UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
245 PEACHTREE CENTER AVENUE NE, SUITE 1200
ATLANTA, GEORGIA 30303-1257
December 20, 2010
Mr. Christopher L. Burton
Vice President
Carolina Power & Light Company
Shearon Harris Nuclear Plant
P.O. Box 165, Mail Zone 1
New Hill, NC 27562-0165
SUBJECT: NOTIFICATION SHEARON HARRIS NUCLEAR PLANT - COMPONENT
DESIGN BASES INSPECTION - NRC INSPECTION REPORT
Dear Mr. Burton:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
Region II staff will conduct a component design bases inspection at your Shearon Harris Nuclear
Power Plant reactor facility during the period of March 21 - April 22, 2011. The inspection team
will be led by Mr. Shakur Walker, a Senior Reactor Inspector from the NRC's Region II Office.
This inspection will be conducted in accordance with the baseline inspection procedure,
Procedure 71111.21, Component Design Bases Inspection, issued December 6, 2010.
The inspection will evaluate the capability of risk significant / low margin components to function
as designed and to support proper system operation. The inspection will also include a review
of selected operator actions, operating experience, and modifications.
During a discussion on December 2, 2010, Mr. Walker confirmed, with Mr. John Doorhy of your
staff, arrangements for an information gathering site visit and the three-week onsite inspection.
The schedule is as follows:
- Information gathering visit: February 28 - March 4, 2011
- Week 1 of onsite inspection: March 21 - March 25, 2011
- Week 2 of onsite inspection: April 4 - April 8, 2011
- Week 3 of onsite inspection: April 18 - April 22, 2011
The purpose of the information gathering visit is to meet with members of your staff to identify
risk-significant components and operator actions. Information and documentation needed to
support the inspection will also be identified and gathered or requested. Mr. George MacDonald
or Mr. Walt Rogers, both Region II Senior Reactor Analysts, may accompany Mr. Walker during
the information gathering visit to review probabilistic risk assessment data and identify risk
significant components which will be examined during the inspection.
CPL 2
The enclosure lists documents that will be needed prior to the information gathering visit. Please
contact Mr. Walker with any questions prior to preparing materials listed in the enclosure and
provide the referenced information to the Region II office by January 28, 2011, unless otherwise
noted. The inspectors will try to minimize your administrative burden by specifically identifying
only those documents required for the inspection preparation.
During the information gathering visit, the team leader will also discuss the following inspection
support administrative details: office space; site, plant and information system access; required
resources; and information exchange protocol.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document Room
or from the Publicly Available Records (PARS) component of NRC's document system
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, control number 3150-
0011.
The NRC may not conduct or sponsor, and a person is not required to respond to, a request for
information or an information collection requirement unless the requesting document displays a
currently valid Office of Management and Budget control number.
Thank you for your cooperation in this matter. If you have any questions regarding the
information requested or the inspection, please contact Mr. Walker at (404) 997-4639 or me at
(404) 997-4519.
Sincerely,
/RA/
Binoy B. Desai, Chief
Engineering Branch 1
Division of Reactor Safety
Docket Nos.: 50-400
License No.: NPF-63
Enclosure: Information Request for Shearon Harris Nuclear Power Plant Component Design
Bases Inspection
cc w/encl: (See page 3)
CPL 3
cc w/encl: W. Lee Cox, III
Brian C. McCabe Section Chief
Manager, Nuclear Regulatory Affairs Radiation Protection Section
Progress Energy Carolinas, Inc. N.C. Department of Environmental
Electronic Mail Distribution Commerce & Natural Resources
Electronic Mail Distribution
R. J. Duncan, II
Vice President Public Service Commission
Nuclear Operations State of South Carolina
Carolina Power & Light Company P.O. Box 11649
Electronic Mail Distribution Columbia, SC 29211
Greg Kilpatrick Chairman
Training Manager North Carolina Utilities Commission
Shearon Harris Nuclear Power Plant Electronic Mail Distribution
Progress Energy Carolinas, Inc.
Electronic Mail Distribution Robert P. Gruber
Executive Director
John C. Warner Public Staff - NCUC
Manager 4326 Mail Service Center
Support Services Raleigh, NC 27699-4326
Progress Energy Carolinas, Inc.
Electronic Mail Distribution Herb Council
Chair
David H. Corlett Board of County Commissioners of Wake
Supervisor County
Licensing/Regulatory Programs P.O. Box 550
Progress Energy Raleigh, NC 27602
Electronic Mail Distribution
Sally Kost
David T. Conley Chair
Associate General Counsel Board of County Commissioners of
Legal Dept. Chatham County
Progress Energy Service Company, LLC P.O. Box 1809
Electronic Mail Distribution Pittsboro, NC 27312
Christos Kamilaris Kelvin Henderson
Director Plant General Manager
Fleet Support Services Carolina Power and Light Company
Carolina Power & Light Company Shearon Harris Nuclear Power Plant
Electronic Mail Distribution Electronic Mail Distribution
John H. O'Neill, Jr. Senior Resident Inspector
Shaw, Pittman, Potts & Trowbridge U.S. Nuclear Regulatory Commission
2300 N. Street, NW Shearon Harris Nuclear Power Plant
Washington, DC 20037-1128 U.S. NRC
5421 Shearon Harris Rd
Joseph W. Donahue New Hill, NC 27562-9998
Vice President
Nuclear Oversight
Carolina Power and Light Company
Electronic Mail Distribution
_________________________ X SUNSI REVIEW COMPLETE
OFFICE RII:DRS RII:DRS
NAME S. Walker B. Desai
DATE 12/20/2010 12/20/10
E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO
INFORMATION REQUEST FOR SHEARON HARRIS NUCLEAR POWER PLANT
COMPONENT DESIGN BASES INSPECTION
Please provide the information electronically in .pdf files, Excel, or other searchable format on
CD/DVD-ROM. The CD/DVD-ROM should be indexed and possibly hyperlinked to facilitate
ease of use. Information in lists should contain enough information to be easily understood to
someone who has knowledge of pressurized water reactor technology.
1. From your most recent probabilistic safety analysis (PSA) excluding external events and
fires, please provide:
a. Two risk rankings of components from your site-specific probabilistic safety
analysis (PSA) - one sorted by Risk Achievement Worth (RAW), and the other
sorted by Birnbaum Importance.
b. A list of the top 500 cutsets.
2. From your most recent probabilistic safety analysis (PSA) including external events and
fires, please provide:
a. Two risk rankings of components from your site-specific probabilistic safety
analysis (PSA) - one sorted by Risk Achievement Worth (RAW), and the other
sorted by Birnbaum Importance.
b. A list of the top 500 cutsets.
3. Risk ranking of operator actions from your site specific PSA sorted by RAW. Provide
copies of your human reliability worksheets for these items.
4. Any pre-existing evaluation or list of components and calculations with low design
margins (i.e., pumps closest to the design limit for flow or pressure, diesel generator close
to design required output, heat exchangers close to rated design heat removal, MOV risk-
margin rankings, etc.).
5. A list of station applicability evaluations/reviews performed and documented in the station
corrective action program in the past two years for industry events, critical equipment
failures, and safety related equipment vulnerabilities (as communicated by NRC generic
communications, industry communications, 10 CFR Part 21 notifications, etc.).
6. A list of operability evaluations completed within the last two years, sorted by associated
component or system.
7. A list of common-cause failures of components that have occurred at Shearon Harris
Nuclear Power Plant and have been identified within the last five years.
8. A list of equipment currently planned for upgrade/improvement by the site (e.g. ONE
List), including a description of the reason(s) why each component (i.e. not a
programmatic or system level concern) is on that list and summaries (if available) of your
plans to address those reasons.
9. A list of equipment currently in RIS 05-020 (formerly GL 91-18) status, or in MR (a)(1)
status.
10. Contact information for a person to discuss PRA information prior to the information
gathering trip: name, title, phone number, and e-mail address.
Enclosure
2
11. Provide two sets of PI&D drawings (11x17) for safety-related systems (for onsite week of
February 28 - March 3, 2011)
12. Provide six copies of FSAR (CD/DVD-ROM only) (for onsite week of February 28 - March
3, 2011)
13. Provide six copies of Technical Specifications and Bases (CD/DVD-ROM only) (for
onsite week of February 28 - March 3, 2011)
Enclosure