ML102150092
ML102150092 | |
Person / Time | |
---|---|
Site: | Salem, Hope Creek ![]() |
Issue date: | 07/20/2010 |
From: | Mulligan P State of NJ, Dept of Environmental Protection |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
Download: ML102150092 (2) | |
Similar Documents at Salem, Hope Creek | |
---|---|
Category:Letter
MONTHYEARIR 05000272/20230042024-02-0505 February 2024
[Table view]Integrated Inspection Report 05000272/2023004 and 05000311/2023004 ML24030A8752024-02-0101 February 2024 Operator Licensing Examination Approval IR 05000354/20230042024-02-0101 February 2024 Integrated Inspection Report 05000354/2023004 ML24009A1022024-01-26026 January 2024 Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 IR 05000354/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000354/2023401 ML23341A1372024-01-16016 January 2024 Issuance of Amendment No. 235 Revise Trip and Standby Auto-Start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection ML23307A1532023-12-15015 December 2023 NRC Investigation Report No. 1-2023-001 ML23335A1122023-12-15015 December 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers LR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023 Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 IR 05000354/20230032023-11-0707 November 2023 Integrated Inspection Report 05000354/2023003 LR-N23-0072, Core Operating Limits Report Cycle 302023-11-0101 November 2023 Core Operating Limits Report Cycle 30 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 LR-N23-0065, Submittal of 2023 Annual 10 CFR 50.46 Report2023-10-0202 October 2023 Submittal of 2023 Annual 10 CFR 50.46 Report LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) IR 05000354/20230052023-08-31031 August 2023 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2023005) ML23233A0762023-08-21021 August 2023 Requalification Program Inspection ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location IR 05000272/20230022023-08-0909 August 2023 Integrated Inspection Report 05000272/2023002 and 05000311/2023002 LR-N23-0055, Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days2023-08-0303 August 2023 Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 IR 05000354/20230102023-08-0303 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000354/2023010 LR-N23-0052, Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers Per Technical Specification 4.6.2.12023-07-31031 July 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers Per Technical Specification 4.6.2.1 LR-N23-0054, In-Service Inspection Activities2023-07-26026 July 2023 In-Service Inspection Activities LR-N23-0042, Spent Fuel Cask Registration2023-07-12012 July 2023 Spent Fuel Cask Registration LR-N23-0046, Emergency Plan Document Revisions Implemented June 28, 20232023-07-10010 July 2023 Emergency Plan Document Revisions Implemented June 28, 2023 LR-N23-0005, License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2023-06-23023 June 2023 License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML23139A1472023-06-0505 June 2023 Relief Request Associated with Fourth Interval In-service Inspection Limited Examinations of Weld Coverage ML23096A1842023-05-0909 May 2023 Issuance of Amendment No. 328 Revise and Relocate Reactor Coolant System Pressure and Temperature Limits and Pressurizer Overpressure Protection System Limits to Pressure and Temperature Limits Report IR 05000272/20230012023-05-0303 May 2023 Integrated Inspection Report 05000272/2023001 and 05000311/2023001 ML23081A4662023-05-0202 May 2023 Issuance of Amendment Nos. 346 and 327 Revise Technical Specifications to Extend Allowable Outage Time for Inoperable Emergency Diesel Generator IR 05000272/20233012023-05-0101 May 2023 Initial Operator Licensing Examination Report 05000272/2023301 and 05000311/2023301 ML23121A1412023-05-0101 May 2023 Senior Reactor and Reactor Operator Initial License Examinations IR 05000354/20230112023-05-0101 May 2023 Commercial Grade Dedication Report 05000354/2023011 LR-N23-0035, 2022 Annual Radioactive Effluent Release Report (ARERR)2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report (ARERR) LR-N23-0034, 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station2023-04-27027 April 2023 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station LR-N23-0033, Core Operating Limits Report Cycle 272023-04-26026 April 2023 Core Operating Limits Report Cycle 27 IR 05000354/20230012023-04-26026 April 2023 Integrated Inspection Report 05000354/2023001 LR-N23-0010, License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location2023-04-21021 April 2023 License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location LR-N23-0009, License Amendment Request (LAR) to Revise the Hope Creek Trip and Standby Auto-start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning (HVAC) Trains2023-04-18018 April 2023 License Amendment Request (LAR) to Revise the Hope Creek Trip and Standby Auto-start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning (HVAC) Trains ML23087A1492023-04-17017 April 2023 NRC to PSEG Salem, Transmittal of the National Marine Fisheries Service'S March 24, 2023, Biological Opinion GAR-2020-02842 Concerning Salem and Hope Creek 2024-02-05 Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50 MONTHYEARLR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023
[Table view]and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary LR-N23-0005, License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2023-06-23023 June 2023 License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML23096A1842023-05-0909 May 2023 Issuance of Amendment No. 328 Revise and Relocate Reactor Coolant System Pressure and Temperature Limits and Pressurizer Overpressure Protection System Limits to Pressure and Temperature Limits Report LR-N23-0010, License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location2023-04-21021 April 2023 License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location LR-N23-0009, License Amendment Request (LAR) to Revise the Hope Creek Trip and Standby Auto-start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning (HVAC) Trains2023-04-18018 April 2023 License Amendment Request (LAR) to Revise the Hope Creek Trip and Standby Auto-start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning (HVAC) Trains LR-N23-0024, Submittal of Hope Creek Generating Station Technical Specification Bases Changes2023-03-29029 March 2023 Submittal of Hope Creek Generating Station Technical Specification Bases Changes LR-N22-0066, License Amendment Request (LAR) to Relocate Technical Specifications (TS) Requirements for Reactor Head Vents to the Technical Requirements Manual (TRM)2022-08-31031 August 2022 License Amendment Request (LAR) to Relocate Technical Specifications (TS) Requirements for Reactor Head Vents to the Technical Requirements Manual (TRM) LR-N22-0012, License Amendment Request to Amend the Technical Specifications to Revise and Relocate the Reactor Coolant System Pressure and Temperature Limits and Pressurizer Overpressure Protection System Limits to a Pressure and Temperature2022-08-0707 August 2022 License Amendment Request to Amend the Technical Specifications to Revise and Relocate the Reactor Coolant System Pressure and Temperature Limits and Pressurizer Overpressure Protection System Limits to a Pressure and Temperature LR-N22-0006, License Amendment Request (LAR) to Amend Salem Unit 1 and Unit 2 Technical Specifications (TS) to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator from 72 Hours to 14 Days2022-06-29029 June 2022 License Amendment Request (LAR) to Amend Salem Unit 1 and Unit 2 Technical Specifications (TS) to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator from 72 Hours to 14 Days LR-N22-0051, License Amendment Request to Relocate Technical Specification Facility/Unit Staff Qualification Requirements to Quality Assurance Topical Report2022-06-22022 June 2022 License Amendment Request to Relocate Technical Specification Facility/Unit Staff Qualification Requirements to Quality Assurance Topical Report ML22061A0302022-04-0404 April 2022 Issuance of Amendment Nos. 343 and 324 Revise Technical Specifications Surveillance Requirements for Auxiliary Feedwater ML21277A1932021-11-16016 November 2021 Enclosure 2, Draft Conforming License Amendments LR-N21-0056, License Amendment Request to Amend the Technical Specifications to Revise Surveillance Requirements for Electric Power Monitor Channels for the Reactor Protection System (RPS) and Power Range Neutron Monitoring System2021-11-0303 November 2021 License Amendment Request to Amend the Technical Specifications to Revise Surveillance Requirements for Electric Power Monitor Channels for the Reactor Protection System (RPS) and Power Range Neutron Monitoring System ML21230A0182021-10-0808 October 2021 Issuance of Amendment No. 339 Revise and Relocate Reactor Coolant System Pressure and Temperature Limits and Pressurizer Overpressure Protection System Limits to Pressure and Temperature Limits Report LR-N21-0065, License Amendment Request - Revision of Salem and Hope Creek Generating Station Technical Specification (TS) to Delete Definitions Found in 10 CFR Part 20 and Delete Figures of the Site and Surrounding Areas from TS2021-09-29029 September 2021 License Amendment Request - Revision of Salem and Hope Creek Generating Station Technical Specification (TS) to Delete Definitions Found in 10 CFR Part 20 and Delete Figures of the Site and Surrounding Areas from TS LR-N21-0048, One-Time License Amendment Request to Revise Unit 2 Technical Specification Action for Rod Position Indicators2021-06-18018 June 2021 One-Time License Amendment Request to Revise Unit 2 Technical Specification Action for Rod Position Indicators LR-N21-0043, Supplement to License Amendment Request to Adopt TSTF-490, Delete Ebar Definition and Revision to RCS Specific Activity Tech Spec2021-06-0909 June 2021 Supplement to License Amendment Request to Adopt TSTF-490, Delete Ebar Definition and Revision to RCS Specific Activity Tech Spec LR-N21-0025, License Amendment Request to Revise Technical Specification Limits for Ultimate Heat Sink2021-05-0707 May 2021 License Amendment Request to Revise Technical Specification Limits for Ultimate Heat Sink RS-21-039, Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments2021-03-25025 March 2021 Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments LR-N21-0026, Supplement to License Amendment Request to Amend the Technical Specifications to Revise and Relocate the Reactor Coolant System Pressure and Temperature Limits and Pressurizer Overpressure Protection System2021-03-17017 March 2021 Supplement to License Amendment Request to Amend the Technical Specifications to Revise and Relocate the Reactor Coolant System Pressure and Temperature Limits and Pressurizer Overpressure Protection System ML21057A2732021-02-25025 February 2021 Application for Order Approving License Transfers and Proposed Conforming License Amendments LR-N21-0006, Application to Revise Technical Specifications to Adopt TSTF-569 Revision of Response Time Testing Definitions2021-02-16016 February 2021 Application to Revise Technical Specifications to Adopt TSTF-569 Revision of Response Time Testing Definitions LR-N20-0060, Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2020-09-29029 September 2020 Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements LR-N20-0003, License Amendment Request to Adopt TSTF-490, Deletion of E-Bar Definition and Revision to RCS Specific Activity Tech Spec2020-09-17017 September 2020 License Amendment Request to Adopt TSTF-490, Deletion of E-Bar Definition and Revision to RCS Specific Activity Tech Spec LR-N20-0051, Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2020-07-21021 July 2020 Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors LR-N20-0027, Supplement to License Amendment Request: Revise Minimum Required Channels, Mode Applicability and Actions for the Source Range and Intermediate Range Neutron Flux Reactor Trip System Instrumentation Technical Specifications2020-05-11011 May 2020 Supplement to License Amendment Request: Revise Minimum Required Channels, Mode Applicability and Actions for the Source Range and Intermediate Range Neutron Flux Reactor Trip System Instrumentation Technical Specifications LR-N20-0010, License Amendment Request to Exclude the Dynamic Effects of Specific Postulated Pipe Ruptures from the Design and Licensing Basis Based on Leak-Before-Break Methodology2020-04-24024 April 2020 License Amendment Request to Exclude the Dynamic Effects of Specific Postulated Pipe Ruptures from the Design and Licensing Basis Based on Leak-Before-Break Methodology LR-N19-0076, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2019-11-25025 November 2019 Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors LR-N19-0055, License Amendment Request: Revise Minimum Required Channels, Mode Applicability and Actions for the Source Range and Intermediate Range Neutron Flux Reactor Trip System Instrumentation Technical Specifications2019-10-23023 October 2019 License Amendment Request: Revise Minimum Required Channels, Mode Applicability and Actions for the Source Range and Intermediate Range Neutron Flux Reactor Trip System Instrumentation Technical Specifications LR-N19-0064, License Amendment Request - Deletion of Facility Operating License Conditions Related to Decommissioning Trust Provisions and License Transfer2019-07-29029 July 2019 License Amendment Request - Deletion of Facility Operating License Conditions Related to Decommissioning Trust Provisions and License Transfer LR-N19-0065, License Amendment Request for Approval of Changes to Emergency Plan Staffing Requirements2019-07-0808 July 2019 License Amendment Request for Approval of Changes to Emergency Plan Staffing Requirements LR-N19-0060, Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2019-06-18018 June 2019 Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program LR-N19-0038, Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR2019-04-22022 April 2019 Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR LR-N19-0004, Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements2019-04-18018 April 2019 Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements LR-N19-0006, Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2019-04-0808 April 2019 Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML19058A2212019-02-27027 February 2019 Application to Revise Technical Specifications to Adopt TSTF-546, Revise APRM Channel Adjustment Surveillance Requirement. LR-N18-0127, Application to Revise Technical Specifications to Adopt TSTF-546, Revise APRM Channel Adjustment Surveillance Requirement.2019-02-27027 February 2019 Application to Revise Technical Specifications to Adopt TSTF-546, Revise APRM Channel Adjustment Surveillance Requirement. LR-N18-0129, License Amendment Request to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements.2019-02-0404 February 2019 License Amendment Request to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements. LR-N18-0116, Response to Request for Additional Information, License Amendment Request: Inverter Allowed Outage Time (AOT) Extension2018-10-30030 October 2018 Response to Request for Additional Information, License Amendment Request: Inverter Allowed Outage Time (AOT) Extension LR-N18-0098, License Amendment Request: Remote Shutdown System2018-10-30030 October 2018 License Amendment Request: Remote Shutdown System LR-N18-0113, Supplement to License Amendment Request: Revise Reactor Trip System Instrumentation, Engineered Safety Feature Actuation System Instrumentation, Main Steam Isolation Valves and Add Main Feedwater Isolation Technical Specification2018-10-27027 October 2018 Supplement to License Amendment Request: Revise Reactor Trip System Instrumentation, Engineered Safety Feature Actuation System Instrumentation, Main Steam Isolation Valves and Add Main Feedwater Isolation Technical Specification LR-N18-0086, Supplemental Information to License Amendment Request (LAR) to Amend the Hope Creek Technical Specifications (TS) to Revise Action for Inoperable Emergency Diesel Generator (EDG) a or 82018-09-26026 September 2018 Supplemental Information to License Amendment Request (LAR) to Amend the Hope Creek Technical Specifications (TS) to Revise Action for Inoperable Emergency Diesel Generator (EDG) a or 8 LR-N17-0144, License Amendment Request: Revise Reactor Trip System Instrumentation, Engineered Safety Feature Actuation System Instrumentation, Main Steam Isolation Valves and Add Main Feedwater Isolation Technical Specification2018-06-29029 June 2018 License Amendment Request: Revise Reactor Trip System Instrumentation, Engineered Safety Feature Actuation System Instrumentation, Main Steam Isolation Valves and Add Main Feedwater Isolation Technical Specification LR-N18-0038, License Amendment Request (LAR) to Amend the Salem Technical Specifications (TS) to Extend the Refueling Water Storage Tank (RWST) Allowed Outage Time2018-06-29029 June 2018 License Amendment Request (LAR) to Amend the Salem Technical Specifications (TS) to Extend the Refueling Water Storage Tank (RWST) Allowed Outage Time LR-N18-0059, Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules2018-06-29029 June 2018 Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules LR-N18-0067, Supplement to License Amendment Request for Vital Instrument Bus Inverter Allowed Outage Time (AOT) Extension2018-06-14014 June 2018 Supplement to License Amendment Request for Vital Instrument Bus Inverter Allowed Outage Time (AOT) Extension ML18136A8662018-05-16016 May 2018 License Amendment Request: Vital Instrument Bus Inverter Allowed Outage Time (AOT) Extension LR-N18-0032, License Amendment Request: Inverter Allowed Outage Time (AOT) Extension2018-04-13013 April 2018 License Amendment Request: Inverter Allowed Outage Time (AOT) Extension LR-N18-0013, License Amendment Request (LAR) to Amend the Hope Creek Technical Specifications (TS) to Revise Action for Inoperable Emergency Diesel Generator (EDG) a or B2018-03-28028 March 2018 License Amendment Request (LAR) to Amend the Hope Creek Technical Specifications (TS) to Revise Action for Inoperable Emergency Diesel Generator (EDG) a or B 2023-09-08 |
Text
State of Neiu Arrs DEPARTMENT OF ENVIRONMENTAL PROTECTION CHRIS CHRISTIE Governor BBMRI Division of Environmental Safety and Health BOB MARTIN Radiation Protection and Release Prevention Element Commissioner KIM GUADAGNO Bureau of Nuclear Engineering Lt. Governor PO Box 415 Trenton, New Jersey 08625-0415 Phone: (609) 984-7700 Fax: (609) 984-7513 July 20, 2010 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Gentlemen:
Subject:
Hope Creek Generating Station (HCGS), Docket No. 50-354 Salem Generating Station (SGS) Units 1 & 2, Dockets No. 50-272 & 311 License Amendment Requests (LAR) H10-02 & S 10-02: "Proposed Revision to Technical Specifications - Removal of Reactor Coolant System Structural Integrity Requirements" PSEG Nuclear LLC (PSEG) submitted the subject amendmentrequest to the Nuclear Regulatory Commission (NRC) on March 25, 2010. The proposed amendment would remove the. reactor coolant system structural integrity requirements from the Technical Specifications (TS) 'of the above stations. As a result, th6 Salem Unit 1 &2 TS surv1ilaihnce requirements'for the augmented inspection of the Reactor Coolant PPlimp (RCP) flywheel wo'uld be relocated to the administrative section of the TS resulting in the establishment of a new TS Program. Hope Creek Generating Station has no augmented inspection requirements.
The New Jersey Department of Envirormenfrt*Protectiorn's Breaiuof Nuclear Engineerinn9 (NJ BNE) reviewed the request in accordance with the reruirements of 10 CFR 50.91(b). We have no c6mments.
If you have any questions, please contact Jerry Humphreys at:(609) 984-7469.
New JerseY is an Equal Opportunit.lEmployer Prited onRecycled Paperand Rec.clable
Sincerely, Patrick Mulligan Manager Bureau of Nuclear Engineering c: P. Baldauf, New Jersey DEP, Assistant Director N. McNamara, NRC Region I State Liaison Officer R. Ennis, NRC Hope Creek Project Manager B. Welling, NRC Senior Resident Inspector, Hope Creek M. Gaffney, PSEG Manager Hope Creek Regulatory Assurance C. Neely, PSEG Director Regulatory Affairs