2/15/2010 Key Milestones Nuclear 2010 Business Plan Overview First Quarter

  • Monti Submit Mella +
  • Monti Successful Completion Instrument Air Vision, Mission, & Values partial turnover Key Initiatives
  • Monti Crane Heavy Load Inspection
  • Monti Successful Operations Accreditation Vision: Work together to provide safe, reliable, and cost Team Visit effective nuclear energy for the communities we serve. Project Performance Stakeholder Predictability
  • Monti EP Full Scale Drill
  • Monti NRC 50.59 Inspection Mission: Foster a learning environment that promotes safe
  • Monti RFO 25 Scope Freeze operations, continually enhances operational performance,
  • PI Load 1 TN-40 Cask promotes accountability for strong financial stewardship and
  • PI Complete First Forging for RSGs demonstrates leadership within the nuclear industry and the Human Performance Outage Performance
  • PI Operations Training Accreditation communities we serve.
  • PI Approve Inst Air Mod scope & budget Values: Maintain a defense in depth strategy to protect
  • PI Complete Phone Replacement employees, the public, and the environment from the inherent
  • Monticello - Improve INPO index - Human Performance & Forced Loss Rate Second Quarter
  • Monticello and Prairie Island -Improve outage preparation & execution
  • Monti Finalize Decision on NFPA 805 or RG nuclear, radiological, environmental, and industrial safety risks
  • Prairie Island - Recover NRC Margin 1.189 associated with operations. Be honest, ethical, and
  • Monti Complete GEZIP installation
  • Monticello - Improve Ops crew performance & process fundamentals accountable; treating people with respect as we work toward
  • Monti Complete Ops Top 10 Equipment List
  • Prairie Island - Address Leadership Assessment Results our common goals. Paperless Recorders (6)
  • Monti Fabrication of HSMs & DSCs
  • Prairie Island - Reduce Corrective & Elective Maintenance backlogs
  • Monti NRC Triennial Heat Sink Inspection
  • Monticello - Improve Forcing Function effectiveness using industry standards
  • Monticello - Improve Corrective Action Program using rigor and oversight
  • Monti EP Full Scale Drill
  • Monticello - Improve Key Project Management & Resource Allocation
  • Monti Operations Accreditation Board Meeting NRC Findings/Violations
  • Monti CAPX 2020 Install Start (2010 work)

Area Site Target (12 mo. rolling average) Measure

  • PI Complete event free Outage OSHA Recordable Incident Prairie Island 0.36
  • PI Successful 50.59 NRC Inspection 40
  • PI Complete Intake Dredging Rate Monticello 0.30
  • PI Successful Initial NRC License Exam 30
  • PI Complete DD CCL Pump Modification 20 Prairie Island Unit 1 Column 1
  • PI Cask 30-39 Contract TN40 High Burnup Part 71 SER Received 10 NRC ROP Column Prairie Island Unit 2 Column 2 0 Third Quarter 10 10 0 0 10 0 10 10 0 10 0

-1 10 -1 l-1 -1 -1 n- b- ar r- ay n- g- p- ct v- ec Ja Fe M Ap M Ju Ju Au Se O No D Monticello Column 1

  • Monti Implement cross-flow MW Recovery Safety Top Quartile 50th Percentile Prairie Island Monticello
  • Monti RFO 25 WO Planning Complete Prairie Island Unit 1 78.3
  • Monti EP Full Scale Drill
  • Monti AFI Closure Date INPO Prairie Island Unit 2 98.6
  • Monti New License Milestone
  • Monti Successful PI&R Inspection Monticello 96.3
  • PI Complete Q-List Project
  • PI Complete Engineering Calcs (CRIP) for INPO Recovery Path Prairie Island < 55R CDBI Dose
  • PI Successful NRC EP Grade Exercise Monticello < 45R
  • PI R11/R12 installation & Turnover 100 Fourth Quarter Prairie Island Unit 1 85.1%
  • Monti EPU Amendment, Approval, &

95 90 Implementation Annual Capacity Factor Prairie Island Unit 2 91.4%

  • Monti Successful ILT Exams 85
  • Monti Successful LOR Exams 80 Reliability Monticello 97.5%
  • Monti Replace No. 17 250 VDC Battery 75
  • Monti 2010 Paperless Recorders Install (17) 70 Outage Performance- Prairie Island 90% Milestones
  • Monti Successful INPO Mid Cycle FSA Review 65 Milestone Met
  • Monti INPO Review Visit EP Full Scale Drill Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Monticello 90% Milestones
  • Monti NRC Initial Operator License Exam 2009 2010
  • Monti RFO 25 WO Walkdowns Complete Major Project Fleet 90% Milestones
  • Monti Install 125 VDC Battery Charger Monti Actual PI Unit 1 Actual PI Unit 2 Actual Efficiency Site Projects Monticello 90% Milestones
  • PI Load 3 TN-40 Casks Monti Forecast PI Unit 1 Forecast PI Unit 2 Forecast
  • PI ZE Piping Replacement (695 complete)

Site Projects Prairie Island 90% Milestones

  • PI Complete Cold Chem Lab Modification
  • PI Complete WINCDMS Implementation
  • PI Complete Station Air Installation