1 WBN2Public Resource From:

Hamill, Carol L [clhamill@tva.gov]

Sent:

Wednesday, October 13, 2010 11:36 AM To:

Wiebe, Joel; Raghavan, Rags; Milano, Patrick; Campbell, Stephen Cc:

Crouch, William D; Boyd, Desiree L

Subject:

10-13-10_PSIPP RAI response to NRC_FINAL Attachments:

image001.jpg; 10-13-10_PSIPP RAI response to NRC_FINAL.pdf Please see attached TVA letter that was sent to the NRC today.

Carol L. Hamill

Licensing/QualityAssurance WBNUnit2Project,EQB1BWBN


4233653177



4233653833

ccllhhaam miillll@

@ttvvaa..ggoovv

Hearing Identifier:

Watts_Bar_2_Operating_LA_Public Email Number:

188 Mail Envelope Properties (25547F570B005144A141ECCA95DA1AB20CEDA67B)

Subject:

10-13-10_PSIPP RAI response to NRC_FINAL Sent Date:

10/13/2010 11:35:54 AM Received Date:

10/13/2010 11:37:01 AM From:

Hamill, Carol L Created By:

clhamill@tva.gov Recipients:

"Crouch, William D" <wdcrouch@tva.gov>

Tracking Status: None "Boyd, Desiree L" <dlboyd@tva.gov>

Tracking Status: None "Wiebe, Joel" <Joel.Wiebe@nrc.gov>

Tracking Status: None "Raghavan, Rags" <Rags.Raghavan@nrc.gov>

Tracking Status: None "Milano, Patrick" <Patrick.Milano@nrc.gov>

Tracking Status: None "Campbell, Stephen" <Stephen.Campbell@nrc.gov>

Tracking Status: None Post Office:

TVACOCXVS2.main.tva.gov Files Size Date & Time MESSAGE 243 10/13/2010 11:37:01 AM image001.jpg 1023 10-13-10_PSIPP RAI response to NRC_FINAL.pdf 415080 Options Priority:

Standard Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Recipients Received:

Page 1 of 1 11/10/2010 file://c:\\EMailCapture\\Watts_Bar_2_Operating_LA_Public\\188\\attch1.jpg

U.S. Nuclear Regulatory Commission Page 2 October 13, 2010

Enclosure:

1.

Response to RAI Regarding the Preservice Inspection Program Plan

2.

List of New Regulatory Commitments cc (Enclosures):

U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381

ENCLOSURE 1 Response to RAI Regarding the Preservice Inspection Program Plan Tennessee Valley Authority - Watts Bar Nuclear Plant - Unit 2, Docket No. 50-391 E1-1 The Nuclear Regulatory Commission (NRC) staff has reviewed and evaluated the information submitted by Tennessee Valley Authority (the licensee) in its letter dated June 17, 2010 (Agencywide Documents Access and Management System Accession No. ML101680561), in which the licensee proposed its Preservice Inspection (PSI) Program Plan in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Section 50.55a for Watts Bar Nuclear Plant (WBN),

Unit 2. The licensee requested NRC to review its proposed PSI Program Plan for WBN, Unit 2 to the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),

Section XI inspection requirements. The applicable ASME Code,Section XI code of record for the WBN, Unit 2 PSI Program Plan is the 2001 Edition through the 2003 Addenda.

In Section 3.4.1.4, the licensee stated that "[t]he IWF-5000 requirements for preservice examination and testing of snubbers will be performed using Subsection ISTD of the ASME/ANSI OM Code 2001 Edition through 2003 OMb Addenda, as permitted by 10 CFR 50.55a(b)(3)(v). Examination shall be performed using the VT-3 visual examination method described in IWA-2213." A similar statement is made in Section 3.18.3.

Please explain what WBN procedures or part of the ASME OM Code Subsection ISTD will be used for snubbers inservice visual examination and testing, because the submittal only includes various WBN procedures for visual examination and nondestructive examination related to ASME Section XI.

Response

TVA will issue a Temporary Change to Nondestructive Examination (NDE)

Procedure N-VT-1 to perform VT-3 examination of snubbers in accordance with the criteria specified in ASME/ANSI OM Code 2001 Edition through 2003 OMb Addenda. The temporary change will implement the preservice examination requirements of ISTD-4100, Preservice Examination. TVA has utilized this process in the past at another nuclear site for performance of VT-3 examination of snubbers.

Testing of mechanical snubbers will be performed by a vendor (to be selected) utilizing their snubber testing program and procedures to meet the criteria specified in ASME/ANSI OM Code 2001 Edition through 2003 OMb Addenda.

The snubber testing requirements will implement ISTD-5100, Preservice Operational Readiness Testing.

ENCLOSURE 2 List of New Regulatory Commitments Tennessee Valley Authority - Watts Bar Nuclear Plant - Unit 2, Docket No. 50-391 E2-1

1.

By November 19, issue a Temporary Change to Nondestructive Examination (NDE)

Procedure N-VT-1 to perform VT-3 examination of snubbers in accordance with the criteria specified in ASME/ANSI OM Code 2001 Edition through 2003 OMb Addenda. The temporary change will implement the preservice examination requirements of ISTD-4100, Preservice Examination.