Letter Sequence RAI |
---|
|
|
MONTHYEARML1109400572011-03-29029 March 2011 R. E. Gina - Biennial Report: Status of Decommissioning Funding Project stage: Request ML1114602102011-05-26026 May 2011 R. E. Ginna and Nine Mile Point, Units 1 and 2 Decommissioning Funding Status Report - Request for Additional Information Project stage: RAI ML11187A3022011-06-24024 June 2011 Response to Request for Additional Information on Status of Decommissioning Funding Project stage: Response to RAI 2011-05-26
[Table View] |
|
---|
Category:Request for Additional Information (RAI)
MONTHYEARML24012A0492024-01-11011 January 2024 Request for Additional Information Regarding Final Response to Generic Letter 2004-02 ML23312A1302023-11-0707 November 2023 Final Rci/Rai - Constellation R. E. Ginna Nuclear Power Plant - Exemption from Security Rule (EPID L-2023-LLE-0029) (Email) ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC Fleet Request License Amendment Request to Adopt TSTF-580, Revision 1 ML23219A1662023-08-16016 August 2023 Request for Additional Information Regarding Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping (EPID: L-2023-LLR-0006) - Non-proprietary ML23205A2432023-07-19019 July 2023 NRC Staff Follow-up Question on Audit Question 18 TSTF-505 and 50.69 Regulatory Audit (E-mail Dated 7/19/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23160A0222023-06-0606 June 2023 NRR E-mail Capture - Calvert Cliffs - Long Term Coupon Surveillance Program RAI ML23156A0102023-06-0404 June 2023 NRR E-mail Capture - Calvert Cliffs - RAI License Amendment Request for Emergency Desiel Generator ML23087A2912023-03-28028 March 2023 Request for Additional Information (3/28/2023 E-mail) - Proposed Emergent I5R-11 Alternative Associated with a Weld Overlay on RPV Recirculation Nozzle N2E DM Weld ML23061A0522023-03-0202 March 2023 Request for Additional Information (3/2/2023 E-mail) - Proposed Alternative Associated with a Weld Overlay Repair to the Torus ML23012A2002023-01-13013 January 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000220/2023401 and 05000410/2023401 ML22207A2162022-07-26026 July 2022 Information Request to Support Triennial Baseline Design-Basis Capability of Power-Operated Valves Inspection; Inspection Report 05000220/2022010 and 05000410/2022010 ML22194A9412022-07-13013 July 2022 Request for Additional Information Relief Request CS-PR-02 (7/13/2022 e-mail) ML22179A2112022-06-28028 June 2022 Notification of Conduct of a Fire Protection Team Inspection ML22160A3962022-06-0909 June 2022 R. E. Ginna Nuclear Power Plant, LLC - Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000244/2022010 ML22129A0132022-05-0606 May 2022 NRR E-mail Capture - Draft RAIs for Requests for Alternatives I4R-17, I4R-23, ISI-05-018, I6R-10 ML22271A0772022-05-0606 May 2022 NRR E-mail Capture - Final RAIs 9.1.2021 Constellation Relief Request ML22091A0852022-04-0101 April 2022 NRR E-mail Capture - Braidwood and Byron - Final RAI Regarding Proposed Alternative for Various Pressurizer Welds (EPID L-2021-LLR-0035 and 0036) ML22091A2392022-04-0101 April 2022 NRR E-mail Capture - Calvert Cliffs - Formal RAI for Proposed Alternative for Examinations of Certain Pressurizer Welds ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21320A3472021-11-16016 November 2021 Request for Additional Information LAR to Revise TSs to Adopt TSTF-582, Revision 0 ML21308A5592021-11-0404 November 2021 NRR E-mail Capture - NRC Request for Additional Information for Ginna Biennial EP Exercise Exemption Request ML21306A3312021-11-0202 November 2021 Request for Additional Information Alternative Request GV-RR-10 (11/2/2021 e-mail) ML21287A0322021-10-13013 October 2021 Request for Additional Information Re Proposed Alternative for Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds ML21287A0932021-10-0505 October 2021 Request for Additional Information: Calvert Cliffs 1 & 2 LAR to Revise Spent Fuel Pool Cooling - Shutdown Cooling Systems Licensing Basis (EPID L-2021-LLA-0112) (Email) ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21187A2232021-07-29029 July 2021 Temporary Instruction 2515/194 Inspection Documentation Request ML21189A1602021-07-0808 July 2021 NRR E-mail Capture - Request for Additional Information - Braidwood, Byron, and Ginna - Amendment to Address the Issues in Westinghouse NSALs ML21180A1562021-06-28028 June 2021 Request for Additional Information Regarding License Amendment Request Concerning Containment Sump ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21130A0382021-05-21021 May 2021 Memo to File - Draft Request for Additional Information Relief Request CISI-03-01 Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements ML21117A0342021-05-0505 May 2021 Request for Additional Information Regarding Proposed Alternative to Use ASME Code Case N-893 ML21125A1282021-05-0404 May 2021 OPC Document Request - Feb 2021 ML21119A1082021-04-27027 April 2021 Ti 2515/194 Inspection Documentation Request ML21110A5112021-04-20020 April 2021 Request for Additional Information Review of License Amendment Request to Revise Technical Specifications to Adopt TSTF-582 ML21088A2682021-03-30030 March 2021 Notification of Conduct of a Fire Protection Team Inspection ML21076A5152021-03-17017 March 2021 R. E. Ginna Nuclear Power Plant - RAI Steam Generator LAR to Revise Technical Specifications for Steam Generator Tube Inspection Frequency (EPID L-2020-LLA-0207) (e-mail) ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21053A3142021-02-22022 February 2021 Information Request for a Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000317/2021010 and 05000318/2021010 ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21029A3302021-01-29029 January 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative Request to Use ASME Code Case N-885 ML20365A0092020-12-30030 December 2020 Request for Additional Information Concerning Review of License Amendment Request and Relief Request to Change Excess Flow Check Valve Testing Frequency (EPIDs L-2020-LLA-0188 and L-2020-LLR-0114) ML20358A2602020-12-28028 December 2020 Changes to Draft Request for Additional Information Regarding License Amendment Request and Relief Request to Change Excess Flow Check Valve Testing Frequency ML20357A2232020-12-17017 December 2020 Update on Ginna POV - 3504A and 4562 (Email Request for Inspection Information) ML20275A0032020-09-30030 September 2020 Request for Additional Information Regarding Alternative Request Re Inservice Inspection Impracticality (L-2020-LLR-0089) ML20272A2802020-09-28028 September 2020 Withdrawal and Replacement of Request for Additional Information to Support Review of License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times ML20248H5192020-09-28028 September 2020 Changes to Draft Request for Additional Information Regarding Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times ML20246G6362020-09-0202 September 2020 Request for Additonal Information to Support Review of License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times NMP2L2739, Request for Additional Information for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 22020-08-28028 August 2020 Request for Additional Information for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 ML20239A7982020-08-25025 August 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet License Amendment Request to Adopt TSTF-568, Revision 2 2024-01-11
[Table view] Category:Letter
MONTHYEARIR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 IR 05000317/20230042024-02-0101 February 2024 Integrated Inspection Report 05000317/2023004 and 05000318/2023004 NMP1L3570, Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-02-0101 February 2024 Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation IR 05000220/20230042024-02-0101 February 2024 Integrated Inspection Report 05000220/2023004 and 05000410/2023004 ML24029A0102024-01-29029 January 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000317/2024010 and 05000318/2024010 ML24026A0112024-01-26026 January 2024 R. E. Ginna Nuclear Power Plant, Relief Request Associated with Inservice Testing of B Auxiliary Feedwater Pump NMP1L3569, CFR 50.46 Annual Report2024-01-26026 January 2024 CFR 50.46 Annual Report ML24003A8872024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0033 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000318/LER-2023-004, Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-16016 January 2024 Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer ML24011A0732024-01-11011 January 2024 Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping 05000318/LER-2023-002, Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-0808 January 2024 Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer 05000318/LER-2023-003, Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip2024-01-0808 January 2024 Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip ML24004A2122024-01-0808 January 2024 Senior Reactor and Reactor Operator Initial License Examinations ML24005A0222024-01-0505 January 2024 Revised Steam Generator Tube Inspection Reports ML23354A0012024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0059 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23304A0642024-01-0202 January 2024 Issuance of Amendment No. 349 to Modify the Long-Term Coupon Surveillance Program IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 ML23348A0992023-12-15015 December 2023 R. E. Ginna Nuclear Power Plant Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0029 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines IR 05000410/20243012023-12-14014 December 2023 Initial Operator Licensing Examination Report 05000410/2024301 NMP1L3566, Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station2023-12-14014 December 2023 Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23347A0092023-12-13013 December 2023 Annual Commitment Change Notification ML23346A0142023-12-12012 December 2023 LLC - Senior Reactor and Reactor Operator Initial License Examinations ML23341A1252023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23291A4642023-12-0707 December 2023 Issuance of Amendment No. 251 Regarding the Adoption of Title 10 the Code of Federal Regulations Section 50.69, Risk-Informed Categorization and Treatment of SSC for Nuclear Power Plants NMP1L3564, Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements2023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements RS-23-125, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) ML23289A0122023-12-0606 December 2023 Issuance of Amendment No. 250 Regarding the Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b NMP1L3563, Submittal of Relief Request I5R-12, Revision 0, Concerning the Installation of a Full Structural Weld Overlay on Reactor Pressure Vessel Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld (32-WD-208)2023-12-0404 December 2023 Submittal of Relief Request I5R-12, Revision 0, Concerning the Installation of a Full Structural Weld Overlay on Reactor Pressure Vessel Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld (32-WD-208) IR 05000220/20234022023-11-28028 November 2023 Security Baseline Inspection Report 05000220/2023402 and 05000410/2023402 ML23331A2992023-11-27027 November 2023 Submittal of Condition Prohibited by Technical Specifications Due to Failure to Sample Diesel Generator Fuel Oil Storage Tank NMP1L3557, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-22022 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000317/20230102023-11-20020 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000317/2023010 and 05000318/2023010 ML23321A1392023-11-17017 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information and Request for Additional Information ML23318A4722023-11-14014 November 2023 Supplement to License Amendment Request to Adopt TSTF-59-A ML23317A1032023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23310A0442023-11-0707 November 2023 Project Manager Assignment IR 05000317/20230402023-11-0202 November 2023 95001 Supplemental Inspection Report 05000317/2023040 and Follow-Up Assessment Letter IR 05000317/20230032023-11-0101 November 2023 Integrated Inspection Report 05000317/2023003 and 05000318/2023003 IR 05000220/20234202023-11-0101 November 2023 Security Baseline Inspection Report 05000220/2023420 and 05000410/2023420 ML23305A0052023-11-0101 November 2023 Operator Licensing Examination Approval IR 05000317/20230902023-10-26026 October 2023 Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation; Inspection Report 05000317/2023090 IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 IR 05000220/20230032023-10-25025 October 2023 Integrated Inspection Report 05000220/2023003 and 05000410/2023003 ML23292A0282023-10-19019 October 2023 LLC - Notification of Conduct of a Fire Protection Team Inspection IR 05000220/20235012023-10-17017 October 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000220/2023501 and 05000410/2023501 IR 05000220/20230112023-10-16016 October 2023 Comprehensive Engineering Team Inspection Report 05000220/2023011 and 05000410/2023011 2024-02-05
[Table view] |
Text
,,~,..l\ REOU, _ UNITED STATES
~
.;:,V -v'"°11 NUCLEAR REGULATORY COMMISSION
- J
...C'> WASHINGTON, D.C. 20555-0001
<< 0
~ !Ii:
.t'
~ Ii;
~ ~ May 26, 2011 1-" ¥>O
- "" Mr. Stephen Mormann Vice President - Financial Services and Treasurer Constellation Energy Nuclear Group, LLC 100 Constellation Way, Suite 200C Baltimore, MD 21202
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION REGARDING DECOMMISSION FUNDING STATUS REPORT FOR CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NOS. 1 AND 2, R. E. GINNA NUCLEAR POWER PLANT, AND NINE MILE POINT NUCLEAR STATION, UNIT NOS. 1 AND 2 (TAC NOS.
ME5463. ME5464, ME5486, ME5504, AND ME5505)
Dear Mr. Mormann:
By letter dated March 29, 2011, Constellation Energy Nuclear Group, LLC (CENG), submitted its 2011 Decommissioning Funding Status Report for Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2, R. E. Ginna Nuclear Power Plant, and Nine Mile Point Nuclear Station, Unit Nos.
1 and 2, as required under Title 10 of the Code of Federal Regulations, Section 50.75(f)(1).
The Nuclear Regulatory Commission (NRC) staff is reviewing the submittals and has determined that additional information for the subject plants is needed to support its review, Enclosed is the NRC staff's request for additional information (RAI), The RAI was discussed with your staff on May 19, 2011, and it was agreed that your response would be provided within 30 days from the date of this letter.
Sincerely, Richard V. Guzman, Senior Project Manager Plant licensing Branch 1-1 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket Nos. 50-317, 50-318, 50-244, 50-220 and 50-410
Enclosure:
As stated cc w/encl: Distribution via listserv
REQUEST FOR ADDITIONAL INFORMATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION 2011 DECOMMISSIONING FUNDING STATUS REPORT FOR CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NOS. 1 AND 2; R. E. GINNA NUCLEAR POWER PLANT, AND NINE MILE POINT NUCLEAR STATION, UNIT NOS. 1 AND 2 The Request for Additional Information (RAI) provided is in response to the Constellation Energy Nuclear Group's (CENG) 2011 Decommissioning Funding Status (DFS) Report. On March 29, 2011, CENG submitted to the Nuclear Regulatory Commission (NRC) the 2011 DFS report for Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2, (Calvert 1 and 2), R. E. Ginna Nuclear Power Plant (Ginna), and Nine Mile Point Nuclear Station, Unit Nos. 1 and 2 (Nine Mile 1 and 2), as required under Title 10 of the Code of Federal Regulations (10 CFR) Section 50.75(f)(1) (Agencywide Documents Access and Management System (ADAMS) Accession No. ML110940057). The NRC staff has determined that additional information requested below will be needed to complete its review.
RAI-1: Minimum Decommissioning Funding Assurance Calculation CENG and Long Island Power Authority (LlPA):
Provide the labor, energy, and burial factors used in your calculation of the minimum requirement for decommissioning financial assurance and, if necessary, a corrected submittal for that part of the DFS Report.
On March 29, 2011, CENG reported the amounts of decommissioning funds estimated to be required under 10 CFR 50.75(b) and (c) that are less than the amount calculated by the NRC staff for the afore-mentioned plants. Also, LlPA reported the amount of decommissioning funds estimated under 10 CFR 50.75(b) and (c) that are less than the amount calculated by the NRC staff for its share of Nine Mile Point 2.
According to 10 CFR 50.75(f)(1), the amount provided in the DFS Report should be "the amount of decommissioning funds estimated to be required under 10 CFR 50.75(b) and (c)."
The formulas for the factors used by the staff can be found using NUREG-1307, Rev. 14, "Report on Waste Burial Charges: Changes in Decommissioning Waste Disposal Costs at Low Level Waste Burial Facilities." For example, the calculations for the Labor and Energy Adjustment Factors can be found on pages 7 and 8 of NUREG-1307, Rev. 14.
Enclosure
-2 RAI-2: Basis for Real Rate of Returns CENG:
Provide the basis for the assumptions used regarding rates of escalation in decommissioning costs, rate of earnings on decommissioning funds, and rates of other factors assumed in the DFS Report.
On March 29, 2011, CENG reported the following:
6 percent rate of earnings on decommissioning funds, and 4 percent rate of escalation in decommissioning costs.
Provide the citation (e.g, an Order by the rate-regulatory authority) by the regulatory entity that allows for the assumptions used regarding rates of escalation in decommissioning costs, rate of earnings on decommissioning funds and rates of other factors assumed in the DFS Report for LlPA's 18-percent ownership of Nine Mile 2.
On March 29, 2011, CENG reported the following for LlPA:
6 percent rate of earnings on decommissioning funds, and 4 percent rate of escalation in decommissioning costs.
As stated in 10 CFR 50.75(f)(1):
The information in [the DFS] report must include [...] the assumptions used regarding rates of escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates of other factors used in funding projections ...
RAI-3: After Tax Decommissioning Funds as of December 31, 2010 Clarify if the amounts of decommissioning funds in the CENG and LlPA trust funds are the after tax amount of funds accumulated through December 31, 2010. If not, provide the after-tax amount of decommissioning funds accumulated through December 31,2010.
CENG and LlPA reported the amounts of decommissioning funds accumulated as of December 31, 2010, but did not indicate if the amounts stated are the before or after-tax balances.
The provisions of 10 CFR 50.75(f)(1) and (2) require the licensee to report the amount of funds accumulated to the end of the calendar year preceding the report.
- 3 RAI-4: Past Contributions CENG:
Provide the annual amount of contributions deposited in the trust funds for radiological decommissioning, as defined in 10 CFR 50.2, starting in 1999 for Calvert 1 and 2, Ginna, and Nine Mile 1 and 2.
In a July 29,2009, letter from CENG to NRC (ADAMS Accession No. ML092160414), CENG stated "[t]hat for 2009, it contributed $18.7 million to the trust for the two CCNPP reactors."
CENG also stated that "[s]ome degree of annual contributions will be needed through 2013."
Provide the annual amount deposited in the trust fund for decommissioning, as defined in 10 CFR 50.2, starting in 1999 for Nine Mile 2.
In a July 29,2009, letter from CENG to NRC (ADAMS Accession No. ML092160414), CENG stated that, " ... (LlPA) will contribute $616,000 annually to the NMPNS Unit 2 decommissioning trust."
Pursuant to 10 CFR 50.75(e)(2), the NRC reserves the right to review the accumulation of decommissioning funds.
May 26,2011 Mr. Stephen Mormann Vice President - Financial Services and Treasurer Constellation Energy Nuclear Group, LLC 100 Constellation Way, Suite 200C Baltimore, MD 21202 SUB-JECT: REQUEST FOR ADDITIONAL INFORMATION REGARDING DECOMMISSION FUNDING STATUS REPORT FOR CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NOS. 1 AND 2, R. E. GINNA NUCLEAR POWER PLANT, AND NINE MILE POINT NUCLEAR STATION, UNIT NOS. 1 AND 2 (TAC NOS.
MES463, MES464, MES486, MESS04, AND MESSOS)
Dear Mr. Mormann:
By letter dated March 29, 2011, Constellation Energy Nuclear Group, LLC (CENG), submitted its 2011 Decommissioning Funding Status Report for Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2, R. E. Ginna Nuclear Power Plant, and Nine Mile Point Nuclear Station, Unit Nos.
1 and 2, as required under Title 10 of the Code of Federal Regulations, Section SO. 7S(f)(1).
The Nuclear Regulatory Commission (NRC) staff is reviewing the submittals and has determined that additional information for the subject plants is needed to support its review.
Enclosed is the NRC staff's request for additional information (RAI). The RAI was discussed with your staff on May 19, 2011, and it was agreed that your response would be provided within 30 days from the date of this letter.
Sincerely, Ira!
Richard V. Guzman, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. SO-317, SO-318, SO-244, 50-220 and 50-410
Enclosure:
As stated cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrPMNinelVlilePoint RidsNrrPMCalvertCliffs RidsNrrLASLittle LPLI-1 R/F RidsNrrPMGinna RidsRgn1 MailCenter RidsNrrDprPfp RidsOGCRp JSimpson, NRR MDusaniwskyj. NRR MPurdie. NRR ASimmons. NRR Accession Number: ML111460210 *RAlln ut NRR-088 FICE LPL 1-1/PM LPL 1-1/PM LPL 1-1/BC A)
ME RGuzman DPickett SUttle JBoska TE 5/26/11 5/26/11 5/26/11 5/26/11 OFFICIAL RECORD COPY