MONTHYEARML24022A1172024-01-23023 January 2024 Acceptance of Requested Licensing Action Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations ML24012A2422024-01-16016 January 2024 Acceptance of Requested Licensing Action License Transfer Request ML23236A0042023-12-27027 December 2023 Issuance of Amendment 274 Re Changes to Perm Defueled Emergency Plan and Perm Defueled Emergency Action Level Scheme ML23355A1242023-12-26026 December 2023 Withdrawal of an Amendment Request Re License Amendment Request to Revise License Condition to Eliminate Cyber Security Plan Requirements ML23192A0772023-12-26026 December 2023 Letter Exemption from the Requirements of 10 CFR 140.11(a)(4) Concerning Offsite Primary and Secondary Liability Insurance ML23191A5222023-12-22022 December 2023 Exemption Letter from the Requirements of 10 CFR 50.54(W)(1) Concerning Onsite Property Damage Insurance (EPID - L-2022-LLE-0032) ML23263A9772023-12-22022 December 2023 Exemption from Certain Emergency Planning Requirements and Related Safety Evaluation ML23354A2602023-12-21021 December 2023 Reference Simulator Inspection Request for Information L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 PNP 2023-030, License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations2023-12-14014 December 2023 License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations PNP 2023-035, Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements2023-12-12012 December 2023 Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements PNP 2023-028, Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments2023-12-0606 December 2023 Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23291A4402023-11-0303 November 2023 Acceptance of Requested Licensing Action Request for Exemption from 10 CFR 50.82(a)(2) to Support Reauthorization of Power Operations IR 05000255/20230032023-10-0404 October 2023 NRC Inspection Report No. 05000255/2023003(DRSS)-Holtec Decommissioning International, LLC, Palisades Nuclear Plant ML23275A0012023-10-0202 October 2023 Request for Withholding Information from Public Disclosure for Palisades Nuclear Plant PNP 2023-025, Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.822023-09-28028 September 2023 Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.82 PNP 2023-026, Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations2023-09-28028 September 2023 Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations PNP 2023-023, Special Report High Range Noble Gas Monitor Inoperable2023-08-0909 August 2023 Special Report High Range Noble Gas Monitor Inoperable ML23215A2302023-08-0303 August 2023 Notice of Organization Change - Chief Nuclear Officer IR 05000255/20230022023-07-19019 July 2023 NRC Inspection Report 05000255/2023002 DRSS-Holtec Decommissioning International, LLC, Palisades Nuclear Plant ML23087A0362023-05-0202 May 2023 PSDAR Review Letter ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment PNP 2023-018, 2022 Annual Non-Radiological Environmental Operating Report2023-04-25025 April 2023 2022 Annual Non-Radiological Environmental Operating Report L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 PNP 2023-007, and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports2023-04-19019 April 2023 and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports PNP 2023-008, 2022 Radiological Environmental Operating Report2023-04-18018 April 2023 2022 Radiological Environmental Operating Report L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations PNP 2023-002, 6 to Updated Final Safety Analysis Report2023-03-31031 March 2023 6 to Updated Final Safety Analysis Report ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance PNP 2023-006, Report of Changes to Security Plan, Revision 202023-03-29029 March 2023 Report of Changes to Security Plan, Revision 20 PNP 2023-012, Presentation on Regulatory Path to Reauthorize Power Operations2023-03-16016 March 2023 Presentation on Regulatory Path to Reauthorize Power Operations ML23038A0982023-03-15015 March 2023 Request for Withholding Information from Public Disclosure ML23095A0642023-03-14014 March 2023 American Nuclear Insurers, Notice of Cancellation Rescinded PNP 2023-001, Regulatory Path to Reauthorize Power Operations2023-03-13013 March 2023 Regulatory Path to Reauthorize Power Operations PNP 2023-004, Report of Changes to Palisades Nuclear Plant Technical Specification Bases2023-03-0808 March 2023 Report of Changes to Palisades Nuclear Plant Technical Specification Bases PNP 2023-005, Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report2023-03-0101 March 2023 Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML23052A1092023-02-17017 February 2023 FEMA Letter to NRC, Proposed Commission Paper Language for Palisades Nuclear Plant Emergency Plan Decommissioning Exemption Request ML23032A3992023-02-0101 February 2023 Regulatory Path to Reauthorize Power Operations IR 05000255/20220032022-12-28028 December 2022 NRC Inspection Report No. 05000255/2022003(DRSS); 07200007/2022001 (Drss) Holtec Decommissioning International, LLC, Palisades Nuclear Plant L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 PNP 2022-037, Report of Changes to Security Plan, Revision 192022-12-14014 December 2022 Report of Changes to Security Plan, Revision 19 ML22321A2852022-11-17017 November 2022 LLC Master Decommissioning Trust Agreement for Palisades Nuclear Plant IR 05000255/20224012022-11-0909 November 2022 Decommissioning Palisades Nuclear Plant - Decommissioning Security Inspection Report 05000255/2022401 PNP 2022-036, Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme2022-11-0808 November 2022 Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme PNP 2022-035, International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations2022-11-0202 November 2022 International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations PNP 2022-024, Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance PNP 2022-026, Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance ML22292A2572022-10-25025 October 2022 Permanently Defueled Emergency Plan License Amendment RAI Letter 2024-01-23
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 5, 2011 Mr. Thomas Kirwin Vice President, Operations Entergy Nuclear Operations. Inc.
Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530
SUBJECT:
PALISADES NUCLEAR PLANT - SUPPLEMENTAL INFORMATION NEEDED FOR ACCEPTANCE OF LICENSE AMENDMENT REQUEST FOR STEAM GENERATOR COLD-LEG TUBESHEET INSPECTION (TAC NO. ME5780)
Dear Mr. Kirwin:
By letter dated March 3, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML110680342), Entergy Nuclear Operations, Inc. (the licensee),
submitted a license amendment request (LAR) for Palisades Nuclear Plant. The proposed LAR would revise Appendix A, Technical Specifications (TS), as they apply to the steam generator program in TS section 5.5.8. The purpose of the change is to revise the repair criteria for the cold-leg side of the steam generator tubesheet. The proposed change would allow not having to inspect the lower portion of the cold-leg steam generator tubes within the tubesheet, since flaws in this lower portion would be acceptable. The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this LAR. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review.
The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required.
This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that the information delineated in the enclosure to this letter is necessary to enable the staff to make an independent assessment regarding the acceptability of the proposed LAR in terms of regulatory requirements and the protection of public health and safety and the environment.
In order to make the application complete, the NRC staff requests that the licensee supplement the application to address the information requested in the enclosure by April 19, 2011. This will enable the NRC staff to begin its detailed technical review. If the information responsive to the NRC staff's request is not received by the above date, the application will not be accepted for review pursuant to 10 CFR 2.101, and the NRC will cease its review actives associated with the
T. Kirwin -2 application. If the application is subsequently accepted for review, you will be advised of any further information needed to support the staff's detailed technical review by separate correspondence.
The information requested and associated time frame in this letter were discussed with Mr. Jim Kuemin of your staff on March 31, 2011. If you have any questions, please contact me at (301) 415-8371.
Sincerely, Mahesh Chawla, Project Manager Plant Licensing Branch 3-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255
Enclosure:
As stated cc w/encl: Distribution via Listserv
SUPPLEMENTAL INFORMATION NEEDED LICENSE AMENDMENT REQUEST FOR STEAM GENERATOR COLD-LEG TUBESHEET INSPECTION ENTERGY NUCLEAR OPERATIONS, INC.
PALISADES NUCLEAR PLAN DOCKET NO. 50-255 By letter dated March 3,2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML110680342), Entergy Nuclear Operations, Inc. (the licensee),
submitted a license amendment request (LAR) for Palisades Nuclear Plant. The proposed LAR would revise Appendix A, Technical Specifications (TS), as they apply to the steam generator program in TS section 5.5.8. The U.S. Nuclear Regulatory Commission (NRC) staff has determined that the LAR is non-acceptable with opportunity to supplement. The reason for the non-acceptance is that the application is not complete. It does not address the lessons learned from the H* and their effect, if any, on the C* results. In other recent "star" proposals that extended the original hot-leg application to the cold-leg, the licensee either addressed this issue in its original submittal or the NRC staff submitted requests for additional information. Given the history of this issue (I.e., factoring in the lessons learned from the H* review into W*, F* cold-leg amendment requests), the licensee should include this in its submittal. As a reference, the NRC staff has provided the following two documents which provide similar information requested by the staff:
- Sequoyah Nuclear Plant (SQN) - Unit 2 - Technical Specifications (TS) Change 09 W* Alternate Repair Criteria (ARC) for Steam Generator (SG) Tubes Cold Leg, dated May 21, 2009 (ADAMS Accession No. ML091530343).
The following information is needed for the acceptance review:
- 1. Please justify the adequacy of the proposed C* distance in light of the lessons learned from the H* review.
Enclosure
T. Kirwin -2 application. If the application is subsequently accepted for review, you will be advised of any further information needed to support the staff's detailed technical review by separate correspondence.
The information requested and associated time frame in this letter were discussed with Mr. Jim Kuemin of your staff on March 31, 2011. If you have any questions, please contact me at (301) 415-8371.
Sincerely, IRAI Mahesh Chawla, Project Manager Plant Licensing Branch 3-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255
Enclosure:
As stated cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC Branch Reading File RidsAcrsAcnw_MailCTR Resource RidsNrrDciCsgb Resource RidsNrrDorl Resource RidsNrrDorlDpr Resource RidsNrrDorlLpl3-1 Resource RidsNrrLABTully Resource RidsNrrPMPalisades Resource RidsOgcRp Resource RidsRgn3MailCenter Resource AObodoako, NRR/DCIICSGB KKarwoski, NRR/DCI/CSGB ADAMS Accession No. ML110910558 OFFICE DORULPL3-1/PM DORULPL3-1/LA DCI/CSGB/BC DORULPL3-1/BC DORULPL3-1/PM NAME MChawla BTuily /JBurkhardt for RTaylor RPascarelli MChawla DATE 04/05/11 04/05/11 04/05/11 04/05/11 04105111 OFFICIAL RECORD COpy