Correction Letter Relief Request for System Pressure Test Examinations on Class 1 Component Pressure Boundaries
ML102920019
Person / Time
Site: Oyster Creek
Issue date: 11/05/2010
From: Geoffrey Miller
Plant Licensing Branch 1
To: Freeman P
NextEra Energy Seabrook
Miller G, NRR/DORL, 415-2481
References
TAC ME2418
Download: ML102920019 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 November 5, 2010 Mr. Paul Freeman Site Vice President c/o Mr. Michael O'Keefe NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03875

SUBJECT:

SEABROOK STATION, UNIT NO.1 - CORRECTION LETTER RE: RELIEF REQUEST FOR SYSTEM PRESSURE TEST EXAMINATIONS ON CLASS 1 COMPONENT PRESSURE BOUNDARIES (TAC NO. ME2418)

Dear Mr. Freeman:

By letter dated October 15, 2010 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML102350341), the Nuclear Regulatory Commission staff authorized an alternative to the requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI for Seabrook Station, Unit No.1 (Seabrook). The purpose of this letter is to correct the cover letter transmitting this authorization. Specifically, the cover letter incorrectly indicated that this action applied to the third 10-year interval for Seabrook, while the enclosed SE correctly indicates its applicability to the second 1O-year interval.

If you have any additional questions regarding this matter, I may be reached via telephone at (301) 415-2481.

sig;/1'~

G. Edward Miller, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-219 cc: Distribution via ListServ

November 5, 2010 Mr. Paul Freeman Site Vice President clo Mr. Michael O'Keefe NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03875

SUBJECT:

SEABROOK STATION, UNIT NO.1 - CORRECTION LETTER RE: RELIEF REQUEST FOR SYSTEM PRESSURE TEST EXAMINATIONS ON CLASS 1 COMPONENT PRESSURE BOUNDARIES (TAC NO. ME2418)

Dear Mr. Freeman:

By letter dated October 15,2010 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML102350341), the Nuclear Regulatory Commission staff authorized an alternative to the requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI for Seabrook Station, Unit No. 1 (Seabrook). The purpose of this letter is to correct the cover letter transmitting this authorization. Specifically, the cover letter incorrectly indicated that this action applied to the third 1O-year interval for Seabrook, while the enclosed SE correctly indicates its applicability to the second 1O-year interval.

If you have any additional questions regarding this matter, I may be reached via telephone at (301) 415-2481.

Sincerely,

/raj G. Edward Miller, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-219 cc: Distribution via ListServ DISTRIBUTION:

Public LPL 1-2 Reading Resource RidsAcrsAcnw_MailCTR Resource RidsNrrPMOysterCreek Resource RidsOgc Resource RidsRgn1 MailCenter Resource RidsNrrLAABaxter Resource RidsNrrDorlLpl1-2 Resource RidsNrrDorlDprResource GMiller, EDOR1 ADAMS Accession Number: ML102920019 *via e-mail OFFICE LPLI-2/PM LPLI-2/LA LPLI-2/BC NAME GEMiller ABaxter* HChernoff DATE 10/22/2010 10/22/2010 11/05/2010 OFFICIAL RECORD COPY