MONTHYEARIR 05000400/20230042024-01-30030 January 2024 Integrated Inspection Report 05000400/2023004 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230032023-11-0909 November 2023 Integrated Inspection Report 05000400/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23234A1702023-10-0303 October 2023 Issuance of Amendment No. 199 Regarding Administrative Changes to the Renewed Facility Operating License and Technical Specifications ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter IR 05000400/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000400/2023402 IR 05000400/20230022023-07-24024 July 2023 Integrated Inspection Report 05000400/2023002 IR 05000400/20234402023-07-17017 July 2023 Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover Letter IR 05000400/20243012023-05-15015 May 2023 Notification of Licensed Operator Initial Examination 05000400/2024301 IR 05000400/20230012023-05-10010 May 2023 Integrated Inspection Report 05000400 2023001 IR 05000400/20234042023-05-0404 May 2023 Cyber Security Inspection Report 05000400/2023404 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23118A1392023-04-28028 April 2023 Submittal of Updated Final Safety Analysis Report (Amendment 65), Technical Specification Bases Revision, Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes IR 05000400/20234032023-04-0505 April 2023 Security Baseline Inspection Report 05000400/2023403 IR 05000400/20230102023-03-15015 March 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000400/2023010 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML23033A5272023-02-0808 February 2023 Correction of Typographical Errors Incurred During Issuance of License Amendment No. 196 IR 05000400/20220042023-02-0707 February 2023 Integrated Inspection Report 05000400/2022004 ML23020A1252023-01-23023 January 2023 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000400/2023403) ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000400/20220032022-11-10010 November 2022 Integrated Inspection Report 05000400/2022003 IR 05000400/20223012022-11-0202 November 2022 NRC Operator License Examination Report 05000400/2022301 ML22271A6202022-09-29029 September 2022 Notification of Shearon Harris Nuclear Power Plant Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000400/2023010 ML22258A1262022-09-14014 September 2022 NRC Operator Licensing Examination Approval 05000400/2022301 ML22242A0022022-09-12012 September 2022 Issuance of Amendments to Adopt TSTF 569, Revision 2, Revise Response Time Testing Definition ML22227A0682022-09-0202 September 2022 Alternative to Certain Inservice Testing Requirements in the American Society of Mechanical Engineers Code for Operation and Maintenance for Certain Target Rock Solenoid Valves IR 05000400/20220052022-08-24024 August 2022 Updated Inspection Plan for Shearon Harris Nuclear Power Plant (Report 05000400/2022005) IR 05000400/20224032022-08-23023 August 2022 Security Baseline Inspection Report 05000400/2022403 ML22126A0082022-08-0909 August 2022 Issuance of Amendment No. 194 Revise Technical Specifications Related to Reactor Protection System Instrumentation P7 IR 05000400/20220022022-08-0505 August 2022 Integrated Inspection Report 05000400/2022002 ML22161B0332022-07-28028 July 2022 Issuance of Amendment No. 193 Regarding Revision of Surveillance Requirements to Remove Shutdown Limitation IR 05000400/20220112022-07-20020 July 2022 Biennial Problem Identification and Resolution Inspection Report 05000400 2022011 IR 05000400/20224022022-06-30030 June 2022 Material Control and Accounting Program Inspection Report 05000400/2022402 (OUO Removed) IR 05000400/20220102022-06-13013 June 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000400/2022010 ML22138A4012022-05-26026 May 2022 Project Manager Reassignment ML22101A2822022-05-0606 May 2022 Regulatory Audit Summary Related to the Review of License Amendment Regarding Revising the Flood Hazard Protection Scheme IR 05000400/20220012022-05-0404 May 2022 Integrated Inspection Report 05000400/2022001 IR 05000400/20224012022-03-24024 March 2022 Security Baseline Inspection Report 05000400/2022401 ML22020A0072022-03-10010 March 2022 Issuance of Amendment No. 192 Regarding Removal of Extraneous Content and Requirements from the Renewed Facility Operating License and Technical Specifications ML22010A2812022-03-0404 March 2022 Issuance of Amendments to Adopt TSTF-577, Rev. 1 Revised Frequencies for Steam Generator Tube Inspections (EPID L-2021-LLA-0161 IR 05000400/20210062022-03-0202 March 2022 Annual Assessment Letter for Shearon Harris Nuclear Power Plant (Report No. 05000400/2021006) ML21351A4722022-02-10010 February 2022 Issuance of Amendment No. 190 Regarding Revision to Containment Spray Nozzle Test Frequency IR 05000400/20210042022-02-0404 February 2022 Integrated Inspection Report 05000400/2021004 ML22034A5352022-02-0202 February 2022 Notification of Licensed Operator Initial Examination 05000400/2022301 2024-01-30
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 April 20, 2011 Mr. Christopher L. Burton Vice President Carolina Power & Light Company Shearon Harris Nuclear Plant P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165
SUBJECT:
MEETING
SUMMARY
- CATEGORY 1 PUBLIC MEETING - ANNUAL ASSESSMENT OF SHEARON HARRIS NUCLEAR PLANT, DOCKET NO.
50-400
Dear Mr. Burton:
This refers to the meeting conducted at our request at Holly Springs Cultural Center on April 14, 2011, at 5:00 pm. The meeting's purpose was to discuss the NRC Reactor Oversight Process Annual Assessment of Shearon Harris Nuclear Plant.
The topics discussed included the reactor oversight process, the NRCs action matrix and the performance of the Harris Nuclear Plant.
Enclosed are a list of attendees and the presentation handouts.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRCs Agency wide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Should you have any questions concerning this meeting, please contact me at (404) 997-4603.
Sincerely,
/RA/
Randall A. Musser, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket No.: 50-400 License No.: NPF-63
Enclosure:
- 1. List of Attendees
- 2. Handout- Shearon Harris - Annual Assessment Meeting cc w/encl.: (See page 2)
__PKG: ML111100021__________ X SUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE JGW1 GJW RAM NAME JWorosilo GWilson RMusser DATE 04/19/2011 04/19/2011 04/19/2011 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO
CP&L 2 cc w/encl: W. Lee Cox, III Brian C. McCabe Section Chief Manager, Nuclear Oversight Radiation Protection Section Shearon Harris Nuclear Power Plant N.C. Department of Environmental Progress Energy Commerce & Natural Resources Electronic Mail Distribution Electronic Mail Distribution Donald L. Griffith Public Service Commission Training Manager State of South Carolina Shearon Harris Nuclear Power Plant P.O. Box 11649 Progress Energy Columbia, SC 29211 Electronic Mail Distribution Chairman LaQuisha M. Parks North Carolina Utilities Commission Manager Electronic Mail Distribution Support Services Shearon Harris Nuclear Power Plant Robert P. Gruber Electronic Mail Distribution Executive Director Public Staff - NCUC David H. Corlett 4326 Mail Service Center Supervisor Raleigh, NC 27699-4326 Licensing/Regulatory Programs Progress Energy Chair Electronic Mail Distribution Board of County Commissioners of Wake County David T. Conley P.O. Box 550 Senior Counsel Raleigh, NC 27602 Legal Department Progress Energy Ernest J. Kapopoulos Jr.
Electronic Mail Distribution Plant General Manager Carolina Power and Light Company Donna B. Alexander Shearon Harris Nuclear Power Plant Manager, Nuclear Regulatory Affairs Electronic Mail Distribution (interim)
Progress Energy Chair Electronic Mail Distribution Board of County Commissioners of Chatham County John H. O'Neill, Jr. P.O. Box 1809 Shaw, Pittman, Potts & Trowbridge Pittsboro, NC 27312 2300 N. Street, NW Washington, DC 20037-1128 Senior Resident Inspector U.S. Nuclear Regulatory Commission Joseph W. Donahue Shearon Harris Nuclear Power Plant Vice President U.S. NRC Nuclear Oversight 5421 Shearon Harris Rd Progress Energy New Hill, NC 27562-9998 Electronic Mail Distribution
3 Letter to Christopher Burton from Randall A. Musser dated April 20, 2011
SUBJECT:
MEETING
SUMMARY
- CATEGORY 1 PUBLIC MEETING - ANNUAL ASSESSMENT OF SHEARON HARRIS NUCLEAR PLANT, DOCKET NO.
50-400 Distribution w/encl:
C. Evans, RII EICS L. Douglas, RII EICS OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMShearonHarris Resource Enclosure