Text

THE ENCLOSURE CONTAINS Security-Related Information -Withhold under 10 CFR 2.390 UPON SEPARATION THIS PAGE IS DECONTROLLED 10 CFR 50.90 s AL* A4subsidiari of Pinnacle West CapitalCorporation Dwight C. Mims Mail Station 7605 Palo Verde Nuclear Senior Vice President Tel. 623-393-5403 P. O. Box 52034 Generating Station Nuclear Regulatory and Oversight Fax 623-393-6077 Phoenix, Arizona 85072-2034 102-06342-DCMfTLC March 31, 2011 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Sirs:

Subject:

Palo Verde Nuclear Generating Station (PVNGS)

Units 1, 2, and 3 Docket Nos. STN 50-528, 50-529 and 50-530 Response to Second Request for Additional Information for the Review of the PVNGS Cyber Security Plan By letter number 102-06226, dated July 22, 2010, Arizona Public Service Company (APS) submitted a request for approval of the PVNGS Cyber Security Plan (Agencywide Documents Access and Management System [ADAMS] Accession No. ML102150230).

The U.S. Nuclear Regulatory Commission (NRC) staff issued a request for additional information (RAI) in a letter dated December 10, 2010 (Accession No. ML103440571),

and APS responded to that RAI by letter dated January 20, 2011 (Accession No. MLI 10320077). In an e-mail dated March 1, 2011, the NRC staff issued a second RAI related to the PVNGS Cyber Security Plan submittal. The enclosure to this letter contains APS's response to this second RAI.

Each of the three questions in the RAI is an industry-generic question developed by NRC staff following discussions with the Nuclear Energy Institute (NEI) and the industry Cyber Security Task Force. The three questions involve the topics of Records Retention, Implementation Schedule, and Scope of Systems.

For each of the three questions, APS is providing a response consistent with an agreed upon method between NEI and the NRC Staff. These RAI responses will require changes in the license amendment request (LAR) for the PVNGS Cyber Security Plan.

APS will provide a timely submittal of the updated PVNGS Cyber Security License Amendment Request (LAR) on a date that will be agreed upon through discussion with the PVNGS NRC Project Manager, Lauren Gibson.

A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway

  • Comanche Peak 0 Diablo Canyon 0 Palo Verde 0 San Onofre 0 South Texas 0 Wolf Creek

THE ENCLOSURE CONTAINS Security-Related Information -Withhold under 10 CFR 2.390 UPON SEPARATION THIS PAGE IS DECONTROLLED ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Response to Second Request for Additional Information for the Review of the PVNGS Cyber Security Plan Page 2 No commitments are being made by this letter. Should you need further information regarding this response, please contact Russell A. Stroud, Licensing Section Leader, at (623) 393-5111.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on 31,3/f (date)

Sincerely, DCM/RAS/TLC/gat

Enclosure:

APS Response to Second NRC Request for Additional Information (RAI)

Regarding PVNGS Cyber Security Plan Submittal cc: E. E. Collins Jr. NRC Region IV Regional Administrator L. K. Gibson NRC NRR Project Manager for PVNGS J. R. Hall NRC NRR Senior Project Manager M. A. Brown NRC Senior Resident Inspector for PVNGS A. V. Godwin Arizona Radiation Regulatory Agency T. Morales Arizona Radiation Regulatory Agency Sr. Physical Security Inspector, RIV/DRS/PSB