Letter Sequence RAI |
---|
|
|
MONTHYEARML1109102402011-03-28028 March 2011 Decommissioning Financial Assurance Project stage: Request ML11129A0072011-05-0505 May 2011 NRR E-mail Capture - FW: ME5494; ME5501 and 02; ME5506 and 07; ME5540 and 41 - 2011 Decommissioning Funding Status (DFS) Report - Request for Additional Information (RAI) Project stage: RAI ML11132A1712011-06-0909 June 2011 Request for Additional Information Regarding Decommissioning Financial Assurance Project stage: RAI ML1118101552011-06-14014 June 2011 Submittal of Decommissioning Funding Status Report: Response to Request for Addition Information Project stage: Request ML11192A0012011-07-0808 July 2011 NRR E-mail Capture - North Anna Power Station, Unit 1 & 2 - Odec'S RAI Responses Decommissioning Financial Assurance Project stage: Other 2011-06-14
[Table View] |
|
---|
Category:Letter
MONTHYEARML24302A2402024-10-28028 October 2024 CFR 21 Report 1-BY-BC-1-LV Battery Charger IR 05000338/20240032024-10-28028 October 2024 – Integrated Inspection Report 05000338-2024003 and 05000339-2024003 ML24302A2342024-10-23023 October 2024 Request for Project Number Related to Dominion Energy Services New Nuclear Program at North Anna Power Station ML24283A0392024-10-0909 October 2024 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.D ML24281A1372024-10-0707 October 2024 ISFSI - Submittal of Cask Registration for Spent Fuel Storage 05000338/LER-2024-001-01, Automatic Reactor Trip Due to Prni High Negative Rate2024-09-24024 September 2024 Automatic Reactor Trip Due to Prni High Negative Rate IR 05000338/20244202024-09-23023 September 2024 Security Baseline Inspection Report 05000338/2024420 and 05000339/2024420, Cover Letter ML24243A0872024-09-20020 September 2024 Response to EPA Comments Regarding the Final Site Specific Supplement to the Generic Eist for License Renewal North Anna Power Station, Units 1 and 2 IR 05000338/20244022024-09-17017 September 2024 Security Baseline Inspection Report 05000338/2024402 and 05000339/2024402 ML24215A2622024-08-28028 August 2024 Transmittal Letter for Subsequent Renewed License IR 05000338/20240052024-08-27027 August 2024 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2024005 and 05000339/2024005) 05000339/LER-2024-001-01, Loss of Generator Field for 2J Eog During 2-PT-82.282024-08-20020 August 2024 Loss of Generator Field for 2J Eog During 2-PT-82.28 ML24234A0742024-08-15015 August 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Letter OG-23-63, NEI 03-08 Needed Guidance: PWR Thermal Shield Flexure Inspection Requirements ML24221A1932024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Upper Mattaponi Tribe ML24221A1882024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Monacan Indian Nation ML24206A0052024-08-0808 August 2024 SLR Final EIS Letter to Achp ML24221A1842024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Nation, Oklahoma ML24221A1912024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Rappahannock Tribe, Inc ML24221A1942024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-United Keetoowah Band of Cherokee Indians in Oklahoma ML24221A1922024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Tuscarora Nation of New York ML24221A1852024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Tribe of Indians ML24221A1832024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Chickahominy Indian Tribe-Eastern Division ML24206A0062024-08-0808 August 2024 Notice of Availability of the Final Environmental Impact Statement for the North Anna Nuclear Power Station Unit Numbers 1 and 2 Subsequent License Renewal (Docket Numbers: 50-338 and 50-339) ML24163A3002024-08-0808 August 2024 Request for Relief Request N1-I5-NDE-007 Inservice Inspection Alternative ML24208A0142024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-Absentee-Shawnee Tribe of Indians of Oklahoma ML24221A1872024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Shawnee Tribe of Oklahoma ML24221A1862024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Band of Cherokee Indians ML24221A1812024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Catawba Indian Nation ML24221A1822024-08-0808 August 2024 Tribal Section 106 Letters - North Anna - Chickahominy Indian Tribe ML24221A1902024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Pamunkey Indian Tribe ML24221A1892024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Nansemond Indian Nation ML24241A0692024-08-0606 August 2024 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000338/20240022024-08-0202 August 2024 Integrated Inspection Report 05000338/2024002 and 05000339/2024002 ML24206A0432024-07-26026 July 2024 Feis - Letter to the Applicant 05000338/LER-2024-001, Automatic Reactor Trip Due to Prni High Negative Rate2024-07-25025 July 2024 Automatic Reactor Trip Due to Prni High Negative Rate ML24206A0902024-07-24024 July 2024 Owners Activity Report ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24143A1622024-06-12012 June 2024 – Correction to Issuance of Amendment Nos. 297 and 280 and Surry Units 1 and 2, Correction to Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code ML24165A1462024-06-0505 June 2024 Loss of Generator Field for 2J EDG During 2-PT-82.28 05000339/LER-2024-001, Loss of Generator Field for 2J EDG During 2-PT-82.282024-06-0505 June 2024 Loss of Generator Field for 2J EDG During 2-PT-82.28 IR 05000338/20240012024-05-10010 May 2024 Integrated Inspection Report 05000338/2024001 and 05000339/2024001 IR 05000338/20244032024-04-30030 April 2024 – Security Baseline Inspection Report 05000338-2024403 and 05000339-2024403 ML24054A0142024-04-22022 April 2024 Issuance of Amendment Nos. 297 and 280, and Surry Power Station Unit Nos. 1 and 2, Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24110A1502024-04-18018 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report ML24110A1392024-04-18018 April 2024 Annual Environmental Operating Report ML24110A1462024-04-18018 April 2024 Independent Spent Fuel Storage Installation (Sfsi) - Annual Radiological Environmental Operating Report ML24087A0572024-04-16016 April 2024 Correction to Issuance of Amendment Nos. 296 and 279 ML24088A2692024-03-27027 March 2024 Core Operating Limits Report Cycle 31 Pattern Sos Revision 0 2024-09-24
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24087A0112024-03-23023 March 2024 NRR E-mail Capture - Draft RAIs for Reactor Coolant Pump (RCP) Relief Request (L-2024-LLR-0022) ML23318A1172023-11-13013 November 2023 NRR E-mail Capture - Formal Issuance of RAIs for North Anna Technical Support Center (TSC) License Amendment Request (LAR) (L-2023-LLA-0006) ML23257A2092023-09-14014 September 2023 NRR E-mail Capture - Formal Issuance of 2nd Round RAIs for Surry Units 1&2 and North Anna Units 1&2 Emergency Plans LAR ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23219A1602023-08-0707 August 2023 003 Radiation Safety Baseline Inspection Information Request ML23171B0522023-06-20020 June 2023 NRR E-mail Capture - RAI for Review of Appendix F to DOM-NAF-2-P (Redacted) ML23081A5282023-04-26026 April 2023 Request for Additional Information - North Anna Subsequent License Renewal Application Environmental Review ML23075A0232023-03-15015 March 2023 NRR E-mail Capture - RAI - License Amend Req (LAR) to Revise Tech Spec (Ts) 3.6.8 Limiting Condition for Operation to Remove Refueling Water Chemical Addition Tank and Replace the Containment Sump Buffer North Anna, 1 and 2 (L-2022-LLA-0162 ML23060A0932023-03-0101 March 2023 NRR E-mail Capture - Formal Issuance of RAIs for Surry/North Anna Emergency Plans LAR ML23059A2282023-02-28028 February 2023 NRR E-mail Capture - Draft RAIs for Containment Buffer Change to Natb (L-2022-LLA-0162) ML22251A1292022-09-0909 September 2022 Request for Additional Information Related to Response to Generic Letter 2004-04 ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) ML22083A2102022-03-24024 March 2022 NRR E-mail Capture - Draft RAI - Relief Request N2-14-LMT-003 Fourth Ten Year Inservice Inspection Interval ML21327A3652021-11-23023 November 2021 NRR E-mail Capture - Draft RAI for TSTF-577 LAR ML21322A0962021-11-18018 November 2021 Final Request for Additional Information Set 5 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21322A0992021-11-18018 November 2021 Final Request for Additional Information Set 5 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21256A0672021-09-13013 September 2021 Final Request for Confirmation of Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21256A0692021-09-13013 September 2021 Final Request for Confirmation of Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Request for Confirmation of Information ML21238A0942021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21238A0982021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21225A5022021-08-13013 August 2021 Request for Additional Information for North Anna Power Station, Units 1 and 2, Surry Power Station, Units 1 and 2, and Millstone Power Station, Units 2 and 3, Appendix E of Fleet Report Com-Naf-2 (EPID:L02021-LLT-0000) Public Version ML21195A2442021-07-13013 July 2021 NRR E-mail Capture - Draft RAI Appendix E to Topical Report DOM-NAF-2 Qualification of the Framatome BWU-I CHF Correlation in the Dominion Energy VIPRE-D Computer Code ML21188A1632021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21188A1652021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21174A1952021-06-23023 June 2021 Safety RAIs - Set Y - Draft - Enclosure ML21166A3512021-06-15015 June 2021 Safety RAIs - Set 4 - Draft ML21123A2972021-05-0303 May 2021 Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - E-mail ML21123A2982021-05-0303 May 2021 Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21091A0032021-04-0101 April 2021 Final Request for Additional Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure 1 - RAIs ML21091A0042021-04-0101 April 2021 SLRA Safety Review - Withdrawn Requests for Information (EPID No. L-2020-SLR-0000) - Enclosure 2 ML21076A4622021-03-17017 March 2021 NRR E-mail Capture - Draft RAI for Versatile Internals and Component Program for Reactors Vipre Code Review (L-2021-LLT-0000) ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 ML21063A5602021-03-0404 March 2021 Final Request for Additional Information Set 1 - North Anna SLRA Safety Review (EPID L-2020-SLR-0000) - Enclosure ML21049A0212021-02-17017 February 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000338/2021012 and 05000339/2021012) and Request for Information (RFI) ML21028A3902021-01-29029 January 2021 Request for Additional Information - North Anna Subsequent License Renewal Application Environmental Review (EPID Number: L-2020-SLE-0000) (Docket: 50-338 and 50-339) ML21028A4352021-01-28028 January 2021 Notification of Target Set Inspection and Request for Information (NRC Inspection Report No. 05000338/2021404 and 05000339/2021404) ML21012A3412021-01-22022 January 2021 Requests for Confirmation of Information for the Environmental Review of the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application (EPID Number: L-2020-SLE-0000) (Docket: 50-338 and 50-339) ML21019A4512021-01-19019 January 2021 Notification of Inspection and Request for Information ML20316A0422020-11-10010 November 2020 NRR E-mail Capture - FW: Draft RAI for North Anna Unit 2 Steam Generator Tube Inspection Report (ML19179A075) ML20223A3412020-08-10010 August 2020 003 Radiation Safety Baseline Inspection Information Request ML20218A4282020-08-0505 August 2020 Notification of Inspection and Request for Information ML20125A0762020-05-0101 May 2020 NRR E-mail Capture - Draft RAI Related to Revised Reactor Vessel Material Surveillance Capsule Withdrawal Schedule Dominion Energy Virginia North Anna Power Station Units 1 and 2 (L-2020-LLL-0038) ML20113A5792020-04-21021 April 2020 NRR E-mail Capture - Draft RAI North Anna Fifth 10-year Interval Relief Request (L-2020-LLR-0023) ML19354B6142019-12-20020 December 2019 NRR E-mail Capture - Draft RAI for North Anna Relief Request P-9 ML19317F1042019-11-0707 November 2019 NRR E-mail Capture - Draft RAIs for SB LOCA LAR (Non Prop) ML19191A2512019-07-10010 July 2019 NRR E-mail Capture - Request for Additional Information Open Phase Condition LAR ML19169A0962019-06-17017 June 2019 NRR E-mail Capture - Request for Additional Information Emergency Action Level Scheme Change for Millstone Power Station - Units 1, 2, and 3, North Anna Power Station - Units 1 and 2, and Surry Power Station - Units 1 and 2 ML19162A0052019-06-10010 June 2019 NRR E-mail Capture - Draft RAIs for Dominion EAL Scheme Change ML19108A1902019-04-18018 April 2019 Emergency Preparedness Program Inspection Request for Information ML19060A2432019-03-0101 March 2019 Related to License Amendment Request to Address Open Phase Conditions 2024-03-23
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 June 9, 2011 Mr. Robert L. Kees Senior Vice President and Chief Financial Officer Old Dominion Electric Cooperative Innsbrook Corporate Center 4201 Dominion Boulevard Glen Allen, VA 23060
SUBJECT:
NORTH ANNA POWER STATION, UNIT NOS. 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION REGARDING DECOMMISSIONING FINANCIAL ASSURANCE (TAC NOS. MESS06 AND MESS07)
Dear Mr. Kees:
By letter to the Nuclear Regulatory Commission (NRC) dated March 28, 2011) Old Dominion Electric Cooperative submitted a report on the status of its decommissioning funding as required by Title 10 of the Code of Federal Regulations (10 CFR), Part SO, Section SO.7S(f)(1).
The NRC staff is reviewing your submittal and has determined that additional information is required to verify compliance with 10 CFR SO.7S. The specific information requested is addressed in the enclosure to this letter. A response is requested within 30 days from the date of this letter.
If you have questions concerning this request, please contact me at (301) 41S-6606.
Sincerely,
~oel ~jd~r Project Manager Plant licensing Branch 11-1 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket Nos. SO-338 and SO-339
Enclosure:
Request for Additional Information cc w/encl: Distribution via listserv
REQUEST FOR ADDITIONAL INFORMATION NORTH ANNA POWER STATION, UNIT NOS. 1 AND 2 DOCKET NOS. 50-338 AND 50-339 In reviewing the Old Dominion Electric Cooperative (Old Dominion) report on the status of its decommissioning funding dated March 28, 2011 (Agency Document and Management System Accession No. ML110910240), for the North Anna Power Station (NAPS), Unit Nos. 1 and 2, the Nuclear Regulatory Commission (NRC) staff has determined that the following information is needed in order to verify that the requirements of Title 10 of the Code of Federal Regulations (10 CFR), Part 50, Section 50.75 have been met:
Request for Additional Information {RA!} #1- Minimum Decommissioning Funding Assurance Calculation According to 10 CFR 50.75(f)(1), the amount provided in the decommissioning funding status (DFS) report should be "the amount of decommissioning funds estimated to be required under 10 CFR 50.75(b) and (c)." The formulas for the factors used by the staff can be found using NUREG-1307, Rev. 14. For example, the calculations for the Labor and Energy Adjustment Factors can be found on pages 7 and 8 of NUREG-1307, Rev. 14.
In the March 28, 2011, letter Old Dominion reported an amount of decommissioning funds estimated to be required under 10 CFR 50.75(b) and (c), greater than the amount calculated by the NRC staff.
Provide the labor, energy, and burial factors used in the calculation of the minimum requirement for decommissioning financial assurance and, if necessary, a corrected submittal for that part of the DFS report. If the factors used are greater than the factors for the appropriate waste vendor option in NUREG-1307, Rev. 14, "Report on Waste Burial Charges: Changes in Decommissioning Waste Disposal Costs at Low-Level Waste Burial Facilities," provide the basis for using the higher factors.
RAJ #2 - Rate of Returns As stated in 10 CFR 50.75(f)(1), "The information in this [the DFS] report must include [...] the assumptions used regarding rates of escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates of other factors used in funding prOjections ...."
In the March 28, 2011, letter Old Dominion reported the following assumptions for its ownership share of North Anna 1 and 2:
4.408 percent rate of escalation in decommissioning costs, and 7.769 percent rate of earnings on decommissioning funds.
Enclosure
-2 Provide the citation (e.g., an Order by the rate-regulatory authority) by the regulatory entity that allows for the assumptions used regarding rate of escalation in decommissioning costs, rate of earnings on decommissioning funds and rates of other factors assumed in the DFS report.
RAI #3 - Reporting Requirements As stated in 10 CFR 50.75(f)(1), "The information in this [the DFS] report must include [... Jany contracts upon which the licensee is relying under paragraph (e)(1 )(v) of this section; any modifications occurring to a licensee's current method of providing financial assurance since the last submitted report ...."
In the March 28, 2011, letter Old Dominion provided information required under 10 CFR 50.75(f)(1), but did not indicate whether there are any contracts upon which it is relying.
Indicate whether there are contracts upon which Old Dominion is relying under paragraph 10 CFR 50.75(e)(1)(v).
RAI #4: Actual Funds as of December 31! 2010 The provisions of 10 CFR 50.75(f)(1) and (2) require the licensee to report the amount offunds accumulated to the end of the calendar year preceding the report.
In the March 28, 2011, letter Old Dominion provided the amount of funds held in the trust as of December 31, 2010, but did not indicate if the amount provided is a before- or after-tax balance.
Clarify if the amount of decommissioning funds is the after-tax amount of funds accumulated through December 31,2010. If not, provide the after-tax amounts of decommissioning funds accumulated through December 31,2010.
June 9, 2011 Mr. Robert L. Kees Senior Vice President and Chief Financial Officer Old Dominion Electric Cooperative Innsbrook Corporate Center 4201 Dominion Boulevard Glen Allen, VA 23060
SUBJECT:
NORTH ANNA POWER STATION, UNIT NOS. 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION REGARDING DECOMMISSIONING FINANCIAL ASSURANCE (TAC NOS. MESS06 AND MESS07)
Dear Mr. Kees:
By letter to the Nuclear Regulatory Commission (NRC) dated March 28, 2011, Old Dominion Electric Cooperative submitted a report on the status of its decommissioning funding as required by Title 10 of the Code of Federal Regulations (10 CFR), Part SO, Section SO.7S(f)(1).
The NRC staff is reviewing your submittal and has determined that additional information is required to verify compliance with 10 CFR SO.7S. The specific information requested is addressed in the enclosure to this letter. A response is requested within 30 days from the date of this letter.
If you have questions concerning this request, please contact me at (301) 41S-6606.
Sincerely, IRA!
Joel S. Wiebe, Senior Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. SO-338 and SO-339
Enclosure:
Request for Additional Information cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL2-1 RlF RidsNrrDorlLpl2-1 Resource RidsNrrPMNorthAnna Resource RidsN rrLAMO' Brien Resource RidsAcrsAcnw_MailCTR Resource RidsNrrDorlDpr Resource RidsRgn2MailCenter Resource RidsOgcRp Resouce RidsNrrDprPfib ADAMS A ccesslon No. ML11132A171 *Bsy memo d ated 4/27/11 OFFICE~2-1/PM LPL2-1/LA PFIBIBC LPL2-1/BC LPL2-1/PM NAME JWiebe MO'Brien CRegan* GKulsea JWiebe (BClayton for) (PBoyle for)
DATE 5/23/11 5/20/11 4/27/11 6/8111 6/9/11 OFFICIAL RECORD COPY