MONTHYEARML1025100362010-09-0808 September 2010 PIC000001-Christopher I. Grimes Resume ML1025006142010-09-0707 September 2010 NRC000001-Boric Acid Corrosion Guidebook, Revision 1 ML1025006402010-09-0707 September 2010 NRC000030-Revised Policy Statement on the Conduct of Nuclear Power Plant Operations ML1025006382010-09-0707 September 2010 NRC000025-Figures 2 Through Figure 6 ML1025006332010-09-0707 September 2010 NRC000027-The Nature of Safety Cultua Review of Theory and Research ML1024607632010-09-0303 September 2010 NSP000061-SER Section 3.0.4 ML1024607282010-09-0303 September 2010 NSP000050-Revised Prefiled Testimony of Northard/Petersen/Peterson-2009 Corrective Action Program Self-Assessment ML1024607252010-09-0303 September 2010 NSP000041-Revised Prefiled Testimony of Northard/Petersen/Peterson-Performance Recovery Plan ML1024607682010-09-0303 September 2010 NSP000069-NRC December 21, 2007 PI&R Report ML1024607712010-09-0303 September 2010 NSP000070-PINGP Pride Initiative Focus 2010 ML1024606332010-09-0303 September 2010 NSP000035B-Revised Testimony of Northard/Petersen/Peterson-Root Cause Evaluation Report 01157726 ML1024606292010-09-0303 September 2010 NSP000020-Revised Testimony of Northard/Petersen/Peterson-Petersen Resume ML1024606272010-09-0303 September 2010 NSP000035C-Revised Testimony of Northard/Petersen/Peterson-Root Cause Evaluation Report 01157726 ML1024606242010-09-0303 September 2010 NSP000019-Revised Testimony of Northard/Petersen/Peterson-Northard Resume ML1024605692010-09-0303 September 2010 Applicant Revised Exhibit NSP000001-Revised Testimony of Steven Skoyen Resume ML1024605662010-09-0303 September 2010 NSP000017-Revised Testimony of Steven Skoyen-NUREG-1765 Excerpts ML1024605152010-09-0303 September 2010 Northern States Power Co. October 2010 Evidentiary Hearing on Safety Culture Contention, Hearing Exhibits ML1024605512010-09-0303 September 2010 NSP000015-Revised Testimony of Steven Skoyen-EFR 1160372-03 ML1024605522010-09-0303 September 2010 NSP000006-Revised Testimony of Steven Skoyen-2006 AES Letter ML1024605532010-09-0303 September 2010 NSP000010-Revised Testimony of Steven Skoyen-EFR 1160372-04 ML1024605542010-09-0303 September 2010 NSP000008-Revised Testimony of Steven Skoyen-Dominion Evaluation R-4448-00-01 ML1024605552010-09-0303 September 2010 NSP000012-Revised Testimony of Steven Skoyen-EC 15651 ML1024605562010-09-0303 September 2010 2009/09/03-Applicant-Revised Exhibit NSP000003-PINGP License Renewal Application Excerpts ML1024605572010-09-0303 September 2010 NSP000013-Revised Testimony of Steven Skoyen-ACRS Letter ML1024605582010-09-0303 September 2010 NSP000007-Revised Testimony of Steven Skoyen-CAP 1160372 ML1024605592010-09-0303 September 2010 NSP000011-Revised Testimony of Steven Skoyen-EC 15044 ML1024605602010-09-0303 September 2010 NSP000016-Revised Testimony of Steven Skoyen-ACRS July 2009 Meeting Transcript Excerpts ML1024605622010-09-0303 September 2010 Applicant Revised Exhibit NSP000004-Root Cause Evaluation Report 01160372-01 ML1024605632010-09-0303 September 2010 NSP000018-Revised Testimony of Steven Skoyen-CE 01140617-03 ML1024605642010-09-0303 September 2010 NSP000009-Revised Testimony of Steven Skoyen-CE 1233806-2 ML1024605652010-09-0303 September 2010 Applicant Revised Exhibit NSP000002-Schematic Representation of PINGP Containment ML1022504662010-08-13013 August 2010 NRC Staff Exhibit 63 - Boric Acid Corrosion Guidebook, Revision 1: Managing Boric Acid Corrosion Issues at PWR Power Stations EPRI, Palo Alto, CA (2001) 1000975 Pages 4-25 & 4-26 ML1022504702010-08-13013 August 2010 2010/08/13-NRC Staff Exhibit 4A - NUREG-1800 Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants (SRP-LR) (September 2005), (Excerpt) ML1022504772010-08-13013 August 2010 NRC Staff Exhibit List ML1022504962010-08-13013 August 2010 Northard Exhibit 43, Section 3.0.4. of NRC SER ML1022504982010-08-13013 August 2010 Northard Exhibit 48, WM-0491 - Prairie Island Corrective Backlog ML1022505002010-08-13013 August 2010 Skoyen Exhibit 17, NUREG-1765 Excerpt ML1022505082010-08-13013 August 2010 Northard Exhibit 52, Pride Initiative Focus/2010 ML1022505132010-08-13013 August 2010 Skoyen Exhibit 18, CE01140617-03 Potential IWE Non-Compliance ML1022505142010-08-13013 August 2010 Northard Exhibit 42, Event Cross References in 2009 ML1022504952010-08-10010 August 2010 Skoyen Rebuttal Exhibits List ML1022505012010-08-10010 August 2010 List of Northard Rebuttal Exhibits ML1024607592010-08-0606 August 2010 NSP000066-PINGP Corrective Backlog 2010 ML1022504752010-08-0404 August 2010 NRC Staff Exhibit 62 - Summary of July 28, 2010 Public Meeting to Discuss Observations and Lessons Learned During the Pilot Application of the Nuclear Energy Institutes Nuclear Safety Culture Assessment Process (August 4, 2010) ML1021607812010-08-0404 August 2010 Intervenor-Exhibit 21-Xcel Management Review Committee Meeting Summary No. 2010-01, Msrc Meeting Date March 17 and 18, 2010 (NSPM Prod 00000267) ML1021607642010-08-0404 August 2010 Intervenor-Exhibit 1-Resume for Christopher I. Grimes ML1025006752010-08-0404 August 2010 NRC000058-Summary of July 28, 2010 Public Meeting to Discuss Observations and Lessons Learned During the Pilot Application of the Nuclear Energy Institute'S Nuclear Safety Culture Assessment Process (August 4, 2010) ML1021503902010-07-30030 July 2010 Applicant-Northard Exhibit 4-INPO V NRC Nuclear Safety Culture Components ML1021503922010-07-30030 July 2010 Applicant-Northard Exhibit 5 - Nuclear 2010 Business Plan Overview ML1021503932010-07-30030 July 2010 Applicant-Northard Exhibit 10-FP-PA-HU-03, Rev. 6, Human Performance Observation Program. 2010-09-08
[Table view] |
Text
2/15/2010 Key Milestones Nuclear 2010 Business Plan Overview First Quarter
- Monti Successful Completion Instrument Air Vision, Mission, & Values partial turnover Key Initiatives
- Monti Crane Heavy Load Inspection
- Monti Successful Operations Accreditation Vision: Work together to provide safe, reliable, and cost Team Visit effective nuclear energy for the communities we serve. Project Performance Stakeholder Predictability
- Monti EP Full Scale Drill
- Monti NRC 50.59 Inspection Mission: Foster a learning environment that promotes safe
- Monti RFO 25 Scope Freeze operations, continually enhances operational performance,
- PI Load 1 TN-40 Cask promotes accountability for strong financial stewardship and
- PI Complete First Forging for RSGs demonstrates leadership within the nuclear industry and the Human Performance Outage Performance
- PI Operations Training Accreditation communities we serve.
- PI Approve Inst Air Mod scope & budget Values: Maintain a defense in depth strategy to protect
- PI Complete Phone Replacement employees, the public, and the environment from the inherent
- Monticello - Improve INPO index - Human Performance & Forced Loss Rate Second Quarter
- Monticello and Prairie Island -Improve outage preparation & execution
- Monti Finalize Decision on NFPA 805 or RG nuclear, radiological, environmental, and industrial safety risks
- Prairie Island - Recover NRC Margin 1.189 associated with operations. Be honest, ethical, and
- Monti Complete GEZIP installation
- Monticello - Improve Ops crew performance & process fundamentals accountable; treating people with respect as we work toward
- Monti Complete Ops Top 10 Equipment List
- Prairie Island - Address Leadership Assessment Results our common goals. Paperless Recorders (6)
- Monti Fabrication of HSMs & DSCs
- Prairie Island - Reduce Corrective & Elective Maintenance backlogs
- Monti NRC Triennial Heat Sink Inspection
- Monticello - Improve Forcing Function effectiveness using industry standards
- Monticello - Improve Corrective Action Program using rigor and oversight
- Monti EP Full Scale Drill
- Monticello - Improve Key Project Management & Resource Allocation
- Monti Operations Accreditation Board Meeting NRC Findings/Violations
- Monti CAPX 2020 Install Start (2010 work)
Area Site Target (12 mo. rolling average) Measure
- PI Complete event free Outage OSHA Recordable Incident Prairie Island 0.36
- PI Successful 50.59 NRC Inspection 40
- PI Complete Intake Dredging Rate Monticello 0.30
- PI Successful Initial NRC License Exam 30
- PI Complete DD CCL Pump Modification 20 Prairie Island Unit 1 Column 1
- PI Cask 30-39 Contract TN40 High Burnup Part 71 SER Received 10 NRC ROP Column Prairie Island Unit 2 Column 2 0 Third Quarter 10 10 0 0 10 0 10 10 0 10 0
-1 10 -1 l-1 -1 -1 n- b- ar r- ay n- g- p- ct v- ec Ja Fe M Ap M Ju Ju Au Se O No D Monticello Column 1
- Monti Implement cross-flow MW Recovery Safety Top Quartile 50th Percentile Prairie Island Monticello
- Monti RFO 25 WO Planning Complete Prairie Island Unit 1 78.3
- Monti EP Full Scale Drill
- Monti AFI Closure Date INPO Prairie Island Unit 2 98.6
- Monti New License Milestone
- Monti Successful PI&R Inspection Monticello 96.3
- PI Complete Q-List Project
- PI Complete Engineering Calcs (CRIP) for INPO Recovery Path Prairie Island < 55R CDBI Dose
- PI Successful NRC EP Grade Exercise Monticello < 45R
- PI R11/R12 installation & Turnover 100 Fourth Quarter Prairie Island Unit 1 85.1%
- Monti EPU Amendment, Approval, &
95 90 Implementation Annual Capacity Factor Prairie Island Unit 2 91.4%
- Monti Successful ILT Exams 85
- Monti Successful LOR Exams 80 Reliability Monticello 97.5%
- Monti Replace No. 17 250 VDC Battery 75
- Monti 2010 Paperless Recorders Install (17) 70 Outage Performance- Prairie Island 90% Milestones
- Monti Successful INPO Mid Cycle FSA Review 65 Milestone Met
- Monti INPO Review Visit EP Full Scale Drill Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Monticello 90% Milestones
- Monti NRC Initial Operator License Exam 2009 2010
- Monti RFO 25 WO Walkdowns Complete Major Project Fleet 90% Milestones
- Monti Install 125 VDC Battery Charger Monti Actual PI Unit 1 Actual PI Unit 2 Actual Efficiency Site Projects Monticello 90% Milestones
- PI Load 3 TN-40 Casks Monti Forecast PI Unit 1 Forecast PI Unit 2 Forecast
- PI ZE Piping Replacement (695 complete)
Site Projects Prairie Island 90% Milestones
- PI Complete Cold Chem Lab Modification
- PI Complete WINCDMS Implementation
- PI Complete Station Air Installation