Initial License Exam, CR JPM Number: S-N-a
ML102230437
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 03/08/2010
From:
NRC/RGN-III
To:
Exelon Generation Co, Exelon Nuclear
References
Download: ML102230437 (74)


Text

Exelon Nuclear Job Performance Measure SHUTDOWN A REACTOR RECIRC PUMP JPM Number: S-N-a Revision Number: 05 Date: 10/09 Developed By:

Instructor Date Approved By:

Facility Representative Date

Job Performance Measure (JPM)

Revision Record (Summary)

Revision 04 Bank JPM.

Revision 05 Revised for 2009 NRC Exam.

S-N-a Page 2 of 9

Job Performance Measure (JPM)

SIMULATOR SETUP INSTRUCTIONS

1. Reset the simulator to IC 10, so that BOTH Recirc Pumps are operating at MINIMUM speed.

NOTE: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.

2. Insert following Malfunctions and/or Remotes:
  • Imf SER0341 ON (drives up annunciator 902-4 E-4, 2A Recirc M-G Temp High).
3. Setup the following Triggers:
  • None.

DOCUMENT PREPARATION

1. Clean copy of DOP 0202-03
2. Clean copy of DOP 0202-04.

S-N-a Page 3 of 9

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 NSO.
2. Annunciator 902-4 E-4 has annunciated due to a high fluid drive oil temperature condition for the 2A Recirc Pump MG Set.

o

3. Temperature is currently at 202 F and rising.

INITIATING CUE

1. The Unit Supervisor has directed you to perform a normal shutdown of the 2A Reactor Recirc Pump in accordance with DOP 0202-04 step G.2, but do NOT isolate it from the reactor.
2. Inform the Unit Supervisor when the task is complete.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluators Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.
  • Denotes critical elements of a critical step.

Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

S-N-a Page 4 of 9

Job Performance Measure (JPM)

JPM Start Time: _________

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT NOTE:

Provide the Examinee with the supplied copy of DOP 0202-03 and DOP 0202-04.

1. Transfer both Recirc Pumps Refers to DOP 0202-03 to to Manual Control. perform actions.
2. Verifies MASTER RECIRC Outer dial in MAN.

FLOW CONTLR, 2-262-22, is in MAN. _____ _____ _____

NOTE:

During performance of the following steps, either A or B pump may be performed in any order.

3. Verifies 2A RECIRC PP Outer dial in BAL.

SPEED CONTLR, 2-262-25A, in BAL. _____ _____ _____

4. Verifies 2B RECIRC PP Outer dial in BAL.

SPEED CONTLRs, 2-262-25B, in BAL. _____ _____ _____

NOTE:

When operating at minimum pump speed, the deviation meters will NOT indicate below the zero (null) point during performance of the following steps:

5. Adjust 2A RECIRC PP Rotates potentiometer both SPEED CONTLR, 2-262-25A, directions and deviation potentiometer to raise AND meter deflects both lower deviation meter above directions. _____ _____ _____

zero point.

6. Adjust 2B RECIRC PP Rotates potentiometer both SPEED CONTLR, 2-262-25B, directions and deviation potentiometer to raise AND meter deflects both lower deviation meter above directions. _____ _____ _____

zero point.

S-N-a Page 5 of 9

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT

7. Adjust 2A RECIRC PP Rotates potentiometer so SPEED CONTLR, 2-262-25A that deviation meter to indicate zero. indicates zero. _____ _____ _____
8. Adjust 2B RECIRC PP Rotates potentiometer so SPEED CONTLR, 2-262-25B that deviation meter to indicate zero. indicates zero. _____ _____ _____
  • 9. Place 2A RECIRC PP Outer dial in MAN.

SPEED CONTLR, 2-262-25A in MAN. _____ _____ _____

  • 10. Place 2B RECIRC PP Outer dial in MAN.

SPEED CONTLR, 2-262-25B in MAN. _____ _____ _____

CUE:

If asked as EO, respond that Seal Purge is in service to the 2A Recirc Pump.

  • 11. Take 2A M G SET DRIVE RED light illuminated.

MOTOR to STOP.

12. Verify 2A Recirc Pump has Is indicated by one or more stopped. of the following:
  • FI 2-260-5A, 2A PP FLOW, lowers to near zero and/or
  • FR 2-260-7, 2A RECIRC PP FLOW (red pen), _____ _____ _____

lowers to near zero and/or

S-N-a Page 6 of 9

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT

  • 13. Close MO 2-202-5A, 2A PP RED light illuminated.

DISCH VLV.

14. Verify 2B Recirc Pump speed Speed indicates ~ 30%.

is approximately 30%.

CUE:

Inform the candidate that 5 minutes have elapsed.

15. Open MO 2-202-5A, 2A PP GREEN light illuminated.

DISCH VLV.

CUE:

If candidate informs that he/she will enter DGP 03-03, inform him/her another NSO will perform.

16. Informs Unit Supervisor task Examinee notifies the Unit is complete. Supervisor.

CUE:

Acknowledge report of task completion.

END JPM Stop Time:_________

S-N-a Page 7 of 9

Job Performance Measure (JPM)

Operators Name:

Job

Title:

RO SRO JPM

Title:

SHUTDOWN A REACTOR RECIRC PUMP Revision Number: 05 JPM Number: S-N-a Task Number and

Title:

202L004, Shutdown the 2A Reactor Recirc Pump K/A Number and Importance: 202001.A4.01 3.7 / 3.7 Suggested Testing Environment: Simulator Actual Testing Environment: Simulator Control Room In-Plant Testing Method: Simulate Alternate Path: Yes No Perform SRO Only: Yes No Time Critical: Yes No Estimated Time to Complete: 12 minutes Actual Time Used: minutes

References:

DOP 0202-03, rev 33 and DOP 0202-04, rev 28 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name (Print):

Evaluators Signature: Date:

S-N-a Page 8 of 9

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 NSO.
2. Annunciator 902-4 E-4 has annunciated due to a high fluid drive oil temperature condition for the 2A Recirc Pump MG Set.

o

3. Temperature is currently at 202 F and rising.

INITIATING CUE

1. The Unit Supervisor has directed you to perform a normal shutdown of the 2A Reactor Recirc Pump in accordance with DOP 0202-04 step G.2, but do NOT isolate it from the reactor.
2. Inform the Unit Supervisor when the task is complete.

S-N-a Page 9 of 9

Exelon Nuclear Job Performance Measure CORE SPRAY - PERFORM PUMP TEST WITH PUMP TRIP JPM Number: S-N-b Revision Number: 04 Date: 10/09 Developed By:

Instructor Date Approved By:

Facility Representative Date

Job Performance Measure (JPM)

Revision Record (Summary)

Revision 03 Bank JPM.

Revision 04 Revised for 2009 NRC Exam.

S-N-b Page 2 of 10

Job Performance Measure (JPM)

SIMULATOR SETUP INSTRUCTIONS

1. Core Spray pump operability surveillance can be performed from any IC with Core Spray in the normal standby lineup NOTE: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.
2. Start the LPCI/CS room cooler fans.
3. Enter the following Expert commands to set up an automatic trigger to trip the Core Spray pump after the test valve is opened:

NOTE:The trigger assignment can be changed to any other available trigger to accommodate running this JPM concurrently with other JPMs.

  • trgset 1 "cssbkppb .and. cslop4b" (Trigger 1 Activates when 2B Core Spray pump is running AND when MO 1402-4B OPEN light turns ON)
  • ior csdtpppb (1 10) trip (After 10 sec, inserts a 2B Core Spray pump trip)
  • ior csdclppb (1 10) off (After 10 sec, inserts a 2B Core Spray pump trip)
  • trgset 2 "(et_array(1) .and. (.not. cssbkppb))"l2 (Trigger 2 Activates when Trigger 1 is active AND when 2B Core Spray pump is NOT running)
  • trg 2 "dor csdtpppb"l2 (Deletes 2B Core Spray pump trip)

DOCUMENT PREPARATION

1. Markup a copy of DOS 1400-05 as complete up through Step I.7. (Ready to start 2B Core Spray Pump per step I.8).

S-N-b Page 3 of 10

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. The Unit 2 Core Spray B Pump operability surveillance is required due to maintenance.
3. The operability surveillance for the 2A Core Spray pump is NOT needed.
4. The system is filled and vented.
5. The required valve operability surveillance has been completed.
6. Vibration data is NOT required.
7. The Unit 2 NLO is standing by in the corner room.
8. The LPCI/Core Spray Room Coolers are running.

INITIATING CUE

1. The Unit Supervisor directs you to perform DOS 1400-05 step I.8 for the 2B Core Spray pump.
2. All applicable Prerequisites have been met.
3. Inform the Unit Supervisor upon completion of step I.8.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

S-N-b Page 4 of 10

Job Performance Measure (JPM)

Information For Evaluators Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.
  • Denotes critical elements of a critical step.

Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

S-N-b Page 5 of 10

Job Performance Measure (JPM)

JPM Start Time: _________

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT NOTE:

Provide Examinee a copy of DOS 1400-05.

1. Verify the following valve line Verifies the following:

up:

  • MO 2-1402-4B Closed
  • Green light illuminated.
  • MO 2-1402-38B Open
  • Green light illuminated.
  • 2-1402-6B Open
  • Green light illuminated.
  • MO 2-1402-25B Closed
  • Green light illuminated.
  • MO 2-1402-3B Open
  • Green light illuminated.
  • 2-1402-40B-SV Closed
  • Directs NLO to Verify 2-1402-40B-SV Closed CUE:

2-1402-40B-SV, INST SV is closed.

NOTE:

The next three (3) actions may be requested to be performed at the same time.

2. Verify 2B CORE SPRAY Contacts NLO to verify 2B MOTOR has adequate CS Motor oil level +0 to -

lubrication. 1/8 inch of the Oil _____ _____ _____

Sightglass Standstill Line.

CUE:

2B Core Spray motor oil level is normal (within +0 to -1/8 inch band).

3. Verify 2B LPCI/CS Room Contacts NLO to verify Cooler is operating properly. proper room cooler operation. _____ _____ _____

CUE:

2B LPCI/CS room cooler is operating normally.

S-N-b Page 6 of 10

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT

4. Direct NLO to open 2-1402- Directs 2-1402-40B-SV 40B-SV and report pressure. Open.

CUE:

When asked, report: 2-1402-40B-SV Inst SV is Open and pressure is 7 psig.

5. Record suction pressure Pressure of 7 psig provided by NLO. recorded on Data Sheet 1.
6. Calculate 2-1402-8B initial DP Calculated:

closed DP.

2-1450-1B ________ psig Minus 2-1402-40B ___7____psig Records 2-1450-1B pressure as 75 psig (+ 5 _____ _____ _____

psig)

CUE:

If examinee requests the above calculation to be verified, sign the verified by line.

If the student informs the SRO that the Core Spray System should be declared inoperable, acknowledge the report.

Pump.

NOTE:

2B Core Spray Pump overcurrent trip malfunction is automatically inserted 10 seconds after the 2-1402-4B valve has dual indication.

  • 8. Open FLOW TEST VLV MO Rotates and holds MO 2-2-1402-4B. 1402-4B Control switch CW to Open. _____ _____ _____

BEGIN ALTERNATE PATH

9. Acknowledge and report Acknowledges alarm and alarm for 2B CS pump trip. makes report.

S-N-b Page 7 of 10

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT CUE:

Acknowledge report.

  • 10. Immediately Close Green light illuminated.

2-1402-4B.

Red light illuminated. _____ _____ _____

CUE:

If examinee enters DOA 6500-10, respond that the assist NSO will execute that procedure.

CUE:

If examinee terminates, or requests permission to terminate the surveillance OR If examinee references the DAN for pump trip and has at least considered the actions to take, then provide the cue:

Terminate the surveillance. Leave the system in the current lineup. Someone else will be assigned to verify the system is restored to normal.

11. Informs Unit Supervisor task Examinee notifies the Unit is complete. Supervisor.

CUE:

Acknowledge report of task completion.

END JPM Stop Time:_________

S-N-b Page 8 of 10

Job Performance Measure (JPM)

Operators Name:

Job

Title:

RO SRO JPM

Title:

CORE SPRAY - PERFORM PUMP TEST WITH PUMP TRIP Revision Number: 04 JPM Number: S-N-b Task Number and

Title:

209L004, Perform a CS pump operability test and determine if the results meet the acceptance criteria as stated in DOS 1400-05 K/A Number and Importance: 209001.A4.01 3.8 / 3.6 Suggested Testing Environment: Simulator Actual Testing Environment: Simulator Control Room In-Plant Testing Method: Simulate Alternate Path: Yes No Perform SRO Only: Yes No Time Critical: Yes No Estimated Time to Complete: 22 minutes Actual Time Used: minutes

References:

DOS 1400-05, rev 39 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name (Print):

Evaluators Signature: Date:

S-N-b Page 9 of 10

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. The Unit 2 Core Spray B Pump operability surveillance is required due to maintenance.
3. The operability surveillance for the 2A Core Spray pump is NOT needed.
4. The system is filled and vented.
5. The required valve operability surveillance has been completed.
6. Vibration data is NOT required.
7. The Unit 2 NLO is standing by in the corner room.
8. The LPCI/Core Spray Room Coolers are running.

INITIATING CUE

1. The Unit Supervisor directs you to perform DOS 1400-05 step I.8 for the 2B Core Spray pump.
2. All applicable Prerequisites have been met.
3. Notify the Unit Supervisor upon completion of step I.8.

S-N-b Page 10 of 10

Exelon Nuclear Job Performance Measure MAIN STEAM - UNISOLATE ONE LINE USING PREFERRED METHOD JPM Number: S-N-c Revision Number: 09 Date: 10/09 Developed By:

Instructor Date Approved By:

Facility Representative Date

Job Performance Measure (JPM)

Revision Record (Summary)

Revision 08 Bank JPM.

Revision 09 Revised for 2009 NRC Exam.

S-N-c Page 2 of 8

Job Performance Measure (JPM)

SIMULATOR SETUP INSTRUCTIONS

1. Reset the simulator to IC 16 (<50% power).

NOTE: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.

2. Power needs to be low enough so that isolating one main steam line will NOT cause a Group 1 high flow isolation.
3. Close D Main Steam Line Isolation Valves:
  • AO-2-203-1D
  • AO-2-203-2D
4. Verify Main Steam Line drain valves closed:
  • MO 2-220-1, 2, 3 & 4
  • MO 2-220-90A, B, C & D
5. Insert following Malfunctions and/or Remotes:
  • None.
6. Setup the following Triggers:
  • None.

DOCUMENT PREPARATION

1. Clean copy of DOP 0250-02.

S-N-c Page 3 of 8

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. Following maintenance work on the AO 2-203-2D MSIV, the D Main Steam Line is ready to be unisolated.

INITIATING CUE

1. The Unit Supervisor has directed you to unisolate the D Main Steam Line in accordance with DOP 0250-02, step G.4.
2. Inform the Unit Supervisor when the task is complete.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluators Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.
  • Denotes critical elements of a critical step.

Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

S-N-c Page 4 of 8

Job Performance Measure (JPM)

JPM Start Time: _________

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT NOTE:

Provide the Examinee with the supplied copy of DOP 0250-02.

1. Reviews procedure to Determines MOs 2-220-1 determine appropriate AND 2-220-2 are available, method. and selects the preferred _____ _____ _____

method.

  • 2. Open MO 2-220-1 RED light illuminated.

(MSL DRN VLV).

  • 3. Open MO 2-220-2 RED light illuminated.

(MSL DRN VLV).

  • 4. Open MO 2-220-3 RED light illuminated.

(MSL DRN VLV) is OPEN.

5. Wait a minimum of 5 minutes. 5 minutes elapsed OR verbal cue received.

CUE:

Inform examinee that 5 minutes has elapsed.

  • 6. Open MO 2-220-90D RED light illuminated.

(MSL DRN VLV to Cond).

7. Wait a minimum of 5 minutes. 5 minutes elapsed OR verbal cue received.

CUE:

Inform examinee that 5 minutes has elapsed.

  • 8. Open AO 2-203-2D GREEN light illuminated.

("D" OUTBOARD MSIV).

S-N-c Page 5 of 8

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT

9. Wait a minimum of 5 minutes, 5 minutes elapsed OR verbal cue received.

CUE:

Inform examinee that 5 minutes has elapsed.

  • 10. Open AO 2-203-1D GREEN light illuminated.

("D" INBOARD MSIV).

11. Close MO 2-220-90D GREEN light illuminated.

(MSL DRN VLV to Cond).

12. Close MO 2-220-1 GREEN light illuminated.

(MSL ISOL DRN VLV).

13. Close MO 2-220-2 GREEN light illuminated.

(MSL DRN VLV).

14. Close MO 2-220-3 GREEN light illuminated.

(MSL DRN VLV).

15. Informs Unit Supervisor task Examinee notifies the Unit is complete. Supervisor.

CUE:

Acknowledge report of task completion.

END JPM Stop Time:_________

S-N-c Page 6 of 8

Job Performance Measure (JPM)

Operators Name:

Job

Title:

RO SRO JPM

Title:

MAIN STEAM - UNISOLATE ONE LINE USING PREFERRED METHOD Revision Number: 09 JPM Number: S-N-c Task Number and

Title:

239L004 Unisolating, One Main Steam Line K/A Number and Importance: 239001.A4.01 4.2 / 4.0 Suggested Testing Environment: Simulator Actual Testing Environment: Simulator Control Room In-Plant Testing Method: Simulate Alternate Path: Yes No Perform SRO Only: Yes No Time Critical: Yes No Estimated Time to Complete: 10 minutes Actual Time Used: minutes

References:

DOP 0250-02, rev 12 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name (Print):

Evaluators Signature: Date:

S-N-c Page 7 of 8

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. Following maintenance work on the AO 2-203-2D MSIV, the D Main Steam Line is ready to be unisolated.

INITIATING CUE

1. The Unit Supervisor has directed you to unisolate the D Main Steam Line in accordance with DOP 0250-02, step G.4.
2. Inform the Unit Supervisor when the task is complete.

S-N-c Page 8 of 8

Exelon Nuclear Job Performance Measure ISO COND - STARTUP, WITH FAILURE OF THE M/U SYSTEM JPM Number: S-N-d Revision Number: 01 Date: 10/09 Developed By:

Instructor Date Approved By:

Facility Representative Date

Job Performance Measure (JPM)

Revision Record (Summary)

Revision 00 Bank JPM.

Revision 01 Revised for 2009 NRC Exam.

S-N-d Page 2 of 9

Job Performance Measure (JPM)

SIMULATOR SETUP INSTRUCTIONS

1. Reset the simulator to any IC.

NOTE: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.

2. Verify the Isolation Condenser is in its normal standby lineup.
3. Ensure 2/3A Clean Demin Pump is operating.
4. Ensure 2/3B Clean Demin Pump is NOT operating.
5. Place 2/3B ISOL CNDR M U PP control switch in PTL.
6. Place a CO tag on the 2/3B ISOL CNDR M U PP control switch.
7. Enter the following Simulator Expert commands which trips the 2/3A Diesel Driven Iso Makeup Pump a few seconds after starting:
  • trgset 1 "wmsdp(1)" { Trigger 1 Activates when 2A IC M-U PP is started}
  • imf wmpmpaf (1 2) { After 2 sec, inserts a trip of 2A IC M-U PP}
8. Verify Reactor Pressure is < 1050 psig.
9. Acknowledge / Reset alarms.

DOCUMENT PREPARATION

1. Clean copy of DOP 1300-03.

S-N-d Page 3 of 9

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. The U2 Isolation Condenser (IC) has been verified in Standby per DOP 1300-01.
3. A pressure transient has occurred which requires the manual initiation of the U2 IC.
4. An NLO is in the field to monitor operation of the U2 IC Makeup Pump.
5. 2/3B ISOL CNDR M U PP is OOS for pump replacement.
6. The time of IC initiation in Unit 2 Reactor Log Book will be recorded by another NSO.

INITIATING CUE

1. The Unit Supervisor has directed you to startup the U2 Isolation Condenser to full flow per DOP 1300-03 Step G.4.
2. Hard Cards are NOT authorized.
3. Inform the Unit Supervisor when the task is complete.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluators Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.
  • Denotes critical elements of a critical step.

Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

S-N-d Page 4 of 9

Job Performance Measure (JPM)

JPM Start Time: _________

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT NOTE:

Provide the examinee with the supplied copy of DOP 1300-03.

  • 1. Place AO 2-1301-17 AO Both RED lights 2-1301-20, VENT VLV, illuminated.

control switch in CLOSE and _____ _____ _____

verify closed.

2. Rotate RX INLET ISOL VLV Places switch to HAND HAND/RESET to HAND. position and releases.
3. Verify annunciator 902-3 B-4, Annunciator 902-3 B-4, ISOL CONDR VLVS OFF ISOL CONDR VLVS OFF NORMAL, alarms. NORMAL illuminated. _____ _____ _____
  • 4. Open AND throttle RED light illuminated.

MO 2-1301-3, RX INLET ISOL, as necessary. _____ _____ _____

5. Monitor IC shell level using Pointer in normal GREEN ISOL CONDR LVL, LI band.

2-1340-2, on Panel 902-3. _____ _____ _____

CUE:

If contacted as Makeup Demin Control Room, report the Dilution Pumps are NOT operating.

6. Open MO 2-4399-74, CLEAN RED light illuminated.

DEMIN VLV.

7. Start 2/3A ISOL CNDR M-U RED Light illuminated.

PP.

NOTE:

2/3A ISOL CNDR M U PP will trip a few seconds after starting, due to a malfunction inserted in setup.

S-N-d Page 5 of 9

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT BEGIN ALTERNATE PATH

  • 8. Directs NLO to close Directs NLO to close the 2-4399-756, 2/3 ISOL CDSR valve.

CLEAN DEMIN MAKEUP SYS DISCH HDR TO U2 ISOL CDSR ISOL VLV.

CUE:

2-4399-756, ISOL CDSR CLEAN DEMIN M/U SYS DISCH HDR TO U2 ISOL CDSR ISOL VLV is closed.

  • 9. Starts 2/3B CLEAN DEMIN BLUE light illuminated.

water Pump.

  • 10. Directs NLO to unlock and Directs NLO to unlock and open 2-4399-72, U2 ISOL open the valve.

CDSR CLEAN DEMIN WTR _____ _____ _____

SUPPLY.

CUE:

2-4399-72, U2 ISOL CDSR CLEAN DEMIN WTR SUPPLY valve is unlocked and open.

NOTE:

IC level requires a long time for level to increase.

11. Cycle MO 2-4399-74, CLEAN Maintains level in green DEMIN VALVE, as needed to band.

maintain LI 2-1340-2, ISOL _____ _____ _____

CONDR LVL, in green band.

CUE:

Inform examinee that another NSO will now assume duties for the IC.

12. Informs Unit Supervisor the Examinee notifies the Unit Iso Cond Makeup Pumps did Supervisor.

NOT start and is currently maintaining IC level with the _____ _____ _____

Clean Demin valves and that the task is complete CUE:

Acknowledge report of task completion.

S-N-d Page 6 of 9

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT END JPM Stop Time:_________

S-N-d Page 7 of 9

Job Performance Measure (JPM)

Operators Name:

Job

Title:

RO SRO JPM

Title:

ISO COND - Startup, With Failure Of The M/U System Revision Number: 01 JPM Number: S-N-d Task Number and

Title:

DRE207LN008, Given a set of conditions, analyze the conditions and determine the corrective actions required to return the Isolation Condenser to a stable condition. .

K/A Number and Importance: 207000.A4.01 3.7 / 3.8 Suggested Testing Environment: Simulator Actual Testing Environment: Simulator Control Room In-Plant Testing Method: Simulate Alternate Path: Yes No Perform SRO Only: Yes No Time Critical: Yes No Estimated Time to Complete: 15 minutes Actual Time Used: minutes

References:

DOP 1300-03, rev 29 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name (Print):

Evaluators Signature: Date:

S-N-d Page 8 of 9

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. The U2 Isolation Condenser (IC) has been verified in Standby per DOP 1300-01.
3. A pressure transient has occurred which requires the manual initiation of the U2 IC.
4. An NLO is in the field to monitor operation of the U2 IC Makeup Pump.
5. 2/3B ISOL CNDR M U PP is OOS for pump replacement.
6. The time of IC initiation in Unit 2 Reactor Log Book will be recorded by another NSO.

INITIATING CUE

1. The Unit Supervisor has directed you to startup the U2 Isolation Condenser to full flow per DOP 1300-03 Step G.4.
2. Hard Cards are NOT authorized.
3. Inform the Unit Supervisor when the task is complete.

S-N-d Page 9 of 9

Exelon Nuclear Job Performance Measure PCIS - VERIFY GROUP 2 ISOLATION. WITH INCOMPLETE ISOLATION JPM Number: S-N-e Revision Number: 00 Date: 10/09 Developed By:

Instructor Date Approved By:

Facility Representative Date

Job Performance Measure (JPM)

Revision Record (Summary)

Revision 00 Modified for 2009 NRC Exam.

S-N-e Page 2 of 10

Job Performance Measure (JPM)

SIMULATOR SETUP INSTRUCTIONS

1. Reset the simulator to any shutdown IC.

NOTE: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.

2. Insert a spurious Group 3 isolation.
3. Manually OPEN the following valves (ensure can be re-closed):
  • MO 2-205-24
  • AO 2-1599-61
  • AO 2-1599-62
4. Insert following Malfunctions and/or Remotes:
  • None.
5. Setup the following Triggers:
  • None.

DOCUMENT PREPARATION

1. Clean copy of DAN 902-5 E-5 Hard Card.

S-N-e Page 3 of 10

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. A spurious Group 2 isolation has occurred.

INITIATING CUE

1. The Unit Supervisor has directed you to verify the Group 2 isolation is complete, utilizing the hard card.
2. Inform the Unit Supervisor when the task is complete.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluators Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.
  • Denotes critical elements of a critical step.

Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

S-N-e Page 4 of 10

Job Performance Measure (JPM)

JPM Start Time: _________

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT NOTE:

Examinee should locate the hard card, then provide the included copy.

The following steps may be performed in any order.

1. On the 902-3 panel, verifies the following valves closed:
  • AO 2-8501-3A
  • RED light illuminated.
  • AO 2-8501-1A
  • RED light illuminated.
  • AO 2-8501-5A
  • RED light illuminated.
  • AO 2-8501-3B
  • RED light illuminated.
  • AO 2-8501-1B
  • RED light illuminated.
  • AO 2-8501-5B
  • RED light illuminated.
  • AO 2-9205A
  • RED light illuminated.
  • AO 2-9206A
  • RED light illuminated.
  • AO 2-9207A
  • RED light illuminated.
  • AO 2-9208A
  • RED light illuminated.
  • AO 2-9205B
  • RED light illuminated.
  • AO 2-9206B
  • RED light illuminated.
  • AO 2-9207B
  • RED light illuminated. _____ _____ _____
  • AO 2-9208B
  • RED light illuminated.

S-N-e Page 5 of 10

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT

2. On the 902-3 panel, verifies the following valves closed:
  • AO 2-1601-55
  • RED light illuminated.
  • AO 2-1601-22
  • GREEN light illuminated.
  • AO 2-1601-21
  • GREEN light illuminated.
  • AO 2-1601-56
  • RED light illuminated.
  • MO 2-1601-57
  • RED light illuminated.
  • AO 2-1601-59
  • RED light illuminated.
  • AO 2-1601-58
  • GREEN light illuminated.
  • AO 2-1601-63
  • GREEN light illuminated.
  • AO 2-1601-62
  • GREEN light illuminated.
  • AO 2(3) 1601 23
  • GREEN light illuminated.
  • AO 2(3) 1601 24
  • GREEN light illuminated.
  • AO 2(3) 1601 61
  • GREEN light illuminated.
  • AO 2(3) 1601 60
  • GREEN light illuminated.
3. On the 902-13 panel, verifies the following valves closed and components tripped:
  • TIPS withdraw
  • WHITE in-shield lights illuminated.
  • TIP Ball Valves Close _____ _____ _____
  • RED lights extinguished.
4. On the 902-4 panel, verifies the following valves closed:
  • AO 2-2001-105
  • GREEN light illuminated.
  • AO 2-2001-106
  • GREEN light illuminated.
  • AO 2-2001-5
  • GREEN light illuminated.
  • AO 2-2001-6
  • GREEN light illuminated.

S-N-e Page 6 of 10

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT BEGIN ALTERNATE PATH

  • 5. On the 902-4 panel, verifies Examinee recognizes that the following valves closed: the following did NOT close:
  • MO 2-205-24
  • MO 2-205-24 _____ _____ _____
  • 6. Examinee CLOSES: Takes manual action for failed auto action by placing the following in the CLOSED position: _____ _____ _____
  • MO 2-205-24
  • MO 2-205-24
  • 7. On the 902-6 panel, verifies Examinee recognizes that the following valves closed: the following did NOT close:
  • AO 2-1599-61
  • AO 2-1599-61
  • AO 2-1599-62 _____ _____ _____
  • AO 2-1599-62
  • 8. Examinee CLOSES both: Takes manual action for failed auto action by placing the following in the CLOSED position:
  • AO 2-1599-61
  • AO 2-1599-61 _____ _____ _____
  • AO 2-1599-62.
  • AO 2-1599-62
9. On the 923-4 panel, verifies the following components tripped:
  • GREEN light illuminated.
  • GREEN light illuminated. _____ _____ _____

Pumps Trip S-N-e Page 7 of 10

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT

10. On the 923-4 panel, verifies the following valves closed:
  • AO 2 & 3 5741A
  • RED light illuminated.
  • AO 2 & 3 5741B
  • RED light illuminated.
  • AO 2 & 3 5742A
  • RED light illuminated.
  • AO 2 & 3 5742B
  • RED light illuminated.
11. On the 923-4 panel, verifies the following tripped and started:
  • 2 and 3A, B, & C
  • GREEN lights RBX Vent Fans Trip illuminated.
  • 2 and 3A, B, & C
  • GREEN lights RBX Exh Fans Trip illuminated.
  • 2 and 3A & B Drywell &
  • GREEN lights Torus Purge Fans for both illuminated.

Unit 2 and Unit 3 Trip

  • SBGT Auto Start _____ _____ _____
  • RED lights illuminated for 2/3A train.
12. Informs Unit Supervisor task Reports Group 2 complete is complete. and the following failed to close automatically.
  • MO 2-205-24
  • AO 2-1599-61
  • AO 2-1599-62 CUE:

Acknowledge report of task completion.

END JPM Stop Time:_________

S-N-e Page 8 of 10

Job Performance Measure (JPM)

Operators Name:

Job

Title:

RO SRO JPM

Title:

PCIS - Verify Group 2 Isolation, With Incomplete Isolation Revision Number: 00 JPM Number: S-N-e Task Number and

Title:

295L022, Initiate/Verify automatic actuations of Emergency Systems.

K/A Number and Importance: 223002.A4.01 3.6 / 3.5 Suggested Testing Environment: Simulator Actual Testing Environment: Simulator Control Room In-Plant Testing Method: Simulate Alternate Path: Yes No Perform SRO Only: Yes No Time Critical: Yes No Estimated Time to Complete: 15 minutes Actual Time Used: minutes

References:

DAN 902-5 E-5 hardcard, rev 31 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name (Print):

Evaluators Signature: Date:

S-N-e Page 9 of 10

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. A spurious Group 2 isolation has occurred.

INITIATING CUE

1. The Unit Supervisor has directed you to verify the Group 2 isolation is complete, utilizing the hard card.
2. Inform the Unit Supervisor when the task is complete.

S-N-e Page 10 of 10

Exelon Nuclear Job Performance Measure EDG - PERFORM SURVEILLANCE TESTING, WITH SCRAM JPM Number: S-N-f Revision Number: 02 Date: 10/09 Developed By:

Instructor Date Approved By:

Facility Representative Date

Job Performance Measure (JPM)

Revision Record (Summary)

Revision 01 Bank JPM.

Revision 02 Revised for 2009 NRC Exam.

S-N-f Page 2 of 9

Job Performance Measure (JPM)

SIMULATOR SETUP INSTRUCTIONS

1. Reset the simulator to any IC 12.

NOTE: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.

2. U2 Diesel Generator should be started and loaded to Bus 24-1, per DOS 6600-01 up to and including step I.12. (inclusive).
3. Insert following Malfunctions and/or Remotes:
  • IRF T02 = TRUE (Set Diesel Generator 2 droop to 55).
4. Acknowledge all applicable alarms (locally and on the 902-8 panel).
5. Setup the following remote functions set to triggers, for when directed by examinee:
  • IRF T02 = FALSE (When directed by examinee to set droop to 5).
  • IRF T20 = ACKNOWLEDGE (A few seconds after the droop has been set to 55 acknowledges U2 D/G Local Panel Trouble Alarms).

DOCUMENT PREPARATION

1. Marked up copy of DOS 6600-01, up to and including step I.14.

S-N-f Page 3 of 9

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. DOS 6600-01 is in progress on the Unit 2 Diesel Generator, which is currently paralleled and loaded to Bus 24-1.
3. The surveillance run will be completed in approximately 5 minutes.
4. The operator performing the surveillance in the control room had to leave for an urgent family emergency.
5. An EO is in the field, with the appropriate portions of DOS 6600-01 (pages 46 - 71)

INITIATING CUE

1. The Unit Supervisor has directed you to review Sections F. and G. of DOS 6600-01 and then complete the procedure, starting at step I.15. to secure the Unit 2 Diesel Generator.
2. Inform the Unit Supervisor when the task is complete.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluators Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.
  • Denotes critical elements of a critical step.

Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

S-N-f Page 4 of 9

Job Performance Measure (JPM)

JPM Start Time: _________

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT NOTE:

Provide the Examinee with the supplied copy of DOS 6600-01.

1. Verifies Chemistry Asks if Chemistry Department has completed all Department has completed required samples per CY-DR- all required samples per _____ _____ _____

120-413. CY-DR-120-413.

CUE:

All required samples have been completed.

2. Verifies the fuel oil transfer Asks if the fuel oil transfer pump has recharged the day pump has recharged the tank at least once during the day tank at least once _____ _____ _____

engine run. during the engine run.

CUE:

The day tank level is in the normal band and has been recharged during the engine run.

3. Data Sheet 1 complete. Asks if Data Sheet complete.

CUE:

Data sheet 1 is complete.

4. Reduce U2 DG load Places the U2 DG Governor c/s to DECR to reduce load until less than _____ _____ _____

100 kW.

BEGIN ALTERNATE PATH CUE:

As soon as the examinee begins to reduce load, announce:

UNIT 2 HAS JUST SCRAMMED.

S-N-f Page 5 of 9

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT

5. Proceed to Attachment A. Recognizes need to perform Attachment A.
  • 6. Open circuit breaker U2 D/G Green light illuminated.

TO BUS 24-1 ACB.

7. Records time of Circuit Records time of Circuit Breaker opening. Breaker opening on attachment A. _____ _____ _____
  • 8. Set droop setting to 5. Directs EO to set 2 DG Droop to 5.

NOTE:

If requested to set droop to 5, signal Sim Op to insert remote function (T02 = FALSE)

If requested to reset local annunciators, signal Sim Op to insert remote function (T20 =

ACKNOWLEDGE)

9. Reset annunciator D/G 2 C-1 Directs EO to reset local Droop not set on 5. annunciator C-1 on local panel A.

CUE:

The droop set at 5. Received local alarm and have acknowledged it.

10. Reset annunciator 902-8 A-7 Annunciator 902-8 A-7 U2 DIESEL GEN TROUBLE alarm tile extinguished.

alarm. _____ _____ _____

  • 11. Adjust D/G frequency to 60 Adjusts frequency to 60 Hz Hz. with Governor Control switch. _____ _____ _____
  • 12. Adjust the D/G voltage to Adjusts voltage to 4160 4160. volts with VOLTAGE REGULATOR control. _____ _____ _____

S-N-f Page 6 of 9

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT

13. Informs Unit Supervisor that Examinee notifies the Unit the D/G is running following Supervisor.

the scram and the task is _____ _____ _____

complete.

CUE:

Acknowledge report of task completion.

END JPM Stop Time:_________

S-N-f Page 7 of 9

Job Performance Measure (JPM)

Operators Name:

Job

Title:

RO SRO JPM

Title:

EDG - PERFORM SURVEILLANCE TESTING, WITH SCRAM Revision Number: 02 JPM Number: S-N-f Task Number and

Title:

264L009 Perform DG Surveillance Testing K/A Number and Importance: 264000.A4.05 3.6 / 3.7 Suggested Testing Environment: Simulator Actual Testing Environment: Simulator Control Room In-Plant Testing Method: Simulate Alternate Path: Yes No Perform SRO Only: Yes No Time Critical: Yes No Estimated Time to Complete: 15 minutes Actual Time Used: minutes

References:

DOS 6600-01, rev 110 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name (Print):

Evaluators Signature: Date:

S-N-f Page 8 of 9

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. DOS 6600-01 is in progress on the Unit 2 Diesel Generator, which is currently paralleled and loaded to Bus 24-1.
3. The surveillance run will be completed in approximately 5 minutes.
4. The operator performing the surveillance in the control room had to leave for an urgent family emergency.
5. An EO is in the field, with the appropriate portions of DOS 6600-01 (pages 46

- 71)

INITIATING CUE

1. The Unit Supervisor has directed you to review Sections F. and G. of DOS 6600-01 and then complete the procedure, starting at step I.15. to secure the Unit 2 Diesel Generator.
2. Inform the Unit Supervisor when the task is complete.

S-N-f Page 9 of 9

Exelon Nuclear Job Performance Measure TIPS - PERFORM TIP TEST IN MANUAL MODE JPM Number: S-N-g Revision Number: 00 Date: 10/09 Developed By:

Instructor Date Approved By:

Facility Representative Date

Job Performance Measure (JPM)

Revision Record (Summary)

Revision 00 New JPM developed for 2009 NRC Exam.

S-N-g Page 2 of 10

Job Performance Measure (JPM)

SIMULATOR SETUP INSTRUCTIONS

1. Reset the simulator to IC 12.

NOTE: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.

2. Insert following Malfunctions and/or Remotes:
  • None.
3. Setup the following Triggers:
  • None.

DOCUMENT PREPARATION

1. Clean copy of DOP 0700-06.

S-N-g Page 3 of 10

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. Due to post maintenance testing, TIP Channel 4 (LPRM 32-57) needs to be tested.
3. The portable X-Y plotter will NOT be used.
4. The TIP trace will NOT be run in conjunction with a DTS.
5. Transfer of data to the process computer is NOT desired.
6. The Radiation Protection Department has been notified of the pending evolution.
7. All personnel are clear of TIP room, Shield Chamber, Index Machine and CRD areas.

INITIATING CUE

1. The Unit Supervisor has directed you to perform TIP System Operation in MANUAL MODE, per DOP 0700-06, step G.2, for TIP Channel 4 (LPRM 32-57).
2. Inform the Unit Supervisor when the detector reaches the TOP CORE LIMIT.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluators Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.
  • Denotes critical elements of a critical step.

Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

S-N-g Page 4 of 10

Job Performance Measure (JPM)

JPM Start Time: _________

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT NOTE:

Provide the Examinee with the supplied copy of DOP 0700-06.

1. Verify all BALL VALVES WHITE lights illuminated.

closed at 902-13 panel:

2. Locate the DRIVE CONTROL All operations are CH A. performed on the DRIVE CH A chassis. _____ _____ _____
  • 3. Place MODE switch in MAN. In-Shield WHITE light illuminated.
  • 4. Place MAN. VALVE Switch in OPEN position.

CONTROL in OPEN.

NOTE:

The next step is a channel check and will not produce any result.

5. At VLV CONTROL CH 1, RED light illuminates.

(2,3,4,5) verify BALL VALVE OPEN light is illuminated. _____ _____ _____

6. Place MANUAL switch in Switch in REV position.

REV.

7. Place MANUAL switch in Switch in OFF position.

OFF.

S-N-g Page 5 of 10

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT

  • 8. Turn CHANNEL switch Switch in CHANNEL 4 clockwise to channel 4 position.

(LPRM 32-57) location. _____ _____ _____

9. Verify READY light lit. WHITE light illuminated.
10. Place CORE LIMIT selector Switch in TOP position.

in TOP.

11. Verify CORE LIMIT display A digital number displayed produces a digit symbol in in all four windows.

each digit window. _____ _____ _____

12. Place CORE LIMIT selector Switch in BOTTOM in BOTTOM. position.
13. Verify CORE LIMIT display A digital number displayed produces a digit symbol in in all four windows.

each digit window. _____ _____ _____

14. Verify DETECTOR A digital number displayed POSITION display produces in all four windows.

a digit symbol in each digit _____ _____ _____

window.

15. Verify CORE LIMIT switch in Switch in BOTTOM BOTTOM position. position.
  • 16. At DRIVE CONTROL CH A, Numbers rise toward 0001.

place MANUAL switch in FWD to start TIP detector insertion and verify DETECTOR POSITION rises from the IN-SHIELD position _____ _____ _____

toward 0001 in slow speed.

NOTE:

For the next step, it is acceptable for the digital numbers exceed 0001.

S-N-g Page 6 of 10

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT

  • 17. WHEN DETECTOR Numbers stop rising.

POSITION indicates 0001, THEN place MANUAL switch in OFF. _____ _____ _____

18. Verify READY light is lit. WHITE light is illuminated.
19. Place CORE LIMIT selector Switch in TOP position.

in TOP.

20. Verify CORE LIMIT display Digital number displayed of produces a digit symbol in ~1510.

each window. _____ _____ _____

21. Place CORE LIMIT selector Switch in BOTTOM in BOTTOM. position.
22. Verify CORE LIMIT display Digital number displayed of produces a digit symbol in ~1377.

each window. _____ _____ _____

  • 23. Place MANUAL switch on the Numbers rise at a slow applicable DRIVE CONTROL rate.

in FWD to start detector insertion and verify DETECTOR POSITION indication rises from _____ _____ _____

Position 0001 in slow speed.

24. WHEN detector passes Numbers rise at a faster approximately Position 0024, rate.

THEN verify detector shifts to _____ _____ _____

fast speed.

25. WHEN detector reaches Numbers rise at a slow BOTTOM CORE LIMIT, rate.

THEN Verify detector shifts to _____ _____ _____

slow speed.

TOP.

S-N-g Page 7 of 10

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT

27. WHEN the detector reaches Switch in OFF position.

the TOP CORE LIMIT, THEN Place MANUAL switch in _____ _____ _____

OFF.

CUE:

Inform the examinee that another Operator will continue this evolution.

28. Informs Unit Supervisor task is complete.

CUE:

Acknowledge report of task completion.

END JPM Stop Time:_________

S-N-g Page 8 of 10

Job Performance Measure (JPM)

Operators Name:

Job

Title:

RO SRO JPM

Title:

TIPS - PERFORM TIP TEST IN MANUAL MODE Revision Number: 00 JPM Number: S-N-g Task Number and

Title:

21501LP002, Given plant conditions which require a TIP trace, run a TIP trace in the manual mode of operation.

K/A Number and Importance: 215001.A4.03 3.0 / 3.1 Suggested Testing Environment: Simulator Actual Testing Environment: Simulator Control Room In-Plant Testing Method: Simulate Alternate Path: Yes No Perform SRO Only: Yes No Time Critical: Yes No Estimated Time to Complete: 20 minutes Actual Time Used: minutes

References:

DOP 0700-06, rev 26 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name (Print):

Evaluators Signature: Date:

S-N-g Page 9 of 10

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. Due to post maintenance testing, TIP Channel 4 (LPRM 32-57) needs to be tested.
3. The portable X-Y plotter will NOT be used.
4. The TIP trace will NOT be run in conjunction with a DTS.
5. Transfer of data to the process computer is NOT desired.
6. The Radiation Protection Department has been notified of the pending evolution.
7. All personnel are clear of TIP room, Shield Chamber, Index Machine and CRD areas.

INITIATING CUE

1. The Unit Supervisor has directed you to perform TIP System Operation in MANUAL MODE, per DOP 0700-06, step G.2, for TIP Channel 4 (LPRM 32-57).
2. Inform the Unit Supervisor when the detector reaches the TOP CORE LIMIT.

S-N-g Page 10 of 10

Exelon Nuclear Job Performance Measure SBGT - POST MAINTENANCE TESTING, WITH AUTO INITIATION JPM Number: S-N-h Revision Number: 08 Date: 10/09 Developed By:

Instructor Date Approved By:

Facility Representative Date

Job Performance Measure (JPM)

Revision Record (Summary)

Revision 07 Bank JPM.

Revision 08 Revised for 2009 NRC Exam.

S-N-h Page 2 of 9

Job Performance Measure (JPM)

SIMULATOR SETUP INSTRUCTIONS

1. Reset the simulator to any low power IC with Reactor Building ventilation operating in a NORMAL lineup.

NOTE: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.

2. Ensure the 2/3A SBGT train is in STBY and the 2/3B SBGT train is in PRI.
3. Place control switches for Unit 2 and 3 DW and Torus Purge fans in PTL on 923-5 panel.
4. Insert following Malfunctions and/or Remotes:
  • Trg 1 "vgdstrta" (Causes Trigger 1 to activate when 2/3 SBGT control switch is place to START)
  • Imf radrbdah (1 45)

(fails A channel reactor building vent monitor high, to cause a Group II isolation 45 sec. after 2/3A SBGT switch is placed to START).

5. Setup the following Triggers:
  • None.

DOCUMENT PREPARATION

1. Marked up copy of DOS 7500-02, up to and including step E.7.

S-N-h Page 3 of 9

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. Maintenance has been completed on 2/3 A SBGT train and the train is back in service.
3. The prerequisites of DOS 7500-02 have been completed.
4. IST testing is NOT required
5. Valve timing is NOT required.
6. No painting OR propane equipment operation has happened in the last 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
7. The Initial Cumulative Run Time has been recorded.

INITIATING CUE

1. The Unit 2 Supervisor has directed you to perform DOS 7500-02 for the 2/3A SBGT train for post maintenance testing.
2. Notify the Unit 2 Supervisor when the task is complete.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluators Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.
  • Denotes critical elements of a critical step.

Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

S-N-h Page 4 of 9

Job Performance Measure (JPM)

JPM Start Time: _________

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT NOTE:

Provide the examinee with the provided copy of DOS 7500-02.

1. Ensure the following: Correctly verifies:
  • 2/3 A and B AIR
  • GREEN lights HEATERs are OFF. illuminated.
  • 2/3 A and B Fans are
  • GREEN lights OFF. illuminated.
2. Verifies the following Correctly verifies:

annunciators are NOT in alarm:

  • NOT illuminated.
  • 923-5 A-6, STBY GAS TRT SYS A TROUBLE
  • 923-5 B-6, STBY GAS
  • NOT illuminated.

TRT SYS B TROUBLE _____ _____ _____

  • 3. Verify "B" SBGT SELECT Places 2/3 B SBGT SWITCH in B STBY position. SELECT switch in B STBY. _____ _____ _____
  • 4. Place 2/3 "A" SBGT SELECT Places the 2/3 "A" SBGT SWITCH to START A SELECT SWITCH to position. START A. _____ ____ _____

NOTE:

The Initial Run Time data has already been recorded. (in the initial cues).

5. Records the Initial Run Time Verifies the Initial Run data for SBGT Train "A" on Time data for SBGT Checklist 1. Train "A" on Checklist 1. _____ _____ _____

NOTE:

45 sec. after the 2/3A SBGT control switch is placed to START, a malfunction is automatically inserted to cause a Reactor Building Hi-Hi Rad condition (auto start signal for SBGT).

Depending on speed of candidate, the following step may or may NOT be completed prior to the malfunction being inserted.

S-N-h Page 5 of 9

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT

6. Verifies the 2/3A SBGT train Verifies the 2/3A SBGT initiated properly. train is initiated properly. _____ _____ _____

NOTE:

When Reactor Building Hi-Hi rad signal is received, the examinee should recognize the need to perform the required Limitation and Action steps (which may be performed in any order).

CUE:

When Reactor Building Isolates (alarm 902-3 F-14), provide the following cue:

Attention for an update, Reactor Building Vent Channel A Rad Hi-Hi alarm received BEGIN ALTERNATE PATH

  • 7. Place the SELECT SWITCH Places the SELECT for the non-running train to SWITCH for "B" SBGT PRI. train to PRI. _____ ____ _____
  • 8. Place the control switch for Places the control switch the train under test to OFF. for "A" SBGT train to OFF. _____ _____ _____
9. Verify train in PRI has Nominally ~4000 scfm.

sufficient flow and the heater is operating. _____ ____ _____

10. Place the Train previously Places the control switch under test to STBY. for "A" SBGT train to STBY. _____ _____ _____

S-N-h Page 6 of 9

Job Performance Measure (JPM)

UNSAT Comment PERFORMANCE CHECKLIST STANDARDS SAT

11. Verifies a Reactor Building Verifies:

Isolation has occurred on Panel 923-4, verifying the following:

  • Trip of both units Reactor Building Vent Fans
  • RED lights illuminated.

(Panel 923-5)

  • Trip of both units Reactor Building Exhaust Fans
  • RED lights illuminated.

(Panel 923-5)

  • Trip of both units Drywell
  • RED lights illuminated.

and Torus Purge Fans (Panel 923-5)

  • Closure of both units
  • RED lights illuminated.

Reactor Building Ventilation Isolation Dampers _____ ____ _____

(Panel 923-4)

12. Informs Unit Supervisor task Examinee notifies the Unit is complete. Supervisor. _____ _____ _____

CUE:

Acknowledge report of task completion.

END JPM Stop Time:_________

S-N-h Page 7 of 9

Job Performance Measure (JPM)

Operators Name:

Job

Title:

RO SRO JPM

Title:

SBGT - POST MAINTENANCE TESTING, WITH AUTO INITIATION Revision Number: 08 JPM Number: S-N-h Task Number and

Title:

261L002, Start the SBGT system.

K/A Number and Importance: 261000.A2.13 3.4 / 3.7 Suggested Testing Environment: Simulator Actual Testing Environment: Simulator Control Room In-Plant Testing Method: Simulate Alternate Path: Yes No Perform SRO Only: Yes No Time Critical: Yes No Estimated Time to Complete: 15 minutes Actual Time Used: minutes

References:

DOS 7500-02, rev 46 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name (Print):

Evaluators Signature: Date:

S-N-h Page 8 of 9

Job Performance Measure (JPM)

INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. Maintenance has been completed on 2/3 A SBGT train and the train is back in service.
3. The prerequisites of DOS 7500-02 have been completed.
4. IST testing is NOT required
5. Valve timing is NOT required.
6. No painting OR propane equipment operation has happened in the last 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
7. The Initial Cumulative Run Time has been recorded.

INITIATING CUE

1. The Unit 2 Supervisor has directed you to perform DOS 7500-02 for the 2/3A SBGT train for post maintenance testing.
2. Notify the Unit 2 Supervisor when the task is complete.

S-N-h Page 9 of 9