Licensee Slides - 1/18/2011 Pre-Licensing Meeting with Energy Northwest to Discuss Proposed Power Range Neutron Monitoring System/Arts/Mellla License Amendment Request for Columbia Generating Station
ML110180381
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 01/18/2011
From:
Energy Northwest
To:
Office of Nuclear Reactor Regulation
Singal, B K, NRR/DORL, 301-415-301
References
TAC ME5129
Download: ML110180381 (26)


Text

Columbia PRNM ARTS/MELLLA License Amendment Request Pre-submittal Meeting January 18, 2011

Meeting Goals

 To communicate why this License Amendment is needed at Columbia

 To provide a clear picture of the level of detail to be included in the submittal

 To gain a thorough understanding of the needs of the NRC Review Staff prior to submitting the amendment request 2

Meeting Goals (contd)

 To minimize the need for requests for additional information

 To achieve an agreement on an acceptable approach for scope and depth of content 3

PRNM/ARTS/MELLLA Primary purposes for pursuing PRNM/

ARTS/MELLLA at Columbia Improve Neutron Monitoring System Reliability Improve Fuel Operating Margin Increase Overall Efficiency of Reactor Operations 4

Overview of Presentation

 Summarize scope of LAR Submittal

 Address NRC concerns identified in Sept. 2010 non-acceptance letter

 Discuss schedule for submittal

 Discuss approach for application of TSTF-493

 Identify any additional open items or NRC staff concerns 5

LAR Submittal Scope

 Information provided as part of initial submittal (separated into distinct PRNM and ARTS/MELLLA attachments)

 Information provided in response to RSI 1-8

 New Information



23A5161 Rev 3 - NUMAC Software Configuration Management Plan



23A5162 Rev 3 - NUMAC Software Management Plan



23A5163 Rev 3 - NUMAC Software Verification and Validation Plan



NEDO-11209-04A Rev 8 (1989) - GE Nuclear Energy QA Program Description



GEH Process Road Map



BTP 7-14 Summary Assessment



BTP 7-14 Matrix to GEH Processes



TS Scope increased to add footnotes (consistent with TSTF-493) 6

Summary of Non-Acceptance

 Changes from 1995 LTR not clearly identified

 B.2.1 Software Lifecycle Process Planning

- insufficient information provided

 B.2.2 Software Life Cycle Process Implementation

- information provided too generic

 Compliance with Regulatory Guide criteria for RGs 1.168 through 1.173 not demonstrated 7

GEH Software Quality & BTP 7-14

 GEH Quality Assurance Process Not structured the same as BTP 7-14 Not managed by a single GEH document NUMAC SCMP, SMP, & SVVP provide guidance on how to utilize the GEH lower level procedures and processes to ensure software quality 8

GEH Software Quality & BTP 7-14

 GEH Quality Assurance Process (contd)

A detailed understanding of several GEH Policies (P&Ps), Engineering Operating Procedures (EOPs), and Common Procedures (CPs), along with project specific documentation is necessary to assemble the software quality management process 9

GEH Software Quality & BTP 7-14

 Actions for Re-submittal GEH is assembling additional documentation to assist with clarity and visibility for the NRCs review based on BTP 7-14 GEH BPT 7-14 Independent Assessment -

by ProDesCon, Inc.

GEH Process Road Map - High level pictorial view 10

11 GEH BPT 7-14 Independent Assessment Concept

12 GEH Process Road Map - Example

Changes from Approved LTR Changes to be identified as follows:

Hardware Summary of significant hardware changes Tables of differences in NUMAC platform and hardware modules by parts list Programmable Devices No changes to PLDs from LTR approved design 13

Changes from Approved LTR Software Synopsis of software evolution process Table of firmware changes for Columbia PRNM Applicable Development Processes Summary of NUMAC software development plans Table of software plans revision history*

  • Copies of the NUMAC SCMP, SMP, SVVP documents will be provided, based on the revisions identified in Table 1-6. Additional documentation will be made available to the NRC, if requested.

14

Changes from Approved LTR

 Software Development (as related to section B.2,and the secure development and operational environment)

Summary of PRNM regulatory compliance Table correlating NUMAC design process to BTP 7-14 15

Software Lifecycle Process Planning

 NUMAC Document Revision History Table with revision history of NUMAC Software Plans Copies of the NUMAC SCMP, SMP, SVVP documents will be provided based on the revisions identified in the Table.

Additional documentation will be made available to the NRC, if requested

 GE Nuclear Quality Assurance Program Revision History NEDO-11209-04A Revision 8, dated 1989 was used for the ENW PRNM Project 16

Software Lifecycle Process Planning

 Software Quality Assurance vs. Quality Assurance Program NEDO-11209-04A Revision 8 provided as a reference to ensure NRC understood GEH was following Appendix B approved program 17

Software Lifecycle Process Planning

 Sufficient Information GEH Process Road Map

 Visual Display of the GEH Process to assist with review BTP 7-14 Summary Assessment

 Will communicate level of assurance that can be demonstrated through existing GEH processes and procedures, and will identify where alternate measure may be required 18

Software Lifecycle Process Planning

 Sufficient Information BTP 7-14 Matrix to GEH Processes

 Utilizes RG 1.168-1.173 Matrices developed by GEH

 Identifies how GEH Plans, Processes, Procedures, and Documents map to the related criteria 19

Software Life Cycle Process Implementation

 Specific Documentation

GEH Process Road Map

BTP 7-14 Summary Assessment

BTP 7-14 Matrix to GEH Processes 20

Regulatory Guidance Criteria 21

 Analysis of Criteria

GEH Process Road Map

BTP 7-14 Summary Assessment

BTP 7-14 Matrix to GEH Processes

Deltas with BTP 7-14

Deltas will be identified and evaluated for acceptable alternatives

Noteworthy Deltas Lack of a formal Software Safety Analysis program Degree of Independence for Software V&V activities Forward/Backward Traceability throughout the lifecycle at the code specific level 22

PRNM ARTS/MELLLA Schedule

 Proposed submittal date late March/early April 2011

 If approved, implementation would be requested for Refueling Outage R21, scheduled for May-June 2013 23

Application of TSTF 493

 Affected Setpoints

RPS and Control Rod Block (APRM/OPRM/LPRM)

 Planned Approach

Option A (footnotes)

Full Implementation (no piece-meal)

 Planned Schedule

Late March/Early April 2011 Submittal

Submitted in parallel with PRNM/ARTS/MELLLA 24

Application of TSTF 493

 Challenges/Questions

Level of Detail Required

Columbia is a BWR/5, will need to adopt portions of NUREG-1433 and NUREG-1434

Acceptability of Timing of Submittal

Need for Commitment in PRNM Submittal 25

26 QUESTIONS?

26