MONTHYEARML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting W3F1-2023-0035, Application for Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program2023-07-26026 July 2023 Application for Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program ML22104A2222022-05-12012 May 2022 Issuance of Amendments Revise Technical Specifications to Adopt TSTF 554 ML22075A1022022-04-29029 April 2022 Issuance of Amendment No. 264 to Relocate Chemical Detection System Technical Specifications to Technical Requirements Manual ML21279A2312021-10-0606 October 2021 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements Using the Consolidated Line-Item Improvement ML21148A0522021-06-0808 June 2021 Correction to License Amendment 214 Request to Support Next Generation Fuel; Review and Approval of Revised ECCS Performance Analysis; and Review and Approval of Supplement to the ECCS Performance Analysis ML21116A1432021-04-26026 April 2021 (Waterford 3) - Revision to License Amendment Request to Relocate Boration Systems Technical Specifications to the Technical Requirements Manual ML20148M1062020-06-22022 June 2020 Corrections to Technical Specifications Issued in Amendments Nos. 102 and 225 and with the Renewed License ML20113E8362020-04-23023 April 2020 Summary of March 19, 2020, Category 1 Public Meeting with Entergy Operations Inc. a Planned LAR to Install Digital Systems in Accordance with Di&C ISG-06 Revision 2, Licensing Processes at Waterford Steam Electric Station ML19175A0422019-09-11011 September 2019 Arkansas Units 1 and 2; Grand Gulf, Unit 1; Indian Point 2 and 3; Palisades; River Bend, Unit 1; Waterford Unit 3 - Issuance of Amendments to Adopt TSTF-529, Clarify Use and Application Rules ML19022A3372019-02-13013 February 2019 Issuance of Amendment No. 253 to Revise Section 15.4.3.1 of the Updated Final Safety Analysis Report to Account for Fuel Misload ML17192A0072017-07-27027 July 2017 Issuance of Amendment No. 250 Adoption of Technical Specifications Task Force Traveler TSTF 545, Revision 3 ML16077A2702016-05-10010 May 2016 Issuance of Amendment No. 247 Regarding Cyber Security Plan Milestone 8 Full Implementation Schedule W3F1-2016-0010, Responses to Request for Additional Information Regarding the Risk-Informed Surveillance Requirements License Amendment Request (LAR)2016-03-0303 March 2016 Responses to Request for Additional Information Regarding the Risk-Informed Surveillance Requirements License Amendment Request (LAR) ML15289A1432015-11-13013 November 2015 Redacted - Issuance of Amendment No. 246 Changes to Technical Specification 3.1.3.4 Regarding Control Element Assembly Drop Times ML15244B3862015-09-0303 September 2015 Correction to Issuance of Amendment Extension of the Integrated Leak Rate Testing to 15 Years ML15139A4832015-08-31031 August 2015 Issuance of Amendment No. 245 Change to Updated Final Safety Analysis Report Clarifying Pressurizer Heaters Function for Natural Circulation at the Onset of a Loss of Offsite Power ML15217A1432015-08-24024 August 2015 Issuance of Amendment No. 244 Extension of the Integrated Leak Rate Testing to 15 Years ML15138A4402015-08-14014 August 2015 Orders Approving Transfer of Facility Operating Licenses and Indirect Transfer, Draft Conforming Amendment, and Safety Evaluation W3F1-2015-0061, Provides Supplement to Revise Control Element Assembly Drop Times Associated with Technical Specification 3.1.3.42015-08-14014 August 2015 Provides Supplement to Revise Control Element Assembly Drop Times Associated with Technical Specification 3.1.3.4 ML15174A2272015-07-29029 July 2015 Issuance of Amendment of Technical Specifications s 3.9.6 and 3.9.7 to the Technical Requirements Manual ML14321A7132014-12-10010 December 2014 Issuance of Amendment No. 241, Revise Operating License Condition for Change to Cyber Security Plan Milestone 8 Full Implementation Date W3F1-2014-0052, License Amendment Request Technical Specification Change to Extend the Type a Test Frequency to 15 Years2014-08-28028 August 2014 License Amendment Request Technical Specification Change to Extend the Type a Test Frequency to 15 Years CNRO-2012-00009, Entergy Responses to Request for Additional Information Regarding Changes to the Quality Assurance Program Manual & Associated Plant Technical Specifications Re Staff Qualifications2012-11-20020 November 2012 Entergy Responses to Request for Additional Information Regarding Changes to the Quality Assurance Program Manual & Associated Plant Technical Specifications Re Staff Qualifications W3F1-2012-0084, Technical Specification Change for Dry Cooling Tower Fans Out of Service for Ultimate Heat Sink2012-10-0808 October 2012 Technical Specification Change for Dry Cooling Tower Fans Out of Service for Ultimate Heat Sink W3F1-2012-0028, Supplement 2 of License Amendment Request to Revise Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train2012-05-22022 May 2012 Supplement 2 of License Amendment Request to Revise Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train W3F1-2011-0067, License Amendment Request, Proposed Change to Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train.2011-10-13013 October 2011 License Amendment Request, Proposed Change to Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train. ML1125103192011-09-20020 September 2011 Correction of an Error in Amendment No. 226, Administrative Changes to Technical Specifications 6.9.1.11 and 6.9.1.11.1 Relating to Core Operating Limits Report ML1109501232011-04-0404 April 2011 Attachment 2 to W3F1-2011-0021, Proposed Operating License Change (Mark-up) and Attachment 3, Revised Operating License Page ML1021001582010-09-13013 September 2010 Issuance of Amendment No. 228, Modify Technical Specification Tables 2.2-1 and 3.3-1 to Clarify Notes and Actions ML1021504662010-09-13013 September 2010 Issuance of Amendment No. 227, Modify Technical Specification 3/4.9.7, Crane Travel - Fuel Handling Building to Permit Certain Operations Needed for Dry Cask Storage of Spent Nuclear Fuel W3F1-2010-0065, Response to Request for Additional Information Associated with Technical Specification Table 3.4-1 Isolation Valve Addition2010-08-12012 August 2010 Response to Request for Additional Information Associated with Technical Specification Table 3.4-1 Isolation Valve Addition W3F1-2010-0047, License Amendment Request for Proposed Change to Technical Specification 3.7.1.2, Emergency Feedwater System.2010-07-20020 July 2010 License Amendment Request for Proposed Change to Technical Specification 3.7.1.2, Emergency Feedwater System. 2CAN051001, Response to Request for Additional Information Associated with Core Operating Limits Report References2010-05-17017 May 2010 Response to Request for Additional Information Associated with Core Operating Limits Report References ML1011100352010-04-22022 April 2010 Correction to Technical Specification Page 3/4 3-10 Issued with Amendment No. 225 Technical Specification Change to Relocate Steam Generator Level - High Trip Function W3F1-2010-0011, License Amendment Request, Technical Specification Change Regarding Steam Generator Program2010-02-22022 February 2010 License Amendment Request, Technical Specification Change Regarding Steam Generator Program ML1005504632010-02-22022 February 2010 Request for Amendment to Technical Specification Table 3.4-1 Isolation Valve Addition W3F1-2009-0045, License Amendment Request to Modify Technical Specification Information for Table 2.2-1 and Table 3.3-12009-10-22022 October 2009 License Amendment Request to Modify Technical Specification Information for Table 2.2-1 and Table 3.3-1 W3F1-2009-0021, License Amendment Request to Revise the Departure from Nucleate Boiling Ratio (DNBR) Safety Limit2009-06-0303 June 2009 License Amendment Request to Revise the Departure from Nucleate Boiling Ratio (DNBR) Safety Limit W3F1-2008-0051, Entergy'S Response to Nrc'S Request for Additional Information Regarding License Amendment Request to Modify Requirements Regarding Control Room Envelope Habitability, Waterford Unit 32009-01-0808 January 2009 Entergy'S Response to Nrc'S Request for Additional Information Regarding License Amendment Request to Modify Requirements Regarding Control Room Envelope Habitability, Waterford Unit 3 ML0819904722008-07-30030 July 2008 License and Technical Specification Pages, Issuance of Amendment No. 216, Modify Diesel Generator Fuel Oil Testing Surveillance Requirements ML0812700362008-05-0909 May 2008 Tech Spec Page for Correction to Amendment 214 Request to Support Next Generation Fuel; Review & Approval of Revised ECCS Performance Analysis; & Review & Approval of Supplement to ECCS Performance Analysis ML0803800062008-04-16016 April 2008 License Page 4 and Technical Specification Page 5-5, Issuance of Amendment No. 215 Use of Optimized ZIRLO-TM Fuel Rod Cladding ML0808800152008-04-15015 April 2008 Tech Spec Pages for Amendment 214, Request to Support Next Generation Fuel; Review and Approval of ECCS Performance Analysis; and Review and Approval of Supplement to ECCS Performance Analysis ML0804401272008-02-12012 February 2008 2/12/2008 E-mail from Licensee Enclosing Markup of Technical Specification Page 5-5, Supplement to 4/24/2007 License Amendment Request Use of Optimized ZIRLO-TM Fuel Rod Cladding W3F1-2008-0001, License Amendment Request NPF-38-275, Containment Isolation Valves.2008-01-0202 January 2008 License Amendment Request NPF-38-275, Containment Isolation Valves. W3F1-2007-0033, License Amendment Request NPF-38-273 to Modify Requirements Regarding Control Room Envelope Habitability2007-08-16016 August 2007 License Amendment Request NPF-38-273 to Modify Requirements Regarding Control Room Envelope Habitability ML0711603482007-04-24024 April 2007 License Amendment Request to Allow the Use of Optimized Zirlo Fuel Rod Cladding ML0706803372007-03-19019 March 2007 Tech Spec Pages for Amendment 212 Reactor Coolant System Leakage Detection Instrumentation ML0703704312007-02-0606 February 2007 Technical Specifications, Issuance of Amendment No. 211 to Facility Operating License Removal of Vendor Recommended Diesel Generator Surveillance Requirement 2023-07-26
[Table view] |
Text
Attachment 2 W3F1-2011-0021 Proposed Waterford 3 Operating License Change (mark-up)
(a) The first performance of SR 6.5.17, in accordance with Specification 6.5.17.c.(i), shall be within the specified Frequency of 6 years, plus the 18-month allowance of SR 4.0.2, as measured from April 17, 2004, the date of the most recent successful tracer gas test, as stated in the October 8, 2004 letter response to Generic Letter 2003-01, or within the next 18 months if the time period since the most recent successful tracer gas test is greater than 6 years.
(b) The first performance of the periodic assessment of CRE habitability, Specification 6.5.17.c.(ii), shall be within 3 years, plus the 9-month allowance of SR 4.0.2, as measured from April 17, 2004, the date of the most recent successful tracer gas test, as stated in the October 8, 2004 letter response to Generic Letter 2003-01, or within the next 9 months if the time period since the most recent successful tracer gas test is greater than 3 years.
(c) The first performance of the periodic measurement of CRE pressure, Specification 6.5.17.d, shall be within 18 months, plus the 138 days allowed by SR 4.0.2, as measured from August 13, 2008, the date of the most recent successful pressure measurement test, or within 138 days if not performed previously.
D. The facility requires an exemption from certain requirements of Appendices E and J to 10 CFR Part 50. These exemptions are described in the Office of Nuclear Reactor Regulation's Safety Evaluation Report, Supplement No. 10 (Section 6.1.2) and Supplement No. 8 (Section 6.2.6), respectively. These exemptions are authorized by law and will not endanger life or property or the common defense and security and are otherwise in the public interest. These exemptions are, therefore, hereby granted pursuant to 10 CFR 50.12. With the granting of these exemptions, the facility will operate, to the extent authorized herein, in conformity with the application, as amended, the provisions of the Act, and the rules and regulations of the Commission.
E. EOI shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The plan, which contains Safeguards Information protected under 10 CFR 73.21, is entitled:
"Physical Security, Safeguards Contingency and Training & Qualification Plan, and was submitted on October 4, 2004.
EOI shall fully implement in accordance with an NRC-approved implementation schedule and maintain in effect all provisions of the Commission-approved Waterford 3 Cyber Security Plan pursuant to 10 CFR 73.55(c)(6) and 10 CFR 73.54 (74 FR 13970) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p).
AMENDMENT NO. 171, 218 Revised by letter dated July 26, 2007
Attachment 3 W3F1-2011-0021 Revised Waterford 3 Operating License Page
(a) The first performance of SR 6.5.17, in accordance with Specification 6.5.17.c.(i), shall be within the specified Frequency of 6 years, plus the 18-month allowance of SR 4.0.2, as measured from April 17, 2004, the date of the most recent successful tracer gas test, as stated in the October 8, 2004 letter response to Generic Letter 2003-01, or within the next 18 months if the time period since the most recent successful tracer gas test is greater than 6 years.
(b) The first performance of the periodic assessment of CRE habitability, Specification 6.5.17.c.(ii), shall be within 3 years, plus the 9-month allowance of SR 4.0.2, as measured from April 17, 2004, the date of the most recent successful tracer gas test, as stated in the October 8, 2004 letter response to Generic Letter 2003-01, or within the next 9 months if the time period since the most recent successful tracer gas test is greater than 3 years.
(c) The first performance of the periodic measurement of CRE pressure, Specification 6.5.17.d, shall be within 18 months, plus the 138 days allowed by SR 4.0.2, as measured from August 13, 2008, the date of the most recent successful pressure measurement test, or within 138 days if not performed previously.
D. The facility requires an exemption from certain requirements of Appendices E and J to 10 CFR Part 50. These exemptions are described in the Office of Nuclear Reactor Regulation's Safety Evaluation Report, Supplement No. 10 (Section 6.1.2) and Supplement No. 8 (Section 6.2.6), respectively. These exemptions are authorized by law and will not endanger life or property or the common defense and security and are otherwise in the public interest. These exemptions are, therefore, hereby granted pursuant to 10 CFR 50.12. With the granting of these exemptions, the facility will operate, to the extent authorized herein, in conformity with the application, as amended, the provisions of the Act, and the rules and regulations of the Commission.
E. EOI shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The plan, which contains Safeguards Information protected under 10 CFR 73.21, is entitled:
"Physical Security, Safeguards Contingency and Training & Qualification Plan, and was submitted on October 4, 2004.
EOI shall fully implement in accordance with an NRC-approved implementation schedule and maintain in effect all provisions of the Commission-approved Waterford 3 Cyber Security Plan pursuant to 10 CFR 73.55(c)(6) and 10 CFR 73.54 (74 FR 13970) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p).
AMENDMENT NO. 171, 218 Revised by letter dated July 26, 2007