May 6-9, 2011 UNITED STATES OF AMERICA U.S. NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of
)
Amerenue ) Docket No. 52-037-COL (Callaway Plant Unit 2) )
)
AP1000 Design Certification Amendment ) NRC-2010-0131 10 CFR Part 52 ) RIN 3150-A18
)
Calvert Cliffs 3 Nuclear Project, L.L.C. ) Docket No. 52-016-COL (Calvert Cliffs Nuclear Power Plant, Unit 3) )
)
Detroit Edison Co. ) Docket No. 52-033-COL (Fermi Nuclear Power Plant, Unit 3) )
)
Duke Energy Carolinas, L.L.C. ) Docket Nos.52-018 (William States Lee III Nuclear Station, ) and 52-019 Units 1 and 2) )
)
Energy Northwest ) Docket No. 50-397-LR (Columbia Generating Station) )
)
Entergy Nuclear Generation Co. ) Docket No. 50-293-LR And Entergy Nuclear Operations, Inc. )
(Pilgrim Nuclear Power Station) )
)
Entergy Nuclear Operations, Inc. ) Docket Nos. 50-247-LR (Indian Point Nuclear Generating ) and 50-286-LR Station, Units 2 and 3) )
)
ESBWR Design Certification Amendment ) NRC-2010-0135 10 CFR Part 52 ) RIN-3150-AI85
)
FirstEnergy Nuclear Operating Co. ) Docket No. 50-346-LR (Davis-Besse Nuclear Power Station, )
Unit 1) )
)
Florida Power & Light Co. ) Docket Nos. 52-040-COL (Turkey Point Units 6 and 7) ) and 52-041-COL
)
Luminant Generation, Co., L.L.C. ) Docket Nos. 52-034-COL (Comanche Peak Nuclear Power Plant, ) and 52-035-COL Units 3 and 4) )
)
Nextera Energy Seabrook, L.L.C. ) Docket No. 50-443-LR (Seabrook Station, Unit 1) )
)
Pacific Gas and Electric Co. ) Docket Nos. 50-275-LR (Diablo Canyon Nuclear Power Plant, ) and 50-323-LR Units 1 and 2) )
)
PPL Bell Bend, L.L.C. ) Docket No. 52-039-COL (Bell Bend Nuclear Power Plant) )
)
Progress Energy Carolinas, Inc. ) Docket Nos. 52-022-COL (Shearon Harris Nuclear Power Plant, ) and 52-023-COL Units 2 and 3) )
)
Progress Energy Florida, Inc. ) Docket Nos. 52-029-COL (Levy County Nuclear Power Plant, ) and 52-030-COL Units 1 and 2) )
)
South Carolina Electric and Gas Co. ) Docket Nos. 52-027-COL And South Carolina Public Service Authority ) and 52-028-COL (Also Referred to as Santee Cooper) )
(Virgil C. Summer Nuclear Station, Units 1 and 2) )
)
Southern Nuclear Operating Co. ) Docket Nos. 52-025-COL (Vogtle Electric Generating Plant, ) and 52-026-COL Units 3 and 4) )
)
South Texas Project Nuclear Operating Co. ) Docket Nos. 52-012-COL (South Texas Project, ) and 52-013-COL Units 3 and 4) )
)
Tennessee Valley Authority ) Docket Nos. 50-438-CP (Bellefonte Nuclear Power Plant, ) and 50-439-CP Units 1 and 2) )
)
Tennessee Valley Authority ) Docket Nos. 52-014-COL (Bellefonte Nuclear Power Plant, ) and 52-015-COL Units 3 and 4) )
)
Tennessee Valley Authority ) Docket No. 50-0391-OL (Watts Bar Unit 2) )
)
2
Virginia Electric and Power Co. )
d/b/a/ Dominion Virginia Power and ) Docket No. 52-017-COL Old Dominion Electric Cooperative )
(North Anna Unit 3) )
PETITIONERS REPLY TO RESPONSES TO EMERGENCY PETITION TO SUSPEND ALL PENDING REACTOR LICENSING DECISIONS AND RELATED RULEMAKING DECISIONS PENDING INVESTIGATION OF LESSONS LEARNED FROM FUKUSHIMA DAIICHI NUCLEAR POWER STATION ACCIDENT I. INTRODUCTION Petitioners hereby reply to the responses filed in the above-captioned proceedings (collectively, the Responses) by the U.S. Nuclear Regulatory Commission (NRC)
Staff, the license applicants and the Nuclear Energy Institute (NEI), to Petitioners Emergency Petition to Suspend All Pending Reactor Licensing Decisions and Related Rulemaking Decisions Pending Investigation of Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident (April 14-18, 2011, corrected April 18, 2011)
(Emergency Petition).1 The Responses are based on mischaracterizations of the 1
In addition to the NRC Staff and NEI, the following new reactor license applicants and license renewal applicants submitted Responses in opposition to the Emergency Petition:
Calvert Cliffs 2 Nuclear Project, L.L.C. and Unistar Nuclear Operating Services, L.L.C.
(Docket No.52-016); the Detroit Edison Co. (Docket No.52-033); Duke Energy Carolinas, L.L.C. (Docket Nos.52-018 and 52-019); Energy Northwest (Docket No. 50-397); Entergy Nuclear Generation co. and Entergy Nuclear Operations, Inc. (Docket No.
50-203); Entergy Nuclear Operations, Inc. (Docket Nos. 50-247 and 50-286); FirstEnergy Nuclear Operating Co. (Docket No. 50-346); Florida Power & Light Co. (Docket Nos.52-040 and 52-041); Luminant Generation Co. (Docket Nos.52-034 and 52-035);
NextEra Energy Seabrook, L.L.C. (Docket No. 50-443); Nuclear Innovation North America L.L.C. (Docket Nos.52-012 and 52-013); Pacific Gas & Electric Co. (Docket Nos. 50-275 and 50-323); PPL Bell Bend, L.L.C. (Docket No.52-039); Progress Energy Carolinas, Inc. (Docket Nos.52-022 and 52-023); Progress Energy Florida, Inc. (Docket Nos.52-029 and 52-030); South Carolina Electric and Gas Co. and South Carolina Public Service Authority (a.k.a. Santee Cooper) (Docket Nos.52-027 and 52-028); Southern Nuclear Operating Co. (Docket Nos.52-025 and 52-026); Tennessee Valley Authority 3
Petition, incorrect representations regarding the NRCs response to the Three Mile Island accident, and incorrect interpretations of the law. Therefore they should be rejected and the Petition should be granted.
II. DISCUSSION A. The Petition is Not a Motion to Suspend all Licensing Proceedings.
The Responses raise a host of procedural criticisms that are based on a concerted mischaracterization of the Petition: almost without exception, they characterize the Petition as a motion to suspend licensing proceedings. See, e.g., NRC Staff Response at 9. Thus, the Responses argue, Petitioners have violated several of the NRCs regulations in Subpart C of 10 C.F.R. Part 2, which govern motions in NRC adjudications. These regulations include the requirement to consult opposing parties before filing a motion (10 C.F.R. § 2.323(b)), the requirement to file a motion within ten days of the precipitating event (10 C.F.R. § 2.323(a)), requirements for motions by parties to stay adjudicatory proceedings (10 C.F.R. § 2.342), and requirements for motions to re-open closed records of adjudicatory proceedings (10 C.F.R. § 2.326).
Contrary to the mischaracterizations by the Responses, however, the Emergency Petition does not constitute a motion that can be brought in an adjudication; nor does it seek suspension of licensing proceedings.
(Docket Nos. 50-391,52-014 and 52-015); and Dominion Virgina Power, et al. (Docket No.52-017).
The Commonwealth of Massachusetts (Docket No. 50-293) also filed a Response in support of Petitioners.
4
- 1. The Emergency Petition is not a motion.
First, Petitioners Emergency Petition cannot be characterized as a motion or the equivalent of a motion that is subject to the regulations in Subpart C of 10 C.F.R. Part 2, because the relief it seeks could not be granted in an adjudication. Petitioners seek to suspend all licensing decisions, which are relegated by the Commission to the NRC Staff pursuant to 10 C.F.R. § 2.340. As further explained below, the regulations in Subpart C of 10 C.F.R. Part 2 regarding adjudications are simply not applicable to these licensing decisions. See Cincinnati Gas and Electric Co. (William H. Zimmer Nuclear Station),
LBP-79-24, 10 NRC 226, 232 (1979) (noting that duty of licensing boards in adjudications is to resolve discrete contentions or issues and that [g]eneral responsibility for operating licenses rests with the Staff. . .)2
- 2. The Emergency Petition seeks blanket suspension of licensing decisions, not licensing proceedings.
Second, despite the Responses persistent mischaracterization of the Emergency Petition, Petitioners do not seek a blanket suspension of all licensing proceedings.
Instead, they seek suspension of all licensing decisions. As discussed above, only the Commission has the authority to issue a blanket suspension of all licensing decisions in order to ensure the lawful and orderly consideration of the lessons learned from the Fukushima accident. While Petitioners also seek suspension of those aspects of contested 2
In order to give notice to interested parties, including applicants and the NRC Staff, the Petition was submitted in pending licensing proceedings, including adjudications; however, it was not described as or intended to be a motion in any adjudication. In fact, the Petition was submitted in several proceedings in which no adjudication is pending, including the design certification rulemakings for the AP1000 and Economic Simplified Boiling Water Reactor (ESBWR), the Callaway combined construction permit/operating license (COL) proceeding, the Bell Bend COL proceeding, and the Columbia license renewal proceeding.
5
proceedings which concern Fukushima-related issues, this relief is incidental to the primary action requested of the Commission, which is to hold in abeyance the NRCs ultimate decisions to license or re-license reactors or certify designs.
Petitioners essentially seek the same measures that the Commission imposed in the aftermath of the Three Mile Island Accident: suspension of all licensing decisions and establishment of procedures for the meaningful and orderly consideration of the lessons learned from the accident, including provision of public participation. See Statement of Policy: Further Commission Guidance for Power Reactor Operating Licenses, CLI-80-42, 12 NRC 654 (1980) (TMI Policy Statement). Just as the Commission did not broadly suspend its licensing proceedings after the Three Mile Island accident, Petitioners do not seek a blanket suspension of licensing proceedings, but rather the establishment of procedures to ensure that contested proceedings will include the consideration of lessons learned from the accident.
Thus, as explained above, the general procedural requirements for motions made in the course of adjudications do not apply;3 nor is the Petition subject to the regulations governing motions for stays or re-opening of closed records. The cases cited in the Responses do not hold otherwise, because they all concern petitions or motions to suspend licensing proceedings. See, e.g., Duke Energy Corp. (McGuire Nuclear Station Units 1 & 2); Catawba Nuclear Station, Units 1 & 2), CLI-01-27, 54 NRC 385, 389-90 3
Before filing this Reply, Petitioners consulted opposing counsel to ask if they would object to a motion to modify the Commissions April 19, 2011 Order to permit such a reply. Petitioners did so because they believed that once the Commission had issued an order in this matter, it was appropriate to consult opposing counsel before seeking to modify the order. By consulting opposing counsel in this limited instance, however, Petitioners do not concede that they were required to do so in filing their Petition in the first instance.
6
(2001); Private Fuel Storage, L.L.C. (Independent Spent Fuel Storage Installation), CLI-01-26, 54 NRC 376, 380 (2001); AmerGen Energy Co., L.L.C. (Oyster Creek Nuclear Generating Station), CLI-08-23, 68 NRC 461, 484 (2008)); Pacific Gas & Electric Co.
(Diablo Canyon Power Plant Independent Spent Fuel Storage Installation), CLI-02-23, 56 NRC 230 (2002); Amergen Energy Co., et al. (Oyster Creek Nuclear Generating Station)
CLI-08-23, 68 NRC 461 (2008). In all of those decisions, the Commission was responding to requests for suspension of licensing proceedings, which is not the case here.
The one NRC case that is clearly applicable here is the 1980 TMI Policy Statement, where the Commission records its determination, in the aftermath of the Three Mile Island accident, that all licensing decisions should be suspended while the Commission studied the lessons to be learned from the accident. As the Commission summarized in that Policy Statement:
After the March 1979 accident at Three Mile Island, Unit 2, the Commission directed its technical review resources to assuring the safety of operating power reactors rather than to the issuance of new licenses. Furthermore, the Commission decided that power reactor licensing should not continue until the assessment of the TMI accident had been substantially completed and comprehensive improvements in both the operation and regulation of nuclear power plants had been set in motion.
12 NRC at 656. While NEI cites numerous licensing-related decisions that were made while the Commission studied the lessons of the Three Mile Island accident, NEI nevertheless admits that no decision authorizing the operation of a new reactor was made until August of 1980, 17 months after the accident. NEI Response at 7, n.15. Similarly, while the Staff cites the TMI Policy Statement for the proposition that the Commission issued several licenses while it continued to study that accident (NRC Staff Response 7
at 11), the Policy Statement states that the Commission waited to issue two full power licenses until after initial drafts of the Three Mile Island Action Plan had been prepared.
12 NRC 658.4 B. Suspension of Licensing Decisions is Necessary to Ensure Compliance With the National Environmental Policy Act.
- 1. No showing of immediate or irreparable harm is required.
Most of the Responses argue that the Emergency Petition should be rejected because it does not show immediate or irreparable harm to public health and safety or the environment. In making these arguments, however, they miss the central point of the Petition, which is to invoke the Commissions responsibility to comply with the National Environmental Policy Act (NEPA) by considering new and significant information relating to the Fukushima accident. 10 C.F.R. § 51.92; Marsh v. Oregon Natural Res.
Council, 490 U.S. 360, 373-74 (1989). The NRCs duty to consider new and significant information before making licensing decisions is nondiscretionary. Calvert Cliffs Coordinating Commission v. AEC, 449 F.2d 1109, 1112 (D.C. Cir. 1971) (federal agencies are held to a strict standard of compliance with NEPAs requirements). See also Silva v. Romney, 473 F.2d 287, 292 (1st Cir. 1973). Therefore it is inappropriate to apply a discretionary stay standard to answer the basic question of whether NEPA must be complied with in a timely fashion.5 4
The NRC Staff and some of the applicants also argue that the Commission did not suspend licensing proceedings while it studied the Three Mile Island accident.
Petitioners do not seek that relief, however. The only relief sought by Petitioners with respect to ongoing licensing proceedings is to request the Commission to establish procedures for the consideration of Fukushima-related issues in adjudications and design certification rulemakings.
5 NEPAs instruction that all federal agencies comply with its requirements -to the fullest extent possible,is neither accidental nor hyperbolic. Rather the phrase is a 8
- 2. The NRCs existing EISs are inadequate because they do not address new and significant information arising from the Fukushima accident.
A number of Responses argue that because the NRC has already prepared final environmental impact statements in some of the proceedings, and these documents already analyze the environmental impacts of the respective licensing decisions, nothing more is required. See, e.g., Southern Nuclear Operating Companys Response at 17-18.
This argument, however, ignores the continuing obligation agencies have to consider new information that comes to light throughout the NEPA process, even after a final EIS has been issued. 10 C.F.R. § 51.92(a); Marsh v. Oregon Natural Res. Council, 490 U.S. at 373-74.
- 3. The existing process is not adequate to ensure prior consideration of new and significant information arising from the Fukushima accident.
Other Responses argue that the existing NRC process for consideration of new and significant information is sufficient to ensure that any new and significant information emerging from the Fukushima accident will be considered. See, e.g., Energy Northwest Response at 21. But this argument ignores the real potential that the NRC may not complete its investigation before it issues or renews licenses for reactors. For instance, during the Fukushima accident, the NRC re-licensed the Vermont Yankee and Palo Verde reactors, completely failing to consider the implications of the accident for those re-licensing decisions in violation of NEPA. In order to comply with NEPA, the Commission must establish measures to ensure that it will not take licensing actions deliberate command that the duty NEPA imposes upon the agencies to consider environmental factors not be shunted aside in the bureaucratic shuffle. Flint Ridge Development Co. v. Scenic Rivers Association of Oklahoma, 426 U.S. 776 (1976).
9
without first taking a hard look at the environmental implications of the Fukushima accident. Friends of the Clearwater v. Dombeck, 222 F.3d 552, 557-58 (9th Cir. 2000)
(quoting Marsh v. Oregon Natural Res. Council, 490 U.S. at 373-74.
The argument that existing procedures are sufficient also ignores NEPAs directive that federal agencies must integrate the NEPA process with other planning at the earliest possible time to insure that planning and decisions reflect environmental values, to avoid delays, and to head off potential conflicts. 40 C.F.R. §1501.2. See also 40 C.F.R. § 1500.2 (Federal agencies shall to the fullest extent possible: Integrate the requirements of NEPA with other planning and environmental review procedures required by law or by agency practice so that all such procedures run concurrently rather than consecutively). Given that the NRC has decided to evaluate whether the Fukushima accident conveys lessons that must be accounted for in its safety regulations, it now has an obligation to explain how the lessons will be integrated into its environmental decision-making process.
Finally, the argument that existing procedures are sufficient fails to recognize the fact that the NRC and license applicants, in the first instance, bear the burden of analyzing environmental issues, not the public. Just as environmental reports by applicants and draft EISs by the NRC Staff must address known environmental issues before they are presented to the public, so they should be required to address the environmental significance of the events in Japan before the public is required to challenge them in comments or hearing requests.
10
- 4. Petitioners are not required to prove that new and significant information from the Fukushima accident is certain to affect the outcome of EISs.
Still other Responses argue that Petitioners have not established that an analysis of the Fukushima accident will, in fact, affect the outcome of EISs for U.S. reactors. See, e.g., Energy Northwest Response at 22-23. But that is not the standard for consideration of new and significant information. NEPA requires that the agency take a hard look at the new information to determine whether a [Supplemental] EIS is necessary. Blue Mountains Biodiversity Project v. United States Forest Service, 229 F.Supp.2d 1140, 1148 (D. Or. 2002) (emphasis added). See also Warm Springs Dam Task Force v.
Gribble, 621 F.2d 1017, 1025 (9th Cir. 1980). By undertaking an investigation of the regulatory implications of the Fukushima accident from a safety standpoint, the Commission has effectively conceded that it has potential significance from an environmental standpoint. See discussion in Section C below.
Entergy argues that Petitioners err in claiming that the NRC must at least prepare an environmental assessment to determine the significance of the Fukushima Daiichi information. Entergy Response at 27 (citing N. Idaho Cmty. Action Network v. DOT, 545 F.3d 1147, 1154 (9th Cir. 2008), price Rd. Neighborhood Assn v. DOT, 113 F.2d 1505, 1509-10 (9th Cir. 1997) (holding that NEPA permits agencies to establish their own methods for evaluating new and significant information.) Petitioners respectfully submit, however, that the cases cited by Entergy do not involve the NRC, a unique agency whose organic statute requires it to offer an opportunity for public participation in its licensing decisions. See Section 189a of the Atomic Energy Act (AEA), 42 U.S.C. § 2239(a).
To the extent that the NRC considers whether to incorporate lessons from the Fukushima 11
accident into its environmental licensing decisions, Section 189a of the AEA requires it to include the interested public in that decision-making process by offering an opportunity for a hearing. In any event, regardless of whether public participation is required in the NRCs analysis of the environmental significance of the Fukushima accident, to date the NRC has not even attempted the requisite hard look at the issue.
Friends of the Clearwater, 222 F.3d at 557-58. Petitioners are not obligated to carry out that task for the NRC.
- 5. NEPA is not retroactive.
A number of the Responses suggest that the Commission may address the lessons of the Fukushima accident by applying them retrospectively after licenses have been issued or renewed. To do so, however, would violate NEPAs signal requirement that environmental impacts must be considered before licensing actions are taken and the die is cast. Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 349 (1989). See also Protect Key West v. Cheney, 795 F. Supp. 1552, 1562 (S.D. Fla. 1992) (citing Sierra Club v. Lujan, 716 F. Supp. 1289 (D. Ariz. 1989); Cady v. Morton, 527 F.2d 786, 795 (9th Cir. 1975)) (rejecting the federal governments argument that studies, surveys, and investigations conducted after the decision was made to proceed with a project could cure any defects in the original EA).
Moreover, once a license is issued, environmental considerations that were non-discretionary prior to licensing also become matters of pure discretion, in which the public has no right of participation. See, e.g., Safe Energy Coalition of Michigan v. NRC, 866 F.2d 1473 (D.C. Cir. 1989). Thus, in an enforcement context, the public will be deprived of any right to challenge the adequacy of post-Fukushima measures to protect 12
the human environment, thereby undermining NEPAs purpose of encouraging public participation in environmental decisions. See Robertson, 490 U.S. at 348-49 (a key purpose of an EIS is to make environmental information available to the larger audience that may also play a role in the decisionmaking process and implementation of that decision.)6
- 6. NEPA applies to the Japan events because the Commission has conceded that they have potential regulatory significance in the U.S.
Finally, several Responses maintain that NEPA does not apply to the Fukushima accident because the NRC is not undertaking a major federal licensing action for reactors in Japan and that the events in Japan do not constitute information that should be incorporated into any future draft or final EIS. See, e.g., NRC Staff Response at 25, 30.
The argument is frivolous. Petitioners do not contend that the NRC is undertaking a major federal licensing action for reactors in Japan, any more than the NRC has done so by creating the Task Force. Just as the Task Force is considering the implications of the Fukushima accident with respect to NRC safety regulations for U.S. reactors and spent fuel pools, so Petitioners are rightfully insisting that the NRC must consider the environmental implications of the Fukushima accident for U.S. reactors and spent fuel pools.
6 For this reason, NEIs suggestion that Petitioners concerns are satisfied by the right to file post-licensing enforcement petitions under 10 C.F.R. § 2.206 is utterly devoid of merit. See NEI Response at 14.
13
C. The Occurrence of the Fukushima Accident and the Commissions Acknowledgement of its Potential Regulatory Significance Demonstrate the Existence of New and Significant Information That Must be Considered in Licensing Decisions.
In their Emergency Petition, the Petitioners contend that in forming the Task Force and identifying issues whose significance for the NRC regulatory process must be studied, the NRC effectively acknowledged that it has new information that could have a significant effect on its environmental decisions for licensing and re-licensing of reactors.
Emergency Petition at 3. Petitioners assert that by establishing the Task Force and charging it with the task of investigating the implications of the Fukushima Daiichi accident with respect to its regulatory program, the Commission has, as a matter of law, bound itself to evaluate the significance of the information yielded by its investigation under NEPA and to analyze any information that is new and significant in supplemental environmental impact statements for all pending licensing decisions. Id. at 4 n.2. Even if the NRC ultimately concludes that the information does not have a significant effect on its licensing decisions, it must nevertheless follow NEPAs procedures for considering the information, including preparation of an environmental assessment. Id. at 27 (citing Marsh, 490 U.S. at 385 (NEPAs mandate applies regardless of [the agencys] eventual assessment of the significance of [the] information.))
This argument is effectively ignored in the Responses to the Petition. Instead, the Responses attack Dr. Makhijanis supporting declaration as if the Petitioners were required to prove the existence of significant new information that affects the outcome of the NRCs environmental analyses. Dr. Makhijanis declaration, however, is more than adequate to serve its purpose of demonstrating that the new and significant information revealed by the Fukushima accident has the potential to affect the outcome of NRC 14
licensing decisions with respect to consideration of environmental impacts. See Makhijani Declaration, par. 5.7 The Responses also contain technical arguments that are not supported by any expert declarations or affidavits. For instance, Entergy Nuclear Generating Co. et al.
challenge Dr. Makhijanis analysis of severe accident probabilities, without providing any countervailing expert analysis. 8 Entergy Response at 22-23. See also NEI Response at 17-18. Those arguments must be rejected out of hand for lack of technical support.
In any event, the Responses challenges to the technical merit of Dr. Makhijanis declaration are without merit. The Staff claims, for instance, that Dr. Makhijani contradicts himself by arguing that the Fukushima accident presents new and significant information, even at the same time that he concedes that the causes, evolution and consequences of the accident are not yet fully clear. NRC Staff Response at 27. Dr.
7 The NRC Staff makes the irrelevant argument that Dr. Makhijanis declaration is insufficient to support the Petition because it does not show the immediate threat to public safety that is necessary for a suspension of a licensing proceeding. NRC Staff Response at 28. As discussed above, however, Petitioners do not seek the suspension of all licensing proceedings. Instead, they ask the Commission to delay issuance of all licensing decisions until it has completed its study of the lessons of the Fukushima accident and applied those lessons to those licensing decisions, as required by NEPA and the AEA. Thus, it is not necessary for Petitioners to show an immediate threat to public safety, only that the NRC would not be in compliance with NEPA and the AEA if it were to issue licenses without considering the environmental and safety implications of the Fukushima accident for those licensing decisions.
8 Some Responses cite NUREG-1437, the NRCs 1996 Generic Environmental Impact Statement for License Renewal of Nuclear Plants, for the proposition that the environmental impacts of severe accidents are small because the risk of a severe accident has been determined to be small. See, e.g., NRC Staff Answer at 26. However, as Dr.
Makhijanis Declaration demonstrates, the Fukushima accident calls into question the NRCs previous assumptions about the risks of severe accidents. The very occurrence of a severe accident at Fukushima presents readily available information that calls into question the validity of the fifteen-year-old GEIS for license renewal. See Blue Mountains Biodiversity Project, 229 F.Supp.2d at 1148 (ordering supplementation of an EIS on summary judgment, where a fourteen-year-old EIS failed to address new and significant information developed over the intervening years).
15
Makhijani does not contradict himself. He relies on factual statements made to the public by the NRC and the French Government. Makhijani Declaration, pars. 6-10. In Dr.
Makhijanis expert opinion, that factual information is sufficient for purposes of concluding that it is both new and significant to the regulatory process. He is not alone in that assessment; merely by assigning the Task Force to study the regulatory implications of the Fukushima accident, the Commission has effectively conceded that the information has regulatory significance. As Commissioner Svinicki stated during a recent Commission briefing on station blackout issues, although . . . were still working to gain knowledge of the events in Japan, station blackout certainly identifies itself as an important issue that we need to be looking at . . . Transcript of Commission briefing on NRC Response to Events in Japan and Briefing on Station Blackout at 5 (April 28, 2011)
(http://www.nrc.gov/reading-rm/doc-collections/commission/tr/2011/20110428a.pdf).9 As Dr. Makhijani attests, station blackout is one of a number of major topics on which the Fukushima accident has revealed new and significant information, including the following:
o Unanticipated compounding effects of simultaneous accidents at multiple co-located reactor units, including spent fuel pools.
o Unanticipated risks of spent fuel pool accidents, including explosions.
o Frequency of severe accidents and explosions.
o Inadequacy of safety systems to respond to long-duration accidents.
o Nuclear crisis management with contaminated control and turbine buildings that have lost power.
o Unanticipated aggravating effects of some emergency measures.
9 The profound gap between conditions covered by the NRCs regulations and actual potential accidents was highlighted during the discussion. As Commissioner Apostolakis observed during the April 28, 2011 briefing, the four-hour period that is required for recovery from a station blackout is conservative only for routine failures of the grid and does not cover major external events. Commission briefing on Transcript of Briefing on NRC Response to Events in Japan and Briefing on Station Blackout at 48. See also id.
at 19.
16
o Health effects and costs of severe accidents.
o The hydrogen explosions at Fukushima and their implications for aircraft crash evaluations.
In addition, the Staff accuses Dr. Makhijani of prejudging the results of the Task Forces review by concluding that the issues identified above should be studied before the NRC makes any further licensing decisions. NRC Staff Response at 28. But Dr.
Makhijani has not prejudged the results of the Task Force study any more than has Commissioner Svinicki by acknowledging that station blackout is an important issue that deserves further study. Tr. of April 28 Briefing at 5.10 Florida Power and Light (FP&L), several other applicants, and the NEI also attack Dr. Makhijanis declaration. FP&L argues that Dr. Makhijanis concern regarding the risk of hydrogen explosions in spent fuel pools is unfounded because the Commissions studies bound and do not ignore hydrogen explosions as a potential mechanism. FP&L Response at 22. See also Entergys Response at 24, which makes a similar argument. But FP&L and Entergy provide no actual support for this novel argument. Their Responses contains no citation to any discussion of hydrogen explosions in an NRC spent fuel pool study (or any other study for that matter), and the Federal Register notice on which FP&L relies does not even mention the word hydrogen. See FP&L Response at 22 n.17 (citing 73 Fed. Reg. 46,204 (August 8, 2007)). Nor do FP&L and Entergy supply an expert declaration in support of their argument. Because the NRCs risk analyses for spent fuel pool accidents do not include 10 Bizarrely, the Staff accuses Dr. Makhijani of advocating the bypassing of the near-term review by the Task Force based on the information currently available. In no respect has Dr. Makhijani advocated the abandonment of any study of the Fukushima accident that is now being conducted by the NRC. What he disagrees with is the hasty issuance of licensing decisions before those studies are complete.
17
hydrogen explosions, there is no way to compare the NRCs scenarios with hydrogen explosion scenarios in U.S. spent fuel pools until the studies of the Fukushima accident are complete. Thus, FP&Ls and Entergys argument is unfounded and must be rejected.
FP&L also disputes Dr. Makhijanis assertion that the uncovering of spent fuel at Fukushima, which was accompanied by boiling of the water in the pools and a destructive hydrogen explosion, demonstrates that the NRCs probability estimates for spent fuel pool fires are far too low. FP&L Response at 23 (citing Makhijani Declaration, par. 22). According to FP&L, there have been no reports of fire at any of the Fukushima spent fuel pools, and the loss of cooling events at all three units were precipitated by the same event - station blackout. Id. In making this argument, FP&L ignores the fact that loss of cooling to a spent fuel pool and boiling off of the water is a recognized precursor to a pool fire. See 73 Fed. Reg. at 46,210. The fact that fuel was uncovered at three of the Fukushima pools thus demonstrates that the precursors to a pool fire are more likely than previously envisioned by the NRC.
FP&L, Dominion Virginia Power, et al, (DVP), and Duke Energy Carolinas, L.L.C. (Duke) also claim that Dr. Makhijani has failed to show the relevance of the Fukushima accident to spent fuel pool storage at the proposed Turkey Point, North Anna and W.S. Lee new reactors because they are not BWR plants like Fukushima. FP&L Response at 21-22, VPC Response at 11-12, Duke Response at 11. But these applicants do not deny that AP1000 design on which their proposed reactors rely calls for storage of spent fuel in high-density pools. As pointed out in a recent legal petition to suspend the AP1000 design certification rulemaking, between Revision 15 and Revision 18 of the Design Control Document for the AP1000 design, Westinghouse increased the fuel 18
density in storage pools from 619 fuel assemblies to 884 assemblies, an increase of 42.8%. See Petition to Suspend AP1000 Design Certification Rulemaking Pending Evaluation of Fukushima Accident Implications on Design and Operational Procedures and Request for Expedited Consideration at 17 (April 6, 2011) (citing AP1000 DCD, Section 9.1.2.1). As Dr. Makhijani states in his declaration, the Japanese store spent fuel at lower density than in the U.S., and therefore the use of high-density pool storage for spent fuel must be re-examined.
Finally, FP&L states that The only specific claim regarding severe reactor accidents is Dr. Makhijanis assertion that the occurrence of accidents at three reactors should change the underlying frequency data that go into computing the probability of a severe accident at a given reactor. FP&L cites Dr. Makhijanis Declaration at pars. 16-19 and asserts that this statement is erroneous. FP&L Response at 21 n.16. However, the cited paragraphs do not discuss the issue of the frequency of the accidents at all.
Paragraph 16 is a listing of the issues analyzed in Dr. Makhijanis expert declaration, while paragraphs 17-19 only point to the fact that the NRC allows collocation of new reactors at existing sites without analyzing the problem of multi-reactor accidents. The question of the frequency of accidents and related probabilistic analysis is addressed elsewhere, in paragraphs 22 to 24 of the Makhijani Declaration. Specifically, his statement that three of the Fukushima reactors appear to have had core damage is simply a reiteration of the facts as they are best known at the present time. Makhijani Declaration at 22. His inference regarding the need to revisit reactor accident probabilities derives directly from this. FP&Ls statement is a misreading of Dr.
19
Makhijanis Declaration, refers to the wrong paragraphs, and is without factual foundation.
D. The Opponents of the Petition Would Put an Unfair Burden on Interested Members of the Public and Invite Chaos into NRC Adjudications.
Numerous Responses argue that the NRCs existing procedures for the raising of contentions in licensing cases is sufficient for the raising of Fukushima-related issues.
See, e.g., NRC Staff Response at 18, NEI Response at 15, FirstEnergy Response at 18.
But a business-as-usual approach is entirely inadequate for these circumstances, where the Fukushima accident has raised so many questions about the adequacy of the NRCs regulatory program and prior environmental analyses and where the Commission itself has undertaken a systematic investigation of the accidents regulatory significance. If the Commission does not yet have enough information to judge the adequacy of its regulatory program in light of the Fukushima accident, then it would be unreasonable to require members of the public to perform that task. Yet, given that intervenors in NRC licensing cases must raise new information within 30 days of obtaining it, and given that some licensing proceedings may be finished before the NRC issues any lessons learned report, that is exactly what members of the public would be forced to do if they wished to have their concerns addressed before a licensing decision was made.
Furthermore, none of the Responses addresses the logistical difficulty of applying standard NRC procedures to the raising of new Fukushima-related contentions without some guidance from the Commission. How will an interested member of the public know when there is enough information from the Fukushima accident to justify the raising of a contention? The Response filed by Energy Northwest in the Columbia 20
Generating Station license renewal proceeding illustrates the potentially absurd result of failing to establish a schedule for submitting contentions on new Fukushima-related information. The Energy Northwest Response suggests no less than four potential trigger events that could have prompted the Petition: the earthquake on March 11, the March 18 issuance of NRC Information Notice 2011-05, the Commissions March 23 approval of an action plan to review the implications of the Fukushima accident, and the April 1 release of the Task Force Charter. Energy Northwest Response at 9. If the Commission fails to provide any guidance regarding when enough information has been generated as a result of the Fukushima accident to support timely contentions, members of the public will have no choice but to submit new or amended contentions every time that some marginal new piece of information becomes available, in order to comply with the 30-day deadline for raising new information in contentions. The result would not only be chaotic and wasteful of the parties resources, but would divert NRC resources away from investigation of the Fukushima accident, where they should be focused. The Commission should avoid such an unproductive and wasteful outcome by providing clear procedures for the raising of issues related to the Fukushima accident after the NRCs long-term investigation has been completed.
III. CONCLUSION For the foregoing reasons, the Emergency Petition should be granted.
21
Respectfully submitted, Signed (electronically) by:
Diane Curran Harmon, Curran, Spielberg & Eisenberg, L.L.P.
1726 M Street N.W. Suite 600 Washington, D.C. 20036 202-328-3500 Fax: 202-328-6918 E-mail: dcurran@harmoncurran.com Counsel to San Luis Obispo Mothers for Peace in Diablo Canyon License Renewal Proceeding Counsel to Southern Alliance for Clean Energy in Watts Bar Unit 2 Operating License Proceeding Signed (electronically) by:
Nina Bell Northwest Environmental Advocates P.O. Box 12187 Portland, OR 97212-0187 503-295-0490 E-mail: nbell@advocates-nwea.org Duly authorized representative of Northwest Environmental Advocates in Columbia Generating Station license renewal proceeding Signed (electronically) by:
Sara Barczak Southern Alliance for Clean Energy 428 Bull Street Savannah, GA 31401 912-201-0354 E-mail: sara@cleanenergy.org Duly authorized representative of Southern Alliance for Clean Energy in Bellefonte Units 3 and 4 COL proceeding Signed (electronically) by:
Cara L. Campbell Ecology Party of Florida 641 SW 6 Avenue E-mail: levynuke@ecologyparty.org Fort Lauderdale, FL 33315 Duly authorized representative of Ecology Party of Florida Signed (electronically) by:
Tom Clements Friends of the Earth 22
1112 Florence Street Columbia, SC 29201 803-834-3084 E-mail: tomclements329@cs.com Duly authorized representative of Friends of the Earth and South Carolina Chapter of Sierra Club in COL proceeding for V.C. Summer Signed (electronically) by:
Robert V. Eye, KS Sup. Ct. No. 10689 Kauffman & Eye 112 SW 6th Ave., Suite 202 Topeka, KS 66603 785-234-4040 E-mail: bob@kauffmaneye.com Counsel for Public Citizen and SEED Coalition in Comanche Peak COL proceeding and South Texas COL proceeding Signed (electronically) by:
William C. Garner Nabors, Giblin & Nickerson, P.A.
1500 Mahan Drive Suite 200 Tallahassee, FL 32308 850-224-4070 Fax: 850-224-4073 E-mail: bgarner@nglaw.com Counsel to Village of Pinecrest, Florida in Turkey Point COL proceeding Signed (electronically) by:
Mindy Goldstein Turner Environmental Law Clinic 1301 Clifton Road Atlanta, GA 30322 404-727-3432 Fax: 404-7272-7853 Email: magolds@emory.edu Counsel to Center for a Sustainable Coast, Georgia Womens Action for New Directions, Savannah Riverkeeper, and the Southern Alliance for Clean Energy in Vogtle Units 3 and 4 COL proceeding.
Counsel to Dan Kipnis, Mark Oncavage, National Parks Conservation Association, and the Southern Alliance for Clean Energy in Turkey Point Units 6 and 7 COL proceeding.
Signed (electronically) by:
Manna Jo Greene, Environmental Director Hudson River Sloop Clearwater, Inc.
724 Wolcott Ave Beacon, NY 12508 23
845-265-8080 (ext. 7113)
Duly authorized representative for Hudson River Sloop Clearwater in Indian Point license renewal proceeding Signed (electronically) by:
Paul Gunter Beyond Nuclear 6930 Carroll Ave., Suite 400 Takoma Park, MD 20912 202-546-4996 E-mail: paul@beyondnuclear.org Duly authorized representative of Beyond Nuclear in Calvert Cliffs COL proceeding, Davis-Besse license renewal proceeding, and Seabrook license renewal proceeding Signed (electronically) by:
Kevin Kamps Beyond Nuclear 6930 Carroll Ave., Suite 400 Takoma Park, MD 20912 202-546-4996 E-mail: paul@beyondnuclear.org Duly authorized representative of Beyond Nuclear in Davis-Besse license renewal proceeding Signed (electronically) by:
Mary Lampert Pilgrim Watch 148 Washington Street Duxbury, MA 02332 Duly authorized representative of Pilgrim Watch in Pilgrim License Renewal Proceeding Signed (electronically) by:
Terry J. Lodge 316 North Michigan St., Suite 520 Toledo, OH 43604-5627 419-255-7552 E-mail: tjlodge50@yahoo.com Attorney for Citizens Environment Alliance of Southwestern Ontario, Dont Waste Michigan, and the Green Party of Ohio in Davis-Besse Nuclear Power Station Unit 1 license renewal proceeding.
Counsel to Keith Gunter, Michael J. Keegan, Edward McArdle, Leonard Mandeville, Frank Mantei, Marcee Meyers, Henry Newnan, Sierra Club (Michigan Chapter),George Steinman, Shirley Steinman, Harold L. Stokes, and Marilyn R. Timmer in the Fermi COL proceeding.
Signed (electronically) by:
24
Michael Mariotte, Executive Director Nuclear Information and Resource Service 6930 Carroll Ave., Suite 340 Takoma Park, MD 20912 301-270-6477 E-mail: nirsnet@nirs.org Duly authorized representative of NIRS in Calvert Cliffs COL proceeding Signed (electronically) by:
Mary Olson NIRS Southeast P.O. Box 7586 Asheville, NC 28802 828-252-8409 E-mail: maryo@nirs.org Duly authorized representative of Nuclear Information and Resource Service in Levy COL proceeding Signed (electronically) by:
Henry B. Robertson Great Rivers Environmental Law Center 705 Olive Street, Suite 614 St. Louis, MO 63101-2208 314-231-4181 E-mail: hrobertson@greatriverslaw.org Counsel to Missouri Coalition for the Environment and Missourians for Safe Energy in Callaway COL proceeding Signed (electronically) by:
John D. Runkle P.O. Box 3793 Chapel Hill, NC 27515-3793 919-942-0600 E-mail: junkle@pricecreek.com Counsel to NC Waste Awareness and Reduction Network in Shearon Harris 2 and 3 COL proceeding Counsel to AP1000 Oversight Group in AP1000 Rulemaking Proceeding Counsel to Blue Ridge Environmental Defense League fin Vogtle 3 and 4 COL proceeding Counsel to Blue Ridge Environmental Defense League and Peoples Alliance for Clean Energy in North Anna 3 COL proceeding Signed (electronically) by:
Raymond Shadis Friends of the Coast/New England Coalition Post Office Box 98 25
Edgecomb, Maine 04556 207-882-7801 E-mail: shadis@prexar.com Duly authorized representative of Friends of the Coast and New England Coalition in Seabrook license renewal proceeding Signed (electronically) by:
Gene Stilp 1550 Fishing Creek Valley Road Harrisburg, PA 17112 717-829-5600 E-mail: genestilp@comcast.net Pro se petitioner in Bell Bend COL proceeding 26
Signed (electronically) by:
Jason Totoiu Everglades Law Center P.O. Box 2693 Winter Haven, FL 33883 561-568-6740 E-mail: Jason@evergladeslaw.org Counsel to Dan Kipnis, Mark Oncavage, National Parks Conservation Association, and the Southern Alliance for Clean Energy in Turkey Point Units 6 and 7 COL proceeding.
Signed (electronically) by:
Barry White Citizens Allied for Safe Energy 1001 SW 129 Terr.
Miami, FL 33176 305-251-1960 E-mail: btwamia@bellsouth.net Duly authorized representative of Citizens Allied for Safe Energy in Turkey Point COL proceeding Signed (electronically) by:
Louis A. Zeller Blue Ridge Environmental Defense League P.O. Box 88 Glendale Springs, NC 28629 336-982-2691 E-mail: BREDL@skybest.com Duly authorized representative of Blue Ridge Environmental Defense League and Bellefonte Efficiency and Sustainability Team in COL Proceeding for Bellefonte Units 3 and 4.
Duly authorized representative of Blue Ridge Environmental Defense League and Peoples Alliance for Clean Energy in North Anna COL proceeding Duly authorized representative of Blue Ridge Environmental Defense League in W.S. Lee COL proceeding May 6-9, 2011 27