Isolation Cooling, 1st Quarter 2011

High Pressure Core Spray, 151 Quarter 2011

Standby Liquid Control, 4th Quarter 2010

230KV Electrical Distribution, 4th Quarter 2010

Standby Service Water, 4th Quarter 2010

MISCELLANEOUS DOCUMENTS

TITLE

ER-RB-2005-0342-000, Functional Impairment of Auxiliary Building

Floor Drains

File No. RBF-07-0070, Response to Generic Letter 2007-01 River Bend

Station - Unit 1 Docket Number 50-458 License Number NPF-47

File No. G.1.495, G9.5, G9.33.4, River Bend Station - Unit 1 Docket

Number 50-458 License Number NPF-47 Updated Response to Generic

Letter 89-13, "Service Water System Problems Affecting Safety-Related

Equipment"

Preventative Maintenance Basis Temp!ate, EN-Relay - Control

- 8 -

REVISION

o

o

o

o

09-0013

REVISION/DATE

o

May 3,2007

October 21, 1998

3

Attachment A

Preventative Maintenance Basis Template, EN- Relay - Protective

Preventative Maintenance Basis Template, EN- Relay - Timing

Preventative Maintenance Basis Template, RBS Protective Relay - Lock

Out Relay

Series

3

3

o

4

Preventative Maintenance Basis Template, Control Relay - Gould "J"

2

Series

River Bend Station Quarterly Trend Report

3rd Quarter 2010

MAI-366755, E12-PC002B

December 15, 2002

Position Paper, Fleet Position Paper for Battery Cell Surveillance

September 29, 2009

Requirements for Specific Gravity

RCP-NLOI-COURSE PLAN, initial Non-Licensed Operator Course Pian

2

RCTB-HZM-Notify, Hazardous Material Shipping Emergency Notification

0

TEAR-RBS-2009-0797, Evaluate CR-RBS-2009-03233 and CR-RBS-

April 20, 2011

2009-03208 for Training Implications

TEAR-RBS-2009-0804, Add CR-RBS-2009-03292 to Fuel Handler

April 20, 2011

Training

TEAR-RBS-2009-0940, Add CR-RBS-2009-03218 (Accidental Start of

SWC-P1 B) to Applicable Training Material as OE

TEAR-RBS-2009-1230, Develop Initial and Reoccurring Training for the

Operations Shift Managers and Control Room Supervisors for

Responsibilities As Defined in 49CFR Subpart I for 24 Hour Emergency

Contact Information Associated With Radioactive Material Shipping

Response

April 20, 2011

April 28, 2011

MEASURING & TEST EQUIPMENT (M&TE) NON-CONFORMANCE NOTIFICATIONS

M&TE ID No. AVC-001A1

M&TE ID No. BMT-015A

M&TE ID No. DIM-388A

M&TE ID No. HPM-110A

M&TE ID No. KTC-088A

M&TE ID No. LRM-011A

M&TE !D No. MOV-191A

M&TE ID No. ROA-034A

TITLE

- 9 -

REVISION/DATE

January 20, 2011

February 6, 2011

January 26, 2011

March 7, 2011

November 22, 2010

April 11, 2011

February 10, 2011

December 2,2010

Attachment A

Preventative Maintenance Basis Template, EN- Relay - Protective

Preventative Maintenance Basis Template, EN- Relay - Timing

Preventative Maintenance Basis Template, RBS Protective Relay - Lock

Out Relay

Series

3

3

o

4

Preventative Maintenance Basis Template, Control Relay - Gould "J"

2

Series

River Bend Station Quarterly Trend Report

3rd Quarter 2010

MAI-366755, E12-PC002B

December 15, 2002

Position Paper, Fleet Position Paper for Battery Cell Surveillance

September 29, 2009

Requirements for Specific Gravity

RCP-NLOI-COURSE PLAN, initial Non-Licensed Operator Course Pian

2

RCTB-HZM-Notify, Hazardous Material Shipping Emergency Notification

0

TEAR-RBS-2009-0797, Evaluate CR-RBS-2009-03233 and CR-RBS-

April 20, 2011

2009-03208 for Training Implications

TEAR-RBS-2009-0804, Add CR-RBS-2009-03292 to Fuel Handler

April 20, 2011

Training

TEAR-RBS-2009-0940, Add CR-RBS-2009-03218 (Accidental Start of

SWC-P1 B) to Applicable Training Material as OE

TEAR-RBS-2009-1230, Develop Initial and Reoccurring Training for the

Operations Shift Managers and Control Room Supervisors for

Responsibilities As Defined in 49CFR Subpart I for 24 Hour Emergency

Contact Information Associated With Radioactive Material Shipping

Response

April 20, 2011

April 28, 2011

MEASURING & TEST EQUIPMENT (M&TE) NON-CONFORMANCE NOTIFICATIONS

M&TE ID No. AVC-001A1

M&TE ID No. BMT-015A

M&TE ID No. DIM-388A

M&TE ID No. HPM-110A

M&TE ID No. KTC-088A

M&TE ID No. LRM-011A

M&TE !D No. MOV-191A

M&TE ID No. ROA-034A

TITLE

- 9 -

REVISION/DATE

January 20, 2011

February 6, 2011

January 26, 2011

March 7, 2011

November 22, 2010

April 11, 2011

February 10, 2011

December 2,2010

Attachment A

M& TE

No. TQW-330A

M&TE ID No. WLS-519A

DRAWINGS

NUMBER

0222.111-000-017

0222. 111-000-043

February 14, 2011

April 11, 2011

Engineering Change Markup EC 27430 -

Reactor Recirculation Pump Assembly

Engineering Change Markup EC 19651 -

Assembly Drawing N-7500 Seal Cartridge 833-

PC001A and 833-PC-001 B

- 10-

REVISION

300

301

Attachment A

M& TE

No. TQW-330A

M&TE ID No. WLS-519A

DRAWINGS

NUMBER

0222.111-000-017

0222. 111-000-043

February 14, 2011

April 11, 2011

Engineering Change Markup EC 27430 -

Reactor Recirculation Pump Assembly

Engineering Change Markup EC 19651 -

Assembly Drawing N-7500 Seal Cartridge 833-

PC001A and 833-PC-001 B

- 10-

REVISION

300

301

Attachment A

Information Request - February 16, 2011

Biennial Problem Identification and Resolution Inspection - River Bend Station

Inspection Report 2011-006

This inspection will cover the period from July 10, 2009, to May 13, 2011. All requested

information should be limited to this period unless otherwise specified. To the extent possible,

the requested information should be provided electronically in Adobe PDF or Microsoft Office

2007 format, and placed on a compact disc or a DVD. In addition, please load the documents

into IMS Certrec. Lists of documents should be provided in Microsoft Excel (2007) or a similar

sortable format.

A supplemental information request will likely be sent prior to April 25, 2011.

Please provide the following no later than March 21, 2011. These documents should cover the

time period from July 10, 2009, to March 1, 2011.

1.

Document Lists

Note: for these summary lists, please include the document/reference number, the

document title or a description of the issue, initiation date, and current status.

a.

Summary list of all corrective action documents related to significant conditions

adverse to quality that were opened, closed, or evaluated during the period

b.

Summary list of all corrective action documents related to conditions adverse to

quality that were opened or closed during the period

c.

Summary lists of all corrective action documents which were upgraded or

downgraded in priority/significance during the period

d.

Summary list of all corrective action documents that subsume or "roll up" one or

more smaller issues for the period

e.

Summary lists of operator workarounds, engineering review requests and/or

operability evaluations, temporary modifications, and control room and safety

system deficiencies opened, closed, or evaluated during the period

f.

Summary list of plant safety issues raised or addressed by the Employee

Concerns Program (or equivalent)

g.

Summary list of all Apparent Cause Evaluations completed during the period

h.

Summary list of all Root Cause Evaluations planned or in progress but not

complete at the end of the period

- 1 -

Attachment B

Information Request - February 16, 2011

Biennial Problem Identification and Resolution Inspection - River Bend Station

Inspection Report 2011-006

This inspection will cover the period from July 10, 2009, to May 13, 2011. All requested

information should be limited to this period unless otherwise specified. To the extent possible,

the requested information should be provided electronically in Adobe PDF or Microsoft Office

2007 format, and placed on a compact disc or a DVD. In addition, please load the documents

into IMS Certrec. Lists of documents should be provided in Microsoft Excel (2007) or a similar

sortable format.

A supplemental information request will likely be sent prior to April 25, 2011.

Please provide the following no later than March 21, 2011. These documents should cover the

time period from July 10, 2009, to March 1, 2011.

1.

Document Lists

Note: for these summary lists, please include the document/reference number, the

document title or a description of the issue, initiation date, and current status.

a.

Summary list of all corrective action documents related to significant conditions

adverse to quality that were opened, closed, or evaluated during the period

b.

Summary list of all corrective action documents related to conditions adverse to

quality that were opened or closed during the period

c.

Summary lists of all corrective action documents which were upgraded or

downgraded in priority/significance during the period

d.

Summary list of all corrective action documents that subsume or "roll up" one or

more smaller issues for the period

e.

Summary lists of operator workarounds, engineering review requests and/or

operability evaluations, temporary modifications, and control room and safety

system deficiencies opened, closed, or evaluated during the period

f.

Summary list of plant safety issues raised or addressed by the Employee

Concerns Program (or equivalent)

g.

Summary list of all Apparent Cause Evaluations completed during the period

h.

Summary list of all Root Cause Evaluations planned or in progress but not

complete at the end of the period

- 1 -

Attachment B

2.

Full Documents, with Attachments

a.

Root Cause Evaluations completed during the period

b.

Quality assurance audits performed during the period

c.

AI! audits/surveillances performed during the period of the Corrective Action

Program, of individual corrective actions, and of cause evaluations

d.

Corrective action activity reports, functional area self-assessments, and non-

NRC third party assessments completed during the period (do not include INPO

assessments)

e.

Corrective action documents generated during the period for the following:

1.

NCV's and Violations issued to RBS

ii.

LER's issued by RBS

f.

Corrective action documents generated for the following, if they were determined

to be applicable to RBS (for those that were evaluated but determined not to be

applicable, provide a summary list):

i.

NRC Information Notices, Bulletins, and Generic Letters issued or

evaluated during the period

ii.

Part 21 reports issued or evaluated during the period

iii.

Vendor safety information letters (or equivalent) issued or evaluated

during the period

iv.

Other external events and/or Operating Experience evaluated for

applicability during the period

g.

Corrective action documents generated for the following:

i.

Maintenance preventable functional failures which occurred or were

evaluated during the period

ii.

Adverse trends in equipment, processes, procedures, or programs which

were evaluated during the period

iii.

Action items generated or addressed by plant safety review committees

during the period

iv.

Problems related to Emergency Diesel Generators since July 2009.

- 2 -

Attachment B

2.

Full Documents, with Attachments

a.

Root Cause Evaluations completed during the period

b.

Quality assurance audits performed during the period

c.

AI! audits/surveillances performed during the period of the Corrective Action

Program, of individual corrective actions, and of cause evaluations

d.

Corrective action activity reports, functional area self-assessments, and non-

NRC third party assessments completed during the period (do not include INPO

assessments)

e.

Corrective action documents generated during the period for the following:

1.

NCV's and Violations issued to RBS

ii.

LER's issued by RBS

f.

Corrective action documents generated for the following, if they were determined

to be applicable to RBS (for those that were evaluated but determined not to be

applicable, provide a summary list):

i.

NRC Information Notices, Bulletins, and Generic Letters issued or

evaluated during the period

ii.

Part 21 reports issued or evaluated during the period

iii.

Vendor safety information letters (or equivalent) issued or evaluated

during the period

iv.

Other external events and/or Operating Experience evaluated for

applicability during the period

g.

Corrective action documents generated for the following:

i.

Maintenance preventable functional failures which occurred or were

evaluated during the period

ii.

Adverse trends in equipment, processes, procedures, or programs which

were evaluated during the period

iii.

Action items generated or addressed by plant safety review committees

during the period

iv.

Problems related to Emergency Diesel Generators since July 2009.

- 2 -

Attachment B

3.

Logs and Reports

a.

Corrective action performance trending/tracking information generated during the

period and broken down by functional organization

b.

Corrective action effectiveness review reports generated during the period

c.

Current system health reports or similar information

d.

Radiation protection event logs during the period

e.

Security event logs and security incidents during the period (sensitive information

can be provided by hard copy during first week on site)

f.

Employee Concern Program (or equivalent) logs (sensitive information can be

provided by hard copy during first week on site)

g,

List of Training deficiencies, requests for training improvements, and simulator

deficiencies for the period

4.

Procedures

5.

a.

Corrective action program procedures, to include initiation and evaluation

procedures, operability determination procedures, apparent and root cause

evaluation/determination procedures, and any other procedures which implement

the corrective action program at RBS.

b.

Quality Assurance program procedures

c.

Employee Concerns Program (or equivalent) procedures

d.

Procedures which implement/maintain a Safety Conscious Work Environment

Other

a.

List of risk significant components and systems

b,

Organization charts for plant staff and long-term/permanent contractors

Note: "Corrective action documents" refers to condition reports, notifications, action requests,

cause evaluations, and/or other similar documents, as applicable to RBS.

As it becomes available, but no later than March 21, 2011, this information should be uploaded

on the Certrec IMS website and inform Mr. Michael Vasquez by email at

MichaeLVasquez@nrc.gov. Paper documents or electronic documents on CD I DVD may be

sent via overnight carrier to:

-3-

Attachment B

3.

Logs and Reports

a.

Corrective action performance trending/tracking information generated during the

period and broken down by functional organization

b.

Corrective action effectiveness review reports generated during the period

c.

Current system health reports or similar information

d.

Radiation protection event logs during the period

e.

Security event logs and security incidents during the period (sensitive information

can be provided by hard copy during first week on site)

f.

Employee Concern Program (or equivalent) logs (sensitive information can be

provided by hard copy during first week on site)

g,

List of Training deficiencies, requests for training improvements, and simulator

deficiencies for the period

4.

Procedures

5.

a.

Corrective action program procedures, to include initiation and evaluation

procedures, operability determination procedures, apparent and root cause

evaluation/determination procedures, and any other procedures which implement

the corrective action program at RBS.

b.

Quality Assurance program procedures

c.

Employee Concerns Program (or equivalent) procedures

d.

Procedures which implement/maintain a Safety Conscious Work Environment

Other

a.

List of risk significant components and systems

b,

Organization charts for plant staff and long-term/permanent contractors

Note: "Corrective action documents" refers to condition reports, notifications, action requests,

cause evaluations, and/or other similar documents, as applicable to RBS.

As it becomes available, but no later than March 21, 2011, this information should be uploaded

on the Certrec IMS website and inform Mr. Michael Vasquez by email at

MichaeLVasquez@nrc.gov. Paper documents or electronic documents on CD I DVD may be

sent via overnight carrier to:

-3-

Attachment B

Michael Vasquez

U.S. NRC Region IV

612 E. Lamar Blvd.

Suite 400

Arlington, TX 76011

Please note that the NRC is not currently able to accept electronic documents on thumb drives

or other similar digital media.

Note: After the request above was sent to RBS, Robert Hagar replaced Michael Vasquez as

the team lead.

- 4 -

Attachment B

Michael Vasquez

U.S. NRC Region IV

612 E. Lamar Blvd.

Suite 400

Arlington, TX 76011

Please note that the NRC is not currently able to accept electronic documents on thumb drives

or other similar digital media.

Note: After the request above was sent to RBS, Robert Hagar replaced Michael Vasquez as

the team lead.

- 4 -

Attachment B