1 WBN2Public Resource From:
Poole, Justin Sent:
Tuesday, June 07, 2011 11:20 AM To:
Epperson, Dan Cc:
WBN2HearingFile Resource
Subject:
FW: NRC Bucket List 6/9/11 Attachments:
NRC PM Open Items List 6-9-11.docx JustinC.Poole ProjectManager NRR/DORL/LPWB U.S.NuclearRegulatoryCommission (301)4152048 email:Justin.Poole@nrc.gov From: Crouch, William D [1]
Sent: Tuesday, June 07, 2011 7:21 AM To: Poole, Justin; Milano, Patrick; Campbell, Stephen Cc: Adair, James G; Arent, Gordon; Beach, Charles D; Bryan, Robert H Jr; Detchemendy, Thomas F; Elliott, Walter L Jr; Elton, Thomas L; Freeman, Edwin E; Glover, Christopher Edmund; Helms, Douglas F; Hemmer, Gerald L Jr; Henrich, Nolan T Jr; Hilmes, Steven A; Johnson, Robert M; Jones, Dennis Michael; Knuettel, Edward Terry; Koontz, Frank A Jr; Metzler, Ernest Thomas; Miller, Lee R; Olson, Peter Edwin; Riedl, Christopher John; Schlessel, Jerry V; Shea, Joe; Smith, James D; Snyder, Laura L; Spink, Thomas E; Stephenson, Catherine L; Stinson, Kelly David Jr; Stockton, Rickey A; Tinley, Mary Darlene; Woods, Steven E
Subject:
NRC Bucket List 6/9/11 Seeattached.
William D. (Bill) Crouch (423)3652004WBN (256)7777676Cell
Hearing Identifier:
Watts_Bar_2_Operating_LA_Public Email Number:
376 Mail Envelope Properties (19D990B45D535548840D1118C451C74D886EB32121)
Subject:
FW: NRC Bucket List 6/9/11 Sent Date:
6/7/2011 11:19:46 AM Received Date:
6/7/2011 11:19:57 AM From:
Poole, Justin Created By:
Justin.Poole@nrc.gov Recipients:
"WBN2HearingFile Resource" <WBN2HearingFile.Resource@nrc.gov>
Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov>
Tracking Status: None Post Office:
HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 1058 6/7/2011 11:19:57 AM NRC PM Open Items List 6-9-11.docx 37920 Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received:
Page 1 of 7 NRC PM Open Items List 6/9/11 (423) 751-6338 ID 657601 No.
Description Status Additional Comments Resp Org/Person
- 1.
Cyber Security Plan/Controls and Implementation Assess CDAs/Identify Mods 2/28/11A RAI Response 4/7/11A Plan for Common Systems 6/8/11 Identify Required Exemptions 6/8/11 Provide forecast for Inspection Readiness 6/8/11 Scope Mods 5/31/11A NRC TI issued TBD Update Cyber Security Plan IAW NEI 08-09 Rev 6 per NRC letter dated 5/24/10. NRC Inspection in 2011 Provide update to change commitment for April ready for Inspection Response to 3 Generic RAIs Provide detail for systems (unit specific and common) which will be complete and which will not be complete for Unit 2 fuel load.
Heinrich/Snyder (Bryan)
Page 2 of 7 No.
Description Status Additional Comments Resp Org/Person NRC Table Top/Pilot Oct 2011 Procedures complete 9/30/11 Inspection Dec 2011
- 2. Instrumentation RAI List (Knuettel)
Ongoing 5/20/11A 5/25/11A 6/17/11 6/3/11A RAI Responses Provide proprietary Westinghouse presentation Provide requested WINCISE Proprietary Documents.
Documents available in Westinghouse offices. See email dated 5/25/11 Provide non-prop WINCISE Document versions NRC review draft RAIs for deletions Eng/Hilmes (Smith)
- 3. Resolve Licensing Basis Preservation Self Assessment PERs (Crouch) 6/10/11 TVA to provide QA audit results Eng/Freeman (Smith)
- 4. Status of GSI 199 Eastern Seismicity (Crouch) 6/12/11 Close to upcoming Generic Letter TVA/NRR
- 5. Complete Implementation (Hemmer)
RAI Response 3/29/11A RAI Clarification for Fuel Question 2 5/9/10A Diesel Respond to RAI Implement two unit commitments.
Provide updated information for tables contained in the 6/29/07 and 7/1/10 letters.
Letter did not address Phase I commitments Diesel is onsite, need support equipment Hemmer (Smith)
Page 3 of 7 No.
Description Status Additional Comments Resp Org/Person 8/1/11 Pump Relocation 10/1/11 Procedures Issued 6/30/11 Inspection -
November 2011 Phase I commitments 8/1/11
- 6. Provide feedback on the status of NRC review of Integrated Safeguards Test submittal SSER 23 NRC to provide status of review in SSER 23 NRR
- 7. Document Control Issues for two letters 6/15/11 7/15, 10/5, 10/21 and 10/29 letters. NRC to reprint 7/15 letter and provide to NRC Document control.
TVA/Bechtel to provide non-proprietary version of documents that can be released to the public. TVA to provide revised letter that says non-prop once prop documents removed. NRC action to contact Kenny Nguyen, NRC Document Control regarding A102.
Licensing/Boyd
- 8. Chapter 15.5 RAIs 12/10/10A RAI response TBD Additional question regarding meteorology data from 2008-2009. Calc revisions required. TVA formulating plan/schedule. Small increases in doses expected except control room which will decrease.
Wastrack (Bryan)
- 9. Fire Protection Report Questions regarding OMA 3/31/11A 5/6/11A Justification Criteria Set 3 RAIs ENG/Hilmes (Crouch)
Page 4 of 7 No.
Description Status Additional Comments Resp Org/Person 5/18/11A 6/17/11 5/26/11A 6/7/11 6/21/11 FPR Justifications Set 4A RAIs Set 4B RAIs Set 5 RAIs
- 11. Environmental Phone call to discuss intake flow rate/velocity at IPS and SCCW in EIS versus NPDES.
4/28/11A Responded to RAI and attached revised Impingement Report Environmental/
Hopping (Bryan)
- 12. Tech Spec Revisions from latest T/S markup and NRC Review comments 5/10/11A 6/10/11 TBD TBD TBD Meeting Submittal to address NRC review comments CSST A & B I-131 DEI Diesel Generator Frequency Licensing/Elton (Bryan)
Are repairs/mods after N-5 controlled under Section III or Section XI? The timing for the NIS-2 in the letter does not comply with the ASME Code. The NIS-2 must be before commercial operation.
Review Code Cases 801/802 vs TVA letter for conflicts.
Eng/Helms (Crouch)
- 14. Chapter 15 RAI on Dose calc basis 6/6/11A Bechtel (Fredrick) preparing answer.
Eng/Koontz (Bryan)
- 15. Chapter 11/FSEIS RAIs 5/11/11A 5/20/11A Public Meeting 5/11/11 Chapter 11/EIS Letter Chem/Woods (Bryan)
Page 5 of 7 No.
Description Status Additional Comments Resp Org/Person 6/3/11A 5/26/11A 5/26/11A TBD 7/29/11 X/Q info in FSAR A104 Chapter 11 RAI List X/Q to 50 miles NRC Computer Code Input Request Cost Benefit Analyses
- 16. Hydrology sand bag question 4/20/11A 5/11/11A 5/20/11A 6/1/11A Five RAI questions NRC Visit to Knoxville/TVA dam NRC Info Request NRC Calc Request and PER Summary Corp/Selman
- 17. Letter to notify NRC when Vital Area Boundary returned to original location 6/6/11A 11/1/11 Date for schedule. Boundary to be restored by 9/30/11 Security Plan Update Lic/Crouch
- 18. Part 70 License 6/13/11 4/29/11 NRC to issue Part 70 license.
NRC question related to dry versus wet storage.
TVA issued letter regarding placement of new Unit 2 fuel in new fuel vault and SFP.
Milano
- 19. ACRS Topics 7/12/11 Improvements, Inspection status, Refurb status, Construction Status, Japan, IST Re-Presentation, Cyber Security, Ch 7 digital upgrades
- 20. SAMDA RAIs 05/11/11A 05/13/11A 5/25/11A 6/14/11 Meeting on 5/11/11 1st Submittal 2nd Submittal 5 questions regarding 2nd submittal
Page 6 of 7 No.
Description Status Additional Comments Resp Org/Person
- 21. SSER 22/23 Open Items Response 6/7/11 Addresses 10 Open Items - Need item 69 clarification
- 22. Chapter 12 RAI on Instrument Channel Operability Tests 6/24/11 ENG/Hilmes
- 23. Transient Analysis issues Overpressurization Boron Info Inadvertent SI CVCS Malfunction Steam line break Proprietary review of audit report Audit Report Response Audit Report Follow up Questions Additional Follow up Audit 4/1/11A 3/25/11A 4/29/11A 4/29/11A 5/13/11A 4/22/11A 5/13/11A 5/24/11A 6/28-30/11 TVA/WEC confirming availability of personnel ENG/Koontz WEC/Morgan
- 26. NRR/Region assign SSER 22 items 1, 4, 7, 9, 11, 19, 21, 38 5/17/11A Issue resolved at 5/17/11 NRC meeting Milano
- 27. FSAR A104 6/3/11A Lic/Stockton
- 28. IEB 88-02 SG Tube Cracking TBD What are the SG inspection plans in light of the experience with a French reactor exhibiting SG tube cracking early? Is TVA planning to change the inspection plan due to this operating experience?
Corp SG/
Webber ISI/Tinley
- 29. Develop list of planned License Conditions, Exemptions and Relief Requests (Crouch) 9/1/11 Review Unit 1 SER for exemptions.
NRR/TVA (Bryan)
- 30. Submit final REP prior to fuel load (Spink)
Complete NRR to determine if submittal has to occur before License rather than before fuel load.
EP/
Detchemendy
Page 7 of 7 No.
Description Status Additional Comments Resp Org/Person Complete 10/1/11
- 1. Fix Section 6.0, Event 6.2 in Rev 92xx.
(Bryan)
- 31. Issue two Unit Offsite Dose Calculation Manual (Beach) Review TS Chapter 5 programs also 9/1/11 Chemistry/
Woods (Bryan)
- 33. Issue Unit 2 Completion Letter (Crouch) 3/1/12 Licensing
- 34. Combined U1/U2 FSAR (Stockton) 3/1/12 Licensing
- 35. Submit final as-constructed FSAR figures 10/1/11 Licensing/
Stockton
- 36. Verify Tech Spec Setpoints match calcs 8/1/11 Eng/Hilmes (Bryan)
- 37. Letter to terminate Part 30/40 License after receipt of Part 50 License 4/1/12 Licensing (Crouch)
- 38. Discuss IPS velocity calc at 5/11 mtg 5/11/11A 5/19/11A Discussed at meeting Provide submittal to describe intake configuration Lic (Bryan)
- 39. Provide date of Unit 1 PASS T/S submittal and NRC SER date 5/3/11A Provide NRC SER to NRR via e-mail Licensing/
Stockton (Crouch)
- 40. Provide feedback on need to revise submittal regarding testing of non-EQ hand switches.
5/4/11A See e-mail from Crouch dated 5/2/11.
NRR reviewed determined no need to revise submittal or NRC July 2 letter.
Milano